Glasser & Glasser v. Jack Bays, Inc.

CourtSupreme Court of Virginia
DecidedFebruary 28, 2013
Docket120287
StatusPublished

This text of Glasser & Glasser v. Jack Bays, Inc. (Glasser & Glasser v. Jack Bays, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Glasser & Glasser v. Jack Bays, Inc., (Va. 2013).

Opinion

PRESENT: All the Justices

GLASSER & GLASSER, PLC, TRUSTEE FOR FIRST MORTGAGE BONDHOLDER, 2006 SERIES

v. Record No. 120287 OPINION BY JUSTICE DONALD W. LEMONS February 28, 2013 JACK BAYS, INC., ET AL.

CITIZENS BUSINESS BANK

v. Record No. 120288

JACK BAYS, INC., ET AL.

CELTIC BANK

v. Record No. 120289

FROM THE CIRCUIT COURT OF PRINCE WILLIAM COUNTY Mary Grace O'Brien, Judge

In this appeal, we consider the validity of various

mechanics' liens filed under Code § 43-4.

I. Facts and Proceedings

A. New Life's Construction Project, Contractors, and Financing

Jack Bays, Inc. ("Jack Bays") is a commercial general

contracting firm with expertise in new church construction.

In 2004, the company's President, Lynn Bays Fuechsel

("Fuechsel"), met the Senior Pastor and Founder of New Life

Anointed Ministries International ("New Life"), Bishop Eugene

Reeves ("Bishop Reeves"). At the time, New Life was beginning

the process of building a church in Woodbridge, Virginia. Jack Bays ultimately became the general contractor on the

project.

On August 22, 2005, Jack Bays submitted a proposal for

the site work portion of the project. Site work included

excavation and grading, utility installation, concrete and

asphalt paving, landscaping, and fencing. New Life accepted

the proposal either contemporaneously or shortly thereafter by

signing an owner/contractor agreement form ("August '05

Agreement"). The agreement form stated that New Life would

pay Jack Bays a stipulated sum of $4,209,532 for initial work

at the project site.

On September 29, 2005, Jack Bays began site work. On

April 26, 2006, a new Agreement ("April '06 Agreement")

provided that New Life would pay Jack Bays a stipulated sum of

$12,016,000. The April '06 Agreement incorporated the sum and

scope of work from the August '05 Agreement.

On December 5, 2006, the parties increased the value of

the contract for the final time. Change Order 13 required

construction on a preschool, sanctuary, lobby and corridors.

The cost of this project was $5,858,732, which brought the

total cost of the project to $17,874,732. The contract

provided for payment of requisitions from Jack Bays based upon

percentage completion of the project.

2 To perform work at the site, Jack Bays contracted with

several subcontractors, the following eleven of which are

parties to this action: Structural Steel, LLC ("Structural

Steel"), United Sprinkler Company, Inc. ("United Sprinkler"),

Virginia Paving Company ("Virginia Paving"), Sparkle Painting

Company, Inc. ("Sparkle Painting"), Scaffold Resource, LLC

("Scaffold Resource"), Miller Construction, Inc. ("Miller

Construction"), Adrian L. Merton, Inc. ("Adrian Merton"),

Century Contracting Corporation ("Century Contracting"),

Clover Contracting, Inc. ("Clover Contracting"), General Glass

Corporation ("General Glass"), and Becker Electric Company. ∗

After briefly working with Branch Banking and Trust, New

Life sought additional funds for the project. To obtain these

funds, New Life worked with Strongtower, a bonding company for

church financing. This collaboration led New Life to obtain

additional financing, specifically in the amount of $13.6

million. San Joaquin Bank (the predecessor to and hereinafter

"Citizens Business Bank"), 1st Centennial Bank (the

predecessor to and hereinafter "Celtic Bank"), and Glasser &

Glasser, PLC ("Glasser & Glasser") (collectively, "Lenders")

were listed as "Lenders" on the Deed of Trust for the new

financing, while Stewart Title Guaranty Company ("Stewart

∗ When referring to the general contractor and the subcontractors we will use the term "Contractors."

3 Title") was designated "Trustee." Glasser & Glasser was also

designated Trustee for "First Mortgage Bondholders, 2006

Series" ("Bondholders"). Citizens Business Bank obtained a

note evidencing the debt in the principal amount of

$8,962,000. Celtic Bank obtained a note in the principal

amount of $4,491,000. Additionally, the Deed of Trust

incorporated a $13,453,000 Trust Indenture "for the benefit of

certain Bondholders," with Glasser & Glasser as Trustee, and

Reliance Trust Company as the trust company and disbursement

agent. The Lenders recorded their Deed of Trust on June 27,

2006.

On September 29, 2005, Jack Bays issued its first

requisition for payment to New Life. New Life paid in full,

and continued to pay its requisitions in full each month

through March 2007. New Life paid part of Jack Bays' April

2007 requisition, falling $141,498.70 short of total payment.

