TQY Investments v. Rodgers Co.

26 Va. Cir. 40, 1991 WL 835254, 1991 Va. Cir. LEXIS 536
CourtFairfax County Circuit Court
DecidedOctober 22, 1991
DocketCase No. (Chancery) 121734
StatusPublished
Cited by5 cases

This text of 26 Va. Cir. 40 (TQY Investments v. Rodgers Co.) is published on Counsel Stack Legal Research, covering Fairfax County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
TQY Investments v. Rodgers Co., 26 Va. Cir. 40, 1991 WL 835254, 1991 Va. Cir. LEXIS 536 (Va. Super. Ct. 1991).

Opinion

By Judge Thomas J. Middleton

On November 5,1990, Rodgers Company, Inc. (“Rodgers”) filed a memorandum of mechanic’s lien against Bogle Group II (“Bogle”). Bogle subsequently changed its name to TQY, the petitioner in this case. TQY, in its Petition to Determine the Validity of the Mechanic’s Lien, contends that the lien is invalid for the following reasons:

The written notice given to Bogle was insufficient;
The error in the affidavit accompanying the memorandum was fatal to perfection of the lien;
Rodgers is time-barred from enforcing the lien;
The description of the property included three acres of public land; and
Rodgers failed to comply with the terms of the contract.
For the reasons stated below, the mechanic’s lien is valid.

I. The subcontractor’s written notice to Bogle on July 24,1991, was sufficient.

Although a general contractor need not give written notice to the owner in order to perfect a mechanic’s lien, see Va. Code Ann. § 43-[41]*414 (1990), a subcontractor must do so, see Va. Code Ann. § 43-7 (1990). Rodgers, as subcontractor, filed its memorandum against Bogle on November 5,1990. On March 1,1991, prior to the end of the six-month period for enforcing the lien, Bogle filed for bankruptcy, thus tolling the six-month statute of limitations. Va. Code Ann. § 43-17 (1990). Because of an address change, Bogle apparently did not receive written notice of the lien until July 24, 1991. Bogle admits, however, to having received actual notice much earlier. It is true that an owner’s actual knowledge of a subcontractor’s lien is no substitute for written notice in the absence of a waiver, Coleman v. Pearman, 159 Va. 72, 165 S.E. 371 (1932), overruled on other grounds, Mills v. Moore’s Super Stores, 217 Va. 276, 227 S.E.2d 719 (1976), and failure to give any written notice at all would have been fatal to the lien. However, § 43-7 does not require that written notice be given within any specified time. Indeed, in Mills, the Virginia Supreme Court held that statutory time requirements for filing the memorandum were inapplicable to notice requirements, stating:

Coleman v. Pearman, 159 Va. 72, 165 S.E. 371 (1932), relied on by the owners, is not controlling. In that case, the subcontractors never gave the written notices to the owners which we held were mandated by the statute. Our opinion stated, in dictum, that all statutory steps must be taken within the specified time in order to perfect a subcontractor’s lien. This fundamental rule of statutory construction applies where a time is specified, e.g., filing the memorandum within sixty days, but we are unwilling to extend it to an act for which no time limit for performance is specifically prescribed in the statute. To the extent, therefore, that Coleman indicates that the subcontractor’s notice to the owner must be given within sixty days after construction is completed or the work otherwise terminated, it is hereby expressly disapproved.

Mills, 217 Va. at 280, 227 S.E.2d at 723 (1976).

Because Bogle had actual notice, the delay did not result in any prejudice. Indeed, Bogle filed its Petition to Determine the Validity of the Mechanic’s Lien on June 19,1991, more than one month before receiving written notice of the lien. Based on Mills, the notice was sufficient.

[42]*42II. The error in the affidavit is not fatal to the lien.

