Mills v. Moore's Super Stores

227 S.E.2d 719, 217 Va. 276, 1976 Va. LEXIS 271
CourtSupreme Court of Virginia
DecidedSeptember 2, 1976
DocketRecord 750967
StatusPublished
Cited by7 cases

This text of 227 S.E.2d 719 (Mills v. Moore's Super Stores) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mills v. Moore's Super Stores, 227 S.E.2d 719, 217 Va. 276, 1976 Va. LEXIS 271 (Va. 1976).

Opinion

*277 Cochran, J.,

delivered the opinion of the court.

In this appeal the only question is whether the appellees, subcontractors furnishing materials for the construction of a residence on certain real estate of the appellants, perfected their statutory liens against the property.

On April 15, 1974, the appellants, James E. Mills and Iris W. Mills, his wife (owners), entered into a contract with Charles W. Hollon under which Hollon agreed to construct a residence for the owners for the sum of $30,000. The contract was executed in order that the owners might obtain a commitment for bank financing. On April 26, 1974, the owners and Hollon executed a second contract for the construction of the same residence on the basis of construction cost plus 15% commission. When the residence was approximately two-thirds completed difficulties arose between the owners and Hollon, and all work performed by Hollon, or his corporation, Hollon and Shelnut Corporation, ceased on September 18, 1974. Thereafter, mechanics’ lien memoranda were filed by Moore’s Super Store (Moore’s), Walter Vincient Toms (Toms), Carey S. Fowler and John L. Bell, T/A Moneta Building Supply Company (Moneta), and others, claiming, as subcontractors, liens for materials furnished for the Mills project.

On November 27, 1974, Moore’s filed its bill of complaint in the court below against the owners, to enforce various mechanics’ liens. Subsequently, Hollon and Shelnut Corporation and Hollon were made parties defendant, and Toms and Moneta, with leave of court, filed intervening petitions for the enforcement of their liens. The matter was referred to a commissioner in chancery, who heard the evidence and reported his findings to the trial court.

The commissioner reported that the contract between the owners and Hollon, dated April 26, 1974, was assigned by Hollon to Hollon and Shelnut Corporation, but that the owners did not consent to the assignment or have any knowledge of it. The commissioner reported that Moore’s filed memoranda of mechanics’ liens against Hollon and Shelnut Corporation and the owners on September 25, 1974, and November 21, 1974, for the same account of $7,572.54; that Toms filed a memorandum against Hollon and Shelnut Corporation and the owners for $557.87 on October 8, 1974, and a memorandum against Charles W. Hollon and the owners on November 21, 1974, for the same account of $557.87; and that Moneta filed a memorandum against Hollon and Shelnut Corporation, Charles W. Hollon, and the owners, on November 21, 1974, for $1,652.85. The commissioner reported that these *278 liens were timely filed, and allowed all of them as first liens against Charles W. Hollon, general contractor, and the owners, except that he reduced Moore’s lien by $2,600.08, the cost of materials which the evidence showed had not been furnished for the owners’ construction job, to the sum of $4,972.46. The land affected by the liens was a tract of 1.43 acres.

The commissioner found, from the testimony of Willie Robert Shelnut, a witness for the owners, who had been associated with Hollon in the construction business, that the total cost of labor and materials furnished on the Mills job before work was discontinued was $21,926.08, on which 15% commissions aggregated $3,288.91, making a total amount payable of $25,214.99. The general contractor had received $20,000 in two payments on account from the bank which had agreed to furnish construction money for the owners, so that only $5,214.99 was available to pay the liens of Moore’s, Toms, and Moneta in the total amount of $7,138.18. The commissioner reported, therefore, that each of these three lien creditors was entitled to the same pro rata share (72.6%) of its asserted claim, or $3,610 for Moore’s, $405.02 for Toms, and $1,199.97 for Moneta. By decree entered May 9, 1975, the chancellor overruled all exceptions to the commissioner’s reports, ratified and confirmed the same, and decreed that the appellees were entitled to liens against the 1.43 acres in the amounts stated in the reports. The owners have appealed from this decree.

The owners first argue that the appellees failed to perfect their liens in compliance with the provisions of Code § 43-7. 1 This statute requires that a subcontractor follow the procedure provided for general contractors in Code § 43-4, 2 and in addition give written notice to the *279 owner in order to perfect his lien which, of course, is limited to the amount in which the owner is indebted to the general contractor, at or after the time of notice.

The evidence establishes that work on the Mills residence under the contract terminated on September 18, 1974. James E. Mills, Hollon, and Shelnut all testified to this fact. Although the appellees conceded in oral argument that work “stopped” on that date, they insisted, nevertheless, that there was no evidence that the work at that time was “otherwise terminated” within the meaning of Code § 43-4. We do not agree.

It is uncontroverted that no employees of Hollon, of Hollon and Shelnut Corporation, or of any subcontractor, worked on the project after September 18. The commissioner found, from the testimony of Mills, that Hollon himself terminated the construction. The owners’ counsel stated in oral argument that Mills “fired” Hollon, a contention which, though denied by Mills in his testimony, was supported by the testimony of both Hollon and Shelnut. Regardless of who prompted the termination, however, the evidence shows that work under the contract ceased on September 18, when Hollon and Shelnut Corporation was experiencing severe financial problems and construction of the Mills residence was approximately two-thirds completed. We hold, therefore, on the record before us, that the work was “otherwise terminated’ on that date, within the meaning of Code § 43-4. See Loan Association v. Kendall Company, 205 Va. 136, 147-48, 135 S.E.2d 178, 186-87 (1964), where we affirmed the chancellor’s decree, which confirmed the commissioner’s finding that work had been “otherwise terminated” prior to completion of construction.

The memorandum of lien filed by Moneta on November 21, 1974, was not filed within sixty days after the work was “otherwise terminated”, as required by Code § 43-4. Therefore, the chancellor erred in allowing this lien.

We reject the owners’ contention, however, that the Moore’s and Toms liens were not perfected in compliance with the statute. While the written notices of these liens were not served on the owners within sixty days after September 18, 1974, the memoranda of liens were timely filed.

There is no requirement in Code § 43-7 that written notice to the *280 owner shall be given within any specified time. The language of this statute has remained without substantive change since its codification as Section 2477, Code of 1887, and no time limit has ever been prescribed for giving notice. The notice affords protection to the owner, who is not in privity of contract with the subcontractor, so that he may not be required to pay twice for the same work and materials.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Glasser & Glasser v. Jack Bays, Inc.
Supreme Court of Virginia, 2013
TQY Investments v. Rodgers Co.
26 Va. Cir. 40 (Fairfax County Circuit Court, 1991)
Blue Ridge Construction Corp. v. Stafford Development Group
24 Va. Cir. 26 (Stafford County Circuit Court, 1991)
Weyant Bros. v. Calvert Construction Co.
18 Va. Cir. 307 (Fairfax County Circuit Court, 1989)
First National Bank of Martinsville v. Roy N. Ford Co.
252 S.E.2d 354 (Supreme Court of Virginia, 1979)
Henderson & Russell Associates, Inc. v. Warwick Shopping Center, Inc.
229 S.E.2d 878 (Supreme Court of Virginia, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
227 S.E.2d 719, 217 Va. 276, 1976 Va. LEXIS 271, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mills-v-moores-super-stores-va-1976.