Thereafter, New Life made no payments to Jack Bays from May

through October 2007, because funding for the project was

exhausted.

Throughout the May-October 2007 period, New Life

attempted to obtain additional financing. Jack Bays

understood from Bishop Reeves that new funding would be

obtained to cover the cost of the project. On July 27, 2007,

Monika Taylor, an underwriter for Quest Capital Funding, wrote

4 to Fuechsel to "inform [Fuechsel] that we are going through

final approval for a $20,000,000.00 (Twenty Million Dollar)

loan for New Life Anointed Church." From her conversations

with Bishop Reeves, Fuechsel expected to be paid for Jack

Bays' prior, ongoing, and future work on or around August 3,

2007. After the anticipated loan from Quest Capital Funding

did not close, Fuechsel was told that financing would instead

be in place by the end of August. However, no further

financing was obtained. Jack Bays continued construction work

at the site from May through September 28, 2007.

B. Contract Work and Demobilization, Mechanics' Liens, and Termination

On September 28, 2007, Jack Bays sent a memorandum to its

subcontractors. The memorandum detailed New Life's efforts to

obtain financing, and informed the subcontractors that delays

in the approval process caused Jack Bays to immediately

"stop[] active work on the site until all payments are

current." The letter asked the subcontractors to consider

waiting until November 2007 to file a mechanics' lien so that

title could remain clear and enable New Life to "have the best

opportunity to obtain financing."

After September 28, 2007, Jack Bays began to shut down

active work on the project by collecting equipment and

rectifying unsafe conditions on the premises. Jack Bays

5 maintained a log of site work during this time and issued a

requisition for October 2007 work it classified as

"demobilization."

According to Jack Bays, subcontractors continued work at

the site through October 11, 2007. However, United Sprinkler

performed "normal course of business" work through at least

October 18, 2007. Sparkle Painting had an employee working on

site through at least October 1, 2007, and possibly through

October 9, although information supporting the latter date was

inconclusive. Scaffold Resource entered the premises on

October 1 to remove scaffolding provided, completing this work

– which was provided for in its contract with Jack Bays – on

October 16. Becker Electric continued contract completion

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Siska Revocable Trust v. Milestone Dev't
715 S.E.2d 21 (Supreme Court of Virginia, 2011)
Smith Mountain Supply v. Windstar Prop.
672 S.E.2d 845 (Supreme Court of Virginia, 2009)
Bayview Loan Servicing, LLC v. Simmons
654 S.E.2d 898 (Supreme Court of Virginia, 2008)
Conyers v. MARTIAL ARTS WORLD OF RICHMOND
639 S.E.2d 174 (Supreme Court of Virginia, 2007)
Amstutz v. Everett Jones Lumber Corp.
604 S.E.2d 437 (Supreme Court of Virginia, 2004)
Shepherd v. Davis
574 S.E.2d 514 (Supreme Court of Virginia, 2003)
Snyder Plaza Properties, Inc. v. Adams Outdoor Advertising, Inc.
528 S.E.2d 452 (Supreme Court of Virginia, 2000)
Carolina Builders Corp. v. Cenit Equity Co.
512 S.E.2d 550 (Supreme Court of Virginia, 1999)
Chaney v. Haynes
458 S.E.2d 451 (Supreme Court of Virginia, 1995)
Woodington Electric, Inc. v. Lincoln Savings & Loan Ass'n
385 S.E.2d 872 (Supreme Court of Virginia, 1989)
Hill v. Hill
318 S.E.2d 292 (Supreme Court of Virginia, 1984)
Mendenhall v. Douglas L. Cooper, Inc.
387 S.E.2d 468 (Supreme Court of Virginia, 1990)
American Standard Homes Corp. v. Reinecke
425 S.E.2d 515 (Supreme Court of Virginia, 1993)
Bauer v. Harn
286 S.E.2d 192 (Supreme Court of Virginia, 1982)
Mills v. Moore's Super Stores
227 S.E.2d 719 (Supreme Court of Virginia, 1976)
Chavis v. Gibbs
94 S.E.2d 195 (Supreme Court of Virginia, 1956)
Northern Virginia Savings & Loan Ass'n v. J. B. Kendall Co.
135 S.E.2d 178 (Supreme Court of Virginia, 1964)
United Masonry Inc. v. Riggs National Bank
357 S.E.2d 509 (Supreme Court of Virginia, 1987)
JAMES T. BUSH CONST. CO., INC. v. Patel
412 S.E.2d 703 (Supreme Court of Virginia, 1992)
Wallace v. Brumback
12 S.E.2d 801 (Supreme Court of Virginia, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
Glasser & Glasser v. Jack Bays, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/glasser-glasser-v-jack-bays-inc-va-2013.