Nicholas v. Miller

30 S.E.2d 696, 182 Va. 831, 153 A.L.R. 752, 1944 Va. LEXIS 239
CourtSupreme Court of Virginia
DecidedJune 22, 1944
DocketRecord No. 2804
StatusPublished
Cited by7 cases

This text of 30 S.E.2d 696 (Nicholas v. Miller) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nicholas v. Miller, 30 S.E.2d 696, 182 Va. 831, 153 A.L.R. 752, 1944 Va. LEXIS 239 (Va. 1944).

Opinion

Gregory, J.,

delivered the opinion of the court.

On August 23, 1940, C. M. Conrad, general contractor, entered into a written contract with Elizabeth L. Nicholas and Georgia W. Nicholas, who will be referred to as the owners, to build for them a duplex apartment house in Harrisonburg, Virginia, at the price, of $5,487.39.

[833]*833The Harrisonburg Building and Supply Company, Incorporated, supplying materials for the construction of the-building under a subcontract with Conrad, the general contractor, refused to extend credit to Conrad, and required the owners to guarantee the payment of i'ts account for any material supplied by it and used in the building. Accordingly, on September 3,. 1940, the owners entered into a written agreement which this court, in Nicholas v. Harrisonburg Bldg., etc., Co., 181 Va. 207, 24 S. E. (2d) 452, pronounced a guaranty agreement whereby' the payment of the account for supplies and materials furnished by the Harrisonburg Building and Supply Company, Incorporated, used in the building, was guaranteed to that corporation by the owners.

After the completion of the building, a controversy arose about the rights of the other materialmen and subcontractors who had also furnished labor and materials for the building. The owners refused to pay to the Harrisonburg Building and Supply Company, Incorporated, the guaranteed amount which they had withheld, and this corporation then brought an action at law against the owners on the contract of guaranty for $1,690.13, representing the total amount due the corporation. A judgment was obtained against the owners for that amount. A writ of error was awarded by this court (see Nicholas v. Harrisonburg Bldg., etc., Co., supra), and the judgment of the lower court was affirmed. In the opinion rendered by this court, it was expressly held that the owners had guaranteed the account of the Harrison-burg Building and Supply Company, Incorporated, the subcontractor, in order that the building might be completed, and that the guaranty contract was the inducement to that corporation to furnish the materials.

In the meantime, on December 31, 1940, more than three months after the account of the Harrisonburg Building and Supply Company, Incorporated, had been guaranteed by the owners, W. J. Miller, trading as Miller Sheet Metal Works, another subcontractor, who had installed two furnaces in the building, filed a memorandum of mechanic’s lien for $414.29, the amount due him, and notice of this lien was [834]*834served on the owners on the same date. Other subcontractors timely filed their mechanic’s liens. A. suit to enforce the mechanic’s liens was filed by W. J. Miller, trading as Miller Sheet Metal Works. In this suit the other subcontractors have filed their petitions to enforce their respective liens.

At the time notice was served of the mechanic’s lien in favor of W. J. Miller, trading as Miller Sheet Metal Works, to-wit: December 31, 1940, the owners had in their hands a balance of $2,165.69, due the general contractor, Conrad, which included the amount withheld by them for the Harrisonburg Building and Supply Company, Incorporated. After the judgment which was obtained against them on the guaranty contract by the Harrisonburg Building and Supply Company, Incorporated, of $1,690.13, had been paid, there remained in their hands the sum of $475.56, which was not sufficient, by more than $400, to pay and satisfy all the liens of the subcontractors.

The decree of the lower court which is now before us for review, refused to allow the owners credit, as against the other subcontractors, for the $1,690.13, paid on the judgment of the Harrisonburg Building and Supply Company, Incorporated. By the decree, the accounts of the various subcontractors were established and allowed in full, and the building and lot were ordered to be sold, and the proceeds applied to the satisfaction in full of the respective mechanic’s liens of the subcontractors, who are the appellees here.

The main - question upon this appeal is whether or not the court erred in fading to hold that the subcontractors were limited in their recovery to the balance remaining in the owners’ hands after the payment of the guaranteed claim of the Harrisonburg Building and Supply Company, Incorporatéd. The court, as we have seen, held that they were not so limited.

A well-defined legislative policy in Virginia, as expressed in statutory enactments (Code, sections 6428, 6429, 6429a, and 6432) is that generally the extent of liability of the owner to a subcontractor or subcontractors is limited to [835]*835the amount the owner is indebted to the general contractor at the time notice to the owner is given by the subcontractor or subcontractors. This policy likely found its source in what is known as the “New York System”, under which the lien of a subcontractor or materialman depends on, and is limited by, the amount remaining due the general contractor at or subsequent to notice by the subcontractor, served on the owner. See 36 Am. Jur., Mechanics’ Liens, section 6.

We are not aware of any case in Virginia in which the owner has been held hable to subcontractors enforcing their mechanics’ liens for an amount that would exceed the total amount of the general contract price. The owner is not required to pay in excess of the agreed price stipulated in the contract with the general contractor. He is required to pay for the building but once.

We have so applied the rule in Virginia. See Schrieber, Sons & Co. v. Citizens Bank, 99 Va. 257, 38 S. E. 134; Thomas & Co. v. McCauley, 143 Va. 451, 130 S. E. 396.

In Burks Pleading and Practice (3rd Ed.), p. 830, the rule is stated thus:

“Where a subcontractor refuses to do work unless the owner will agree to pay him, it seems that, if the contractor cannot have the work done in a reasonable time, and the owner is thus compelled to guarantee bills of subcontractors, the owner is entitled, both as against the general contractor and other subcontractors, to deduct the amounts for which he has thus become responsible.”

Our present statute, Code, sec. 6429a (Michie), enacted in 1924 (see Acts 1924, p. 658), provides how the owner or general contractor may be made personally liable to subcontractors and others performing work or supplying materials for a building. The Code revisors of 1919 had previously eliminated the old section 2479 of the Code of 1887, which then provided for the personal liability of the owner. The reason for the revisors’ action is found in an explanatory revisors’ note to section 6431 of the 1919 Code:

[836]*836“Section 2479 of the Code of 1887, as amended, dealing with personal liability of owner, has been omitted, thereby taking out of the statute the whole subject of personal liability of the owner. So long as the personal liability of the owner is retained in the chapter, it is practically impossible to administer the mechanics’ lien law in such a way as will give information to everybody of the state of the liens, and not do injustice to someone. In practice this section caused much confusion, and, in some cases, injustice. If any person desires to secure the personal liability of the owner, it should be a matter of contract, and there is no necessity for injecting it into the mechanics’ lien law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

W. O. Grubb Steel Erection, Inc. v. 515 Granby, L.L.C.
78 Va. Cir. 463 (Norfolk County Circuit Court, 2009)
Lower v. Cranch
32 Va. Cir. 110 (Loudoun County Circuit Court, 1993)
English's, Inc. v. McCrickard
7 Va. Cir. 218 (Campbell County Circuit Court, 1984)
Henderson v. Couch
274 S.W.2d 844 (Court of Appeals of Texas, 1955)
Anderson v. White
32 S.E.2d 72 (Supreme Court of Virginia, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
30 S.E.2d 696, 182 Va. 831, 153 A.L.R. 752, 1944 Va. LEXIS 239, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nicholas-v-miller-va-1944.