Coleman v. Pearman

165 S.E. 371, 159 Va. 72, 1932 Va. LEXIS 175
CourtSupreme Court of Virginia
DecidedSeptember 22, 1932
StatusPublished
Cited by15 cases

This text of 165 S.E. 371 (Coleman v. Pearman) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coleman v. Pearman, 165 S.E. 371, 159 Va. 72, 1932 Va. LEXIS 175 (Va. 1932).

Opinion

Hudgins, J.,

delivered the opinion of the court.

The only question involved in this appeal is whether or not the appellants have perfected their respective liens as subcontractors under the mechanics’ lien statutes.

W. J. Pearman, R. A. Covington and L. G. Priddy, appellees, filed a bill in chancery alleging that in August, 1929, they, as owners of a certain parcel of land in the city of Roanoke, made a contract with Roanoke Construction and Lumber Corporation, as general contractor, to erect a building thereon, according to certain plans and specifications, for a sum not to exceed $19,650 on a cost plus basis; that the owners were compelled to complete the building because of the failure of the general contractor and its consequent inability to comply with the terms of the contract; that a final settlement with the general contractor showed that the owners had overpaid it in the sum of $1,022.75; that H. L. Coleman, Stone Tile and Supply Co., Inc., Adams, Payne and Gleaves, Inc., and J. W. Hodges, trading as Joseph W. Hodges and Sons, appellants, filed in the clerk’s office for recordation their respective memoranda for mechanics’ liens on forms prescribed for general contractors; that Roanoke Iron and Bridge Works, Inc., and J. G. Wilson Corporation, as subcontractors, filed their respective memoranda for mechanics’ liens, and gave notice to the owners of the amount and character of their respective claims; that at the time of receiving these notices the owners were not indebted to Roanoke Construction and Lumber Corporation; that the appellants were not general contractors; and that the recordation of the memoranda of the several parties did not constitute valid liens on the property, but were clouds upon the owners’ title.

The prayer of the bill was that the court declare the said memoranda, as recorded, invalid as mechanics’ liens, [77]*77and that they be so marked of record. A demurrer was filed to this bill and overruled.

From the answers of the respondents and the evidence, it appears that the complainants, the owners of the land, owned all the stock in a certain corporation, i. e., Jefferson Electric Company; that Roanoke Construction and Lumber Corporation, at the time of entering into the building contract, owed Jefferson Electric Company the sum of $5,000, and that before the building was completed this indebtedness had been increased to $7,680; that no part of the consideration for this debt was used in and about the buildings in question; and that, with the consent of Roanoke Construction and Lumber Corporation, the owners had paid the debt out of the sums due under.the building contract.

The trial court held that the payment of this debt to Jefferson Electric Company constituted an assignment pro tanto of the sum due the general contractor, which assignment, by the provisions of Code, section 6435, was void as to laborers and materialmen who had perfected their liens in the manner prescribed by chapter 270 of the Code (section 6426 et seq.). From this decision the owners sought an appeal, which was refused.

Later—i. e., December 24, 1930—the trial court entered a decree declaring valid the liens claimed by Roanoke Iron and Bridge Works, Inc., and J. G. Wilson Corporation, but held invalid the liens claimed by the appellants. It is the latter part of this decree that appellants are seeking to reverse by this appeal.

Appellants now admit that they are not entitled to liens on the property, as general contractors; they contend, however, that they have complied with all the provisions of Code, section 6428, except the giving of written notice to the owners of the amount and character of their claims, and that in this case notice was not necessary, because the owners had actual knowledge of all the facts which a formal notice would have given.

It is to be observed that a general contractor may [78]*78perfect his lien without giving notice to the owner, the filing of the required memorandum for recordation in the clerk’s office being sufficient, but Code, section 6428, expressly requires that a subcontractor comply with the provisions of section 6427, i. e., file certain memoranda required for the perfection of a general contractor’s lien, “and in addition, give notice in writing to the owner of the property, or his agent, of the amount and character of his claim.”