Section 43-7 of the Va. Code, in mandating compliance with Section 43-4, requires that the memorandum of mechanic’s lien be verified under oath. Section 43-8 includes a sample affidavit and language that such an affidavit “shall be sufficient if substantially in [that] form and effect.” TQY argues that the affidavit accompanying the memorandum is fatally defective in that it erroneously names Bogle Group II, L.P. (the owner), rather than Bogle Construction Co., Inc. (the general contractor) as the party indebted to the subcontractor. Within the same document, however, the memorandum and notice provisions correctly identify Bogle Construction Co., Inc., as the general contractor. In addition, the substantial identities of Bogle Group II and Boyle Construction make any confusion due to the error unlikely.

This court has previously ruled that a deficiency in the affidavit portion of the memorandum of mechanic’s lien is not necessarily fatal to the lien. See Judge Kenny’s opinion in Weyant Bros., Inc. v. Calvert Constr. Co., 18 Va. Cir. 307 (Cir. Ct. of Fairfax County 1989) (mechanic’s lien valid where the affidavit omitted the sum claimed, but where the memorandum included it); see also Judge Stevens’ letter opinion in R.G. Griffith, Inc. v. Great Falls W. Assoc., Chancery No. 119990 (Cir. Ct. of Fairfax County, May 15, 1991) (citing Diebold v. Tatterson, 115 Va. 766, 80 S.E. 585 (1914) (mechanic’s lien valid where affidavit incorrectly listed the name of the claimant, but where the claimant’s identity was clear from the document as a whole)). Because Bogle Construction’s identity is clear from the entire document, the error in the affidavit is not fatal to the lien.

Section 43-15 of the Virginia Code provides in pertinent part:

No inaccuracy in the memorandum filed . . . shall invalidate the lien, if . . . the memorandum conforms substantially to the requirements of Sections 43-5, 43-8 and 43-10, respectively, and is not willfully false.

The affidavit conforms substantially to the requirements of Va. Code Ann. § 43-8 and is not willfully false. It therefore does not invalidate the lien.

[43]*43III. The filing of the bankruptcy petition tolls the time to file a Bill of Complaint to enforce the lien.

A contractor may not file a Bill of Complaint to enforce a mechanic’s lien against the owner after the owner has filed a bankruptcy petition. To do so would plainly violate the automatic stay provisions of 11 U.S.C. Sect. 362. H.T. Bowling, Inc. v. Bain, 52 Bankr. 58 (Bankr. W.D. Va. 1985), aff’d sub nom. In re Bain, 64 Bankr. 581 (Bankr. W.D. Va. 1986).

To protect the properly perfected lien creditor, the Bankruptcy Code provides for the tolling of the applicable statute of limitations until the later of the remainder of the statutory period or thirty days after notice of the termination or expiration of the automatic stay. 11 U.S.C. Sect. 108(c).

Rodgers filed its memorandum on November 5,1990, after which it had six months to file a Bill of Complaint to enforce the mechanic’s lien. Va. Code Ann. § 43-17 (1990). However, Bogle’s bankruptcy petition of March 1, 1991, tolled the statute of limitations and prohibited Rodgers from filing a suit to enforce the lien. Under the Bankruptcy Code provisions, Rodgers has thirty days after the termination of the stay to file a bill to enforce the lien. 11 U.S.C. § 108(c).

IV.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Heritage Contracting, L.L.C. v. Vasquez
81 Va. Cir. 161 (Fairfax County Circuit Court, 2010)
Ndeh v. Midtown Alexandria, LLC
300 F. App'x 203 (Fourth Circuit, 2008)
Smith v. Adelphia Cable Communications
63 Va. Cir. 580 (Roanoke County Circuit Court, 2004)
Davenport Insulation of Harrisonburg, Inc. v. Aliff
50 Va. Cir. 314 (Rockingham County Circuit Court, 1999)
Ashco Int'l, Inc. v. Westmore Shopping Ctr. Assocs.
42 Va. Cir. 427 (Fairfax County Circuit Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
26 Va. Cir. 40, 1991 WL 835254, 1991 Va. Cir. LEXIS 536, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tqy-investments-v-rodgers-co-vaccfairfax-1991.