There is no privity of contract between a subcontractor and the owner. A party whose labor or material is used in the erection of a building, without the consent of either the general contractor or the owner, is given a right by the mechanics’ lien statutes in the sums to become due under the building contract, but in order to perfect that right it is essential that such party substantially comply with all the requirements of the statutes. Judge Kelly, in Maddux v. Buchanan, 121 Va. 102, 92 S. E. 880, 831, said:

“Laborers and materialmen are favored by the statute, but not to the extent of requiring the owner of property to pay the same bill twice, once to the builder with whom he has contracted, and again to parties with whom he has no contractual relations. Our present mechanic’s lien laws deal fairly with both the owner and the subcontractor, requiring the owner, after notice, to withhold from the general contractor enough to pay the subcontractor,” provided the owner is indebted to the general contractor at the time notice is given, or may thereafter become indebted to him by virtue of the contract.

“ * * * The statute was designed to protect subcontractors, and creates a liability which would not otherwise exist; but the terms must be met before its benefits can be enjoyed. In other words, as this court has said in former decisions, ‘the owner is under no obligation to protect the interest of the subcontractor, except where the latter has complied with the law, and thus placed himself in a position to demand protection from the owner.’ (Schrieber v. Bank, 99 Va. 257, 262, 38 S. E. 134, 135; University of [79]*79Va. v. Snyder, 100 Va. 567, 581, 42 S. E. 337; Steigleder v. Allen, 113 Va. 686, 691, 75 S. E. 191.)”

Judge Whittle, in the case of Francis v. Hotel Rueger, 125 Va. 106, 99 S. E. 690, 694, has this to say:

“An examination of outside authorities shows that there exists a hopeless diversity of opinion as to whether mechanics’ lien statutes should receive a liberal or strict construction. We believe the correct rule deducible from the language and purposes of our statute and the decisions of this court with respect to it is, that there must be a substantial compliance with the requirement of that portion of the statute which relates to the creation of the lien; but that the provisions with respect to its enforcement should be liberally construed.”

Laborers and materialmen who are unwilling to extend credit to a general contractor have three courses, or methods, open to them to obtain additional security for their claims out of the funds due, or to become due, under the building contract: (1) By taking the steps prescribed by section 6429a of the Code of 1930 to fasten personal responsibility upon the owner; (2) by filing separate and independent liens under Code, sections 6428; (3) by taking advantage of a lien perfected by the general contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Davenport Insulation of Harrisonburg, Inc. v. Aliff
50 Va. Cir. 314 (Rockingham County Circuit Court, 1999)
Self v. Jenkins
34 Va. Cir. 155 (King George County Circuit Court, 1994)
Springfield Engineering Corp. v. Three Score Development Corp.
29 Va. Cir. 218 (Stafford County Circuit Court, 1992)
TQY Investments v. Rodgers Co.
26 Va. Cir. 40 (Fairfax County Circuit Court, 1991)
Blue Ridge Construction Corp. v. Stafford Development Group
24 Va. Cir. 26 (Stafford County Circuit Court, 1991)
Weyant Bros. v. Calvert Construction Co.
18 Va. Cir. 307 (Fairfax County Circuit Court, 1989)
Gunther v. Cantrell
11 Va. Cir. 255 (Fairfax County Circuit Court, 1988)
United Materials & Services, Inc. v. National Capital Developers
8 Va. Cir. 48 (Alexandria County Circuit Court, 1982)
Mills v. Moore's Super Stores
227 S.E.2d 719 (Supreme Court of Virginia, 1976)
Guldberg v. Greenfield
146 N.W.2d 298 (Supreme Court of Iowa, 1966)
Perrin & Martin, Inc. v. United States
233 F. Supp. 1016 (E.D. Virginia, 1964)
Nicholas v. Miller
30 S.E.2d 696 (Supreme Court of Virginia, 1944)
Alessandrini v. Mullins
16 S.E.2d 323 (Supreme Court of Virginia, 1941)
Wallace v. Brumback
12 S.E.2d 801 (Supreme Court of Virginia, 1941)
Hooff v. Paine
2 S.E.2d 313 (Supreme Court of Virginia, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
165 S.E. 371, 159 Va. 72, 1932 Va. LEXIS 175, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coleman-v-pearman-va-1932.