Lubman v. C.A. Guard Masonry Contractor, Inc. (In Re Gem Construction Corp. of Virginia)

262 B.R. 638, 2000 WL 33321165
CourtUnited States Bankruptcy Court, E.D. Virginia
DecidedSeptember 14, 2000
Docket10-15634
StatusPublished
Cited by24 cases

This text of 262 B.R. 638 (Lubman v. C.A. Guard Masonry Contractor, Inc. (In Re Gem Construction Corp. of Virginia)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lubman v. C.A. Guard Masonry Contractor, Inc. (In Re Gem Construction Corp. of Virginia), 262 B.R. 638, 2000 WL 33321165 (Va. 2000).

Opinion

MEMORANDUM OPINION

DOUGLAS 0. TICE, Jr., Chief Judge.

The plaintiff, Sherman B. Lubman, chapter 7 trustee for the bankruptcy estate of GEM Construction Corporation of Virginia (GEM), filed a complaint against thirty defendants to avoid preferential payments pursuant to 11 U.S.C. § 547(b) and for judgment for the amount of the transfers against defendants pursuant to § 550. The only remaining issues for this court to decide are (1) whether the defendants C.A. Guard Masonry Contractor, Inc. (C.A.Guard) and Stovall Associates, Inc. (Stovall) have met their respective burdens of proving that the payments they received are shielded from avoidance under “new value” exception of § 547(c)(1); and (2) whether C.A. Guard has met its burden of proving that the payment it received is protected from avoidance under “ordinary course of business” exception of § 547(c)(2).

For reasons stated in this memorandum opinion, the court will enter judgment against C.A. Guard pursuant to § 547(b) in the amount of the transfer. With respect to Stovall, the court will enter judgment against the trustee because the preferential transfer to Stovall meets the new value exception under § 547(c)(1).

Findings of Fact.

Debtor GEM was a construction company that operated as a general contractor or subcontractor depending on the nature of the project. Defendants C.A. Guard and Stovall performed subcontract work for GEM.

On April 23, 1998, an involuntary chapter 7 bankruptcy petition was filed against GEM, and an order for relief was entered on May 15,1998. Within ninety days prior to the filing of GEM’s bankruptcy, GEM made several payments to its subcontractors. Among the transfers made by GEM was a payment to C.A. Guard in the amount of $21,209.06 and a payment to Stovall in the amount of $81,874.00.

I. C.A. GUARD.

GEM’s payment to C.A. Guard was for work performed on two separate construction projects. On one project, A.H. Robins, Inc., contracted with Suitt Construction for budding renovation work. Suitt Construction subcontracted work on the *643 project to GEM, which in turn, subcontracted masonry work to C.A. Guard. On the other project, Investment Partners contracted with GEM for construction work at the Genito Mini Storage Facility. GEM also subcontracted masonry work on this project to C.A. Guard. Both projects were substantially completed by September 1997.

C.A. Guard and GEM had a long and enduring relationship, doing business together off and on for the last twenty years. C.A. Guard had never filed mechanics’ liens on any job that it had with GEM until December 23, 1997, when it filed two mechanics’ liens, one against property of A.H. Robins in the amount of $19,793.00, covering a portion of amounts billed by invoice dated July 22, 1997, and the other against property at the Genito Mini Storage Facility in the amount of $10,613.00, covering amounts billed by invoice dated October 24,1997.

On December 23, 1997, the date the mechanics’ hens were recorded, Suitt Construction owed GEM $715.69 under their contract. On that date, the amount A.H. Robins owed Suitt Construction on the A.H. Robins project is unknown, as is the amount, if any, Investment Partners owed GEM on the Genito project.

C.A. Guard did not file suit to enforce either hen and released both hens on January 6, 1998, based on GEM’s promise to pay. GEM sent C.A. Guard a check in the amount of $21,209.06 dated January 21, 1998, which cleared debtor’s bank account on January 23, 1998. 1 The transfer constituted payment of $11,199.69 on the A.H. Robins project and $10,009.37 on the Geni-to project.

At the time of GEM’s payment to C.A. Guard, Suitt Construction still owed GEM $715.69; however, the amount A.H. Robins owed Suitt Construction and the amount, if any, Investment Partners owed GEM are unknown.

II. STOVALL.

GEM’s payment to Stovall was for work performed on GEM’s construction contract with Baptist Theological Seminary (BTS). Under the terms of the contract, BTS was authorized to retain and hold a percentage of payments on work in progress until final completion and acceptance of the work covered under the contract. GEM entered into a contract with Stovall, pursuant to which Stovall agreed to supply materials and labor in connection with interior storm windows and glazing work on the project. Stovall last performed work under this subcontract on November 19, 1997. No subcontractors other than Stovall were working on the project in November and December 1997 and January 1998.

As part of the general contract, GEM obtained a payment bond on the project from Markel Insurance Company (Markel) during 1996. As security, the bond contained a provision that stated that “funds earned by the contractor in the performance of the construction contract are dedicated to satisfy obligations of the contractor and the surety under [the] bond, subject to the owner’s priority to use the funds for the completion of the work.” Markel also received a general indemnity agreement signed by GEM and its principal, George Peterson, dated August 7, 1996.

On November 17, 1997, ten days after completing work on the site, Stovall sent a certified letter to Markel and BTS making *644 a demand for payment under the bond. Negotiations ensued, culminating in a request by Markel and GEM to BTS asking that BTS make full payment to Stovall by check payable jointly to Stovall and GEM. On January 28, 1999, in response to this request, the owner paid Stovall $32,510.00 by check payable jointly to Stovall and GEM. 2

On February 5, 1998, Stovall filed suit against GEM and Markel in the circuit court of the City of Richmond for the outstanding balance on its subcontract. GEM and Markel were served with notice of the suit on February 18, 1998, and February 17, 1998, respectively. On February 18, 1998, the same day that GEM received notice of the lawsuit, GEM delivered a check in the amount of $81,874.00 to Stovall for the full balance due under the subcontract, and Stovall contemporaneously executed a final lien waiver. Stovall also dismissed its case against GEM and Markel.

At the time of GEM’s payment to Sto-vall, BTS owed GEM approximately $120,000.00, representing retainage under the general contract, and GEM owed its subcontractors approximately $254,832.08.

Additional findings of fact are stated in the conclusions of law section of this opinion.

Discussion and Conclusions of Law.

Bankruptcy Code § 547(b) permits a trustee to invalidate certain pre-bankruptcy transfers of a debtor, generally referred to as preferences. See 11 U.S.C. § 547(b); see also Advo-System, Inc. v. Maxway Corp., 37 F.3d 1044, 1045 (4th Cir.1994).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Newton v. McGhee-Rosenburgh
E.D. Tennessee, 2021
KH Funding Co. v. Escobar (In re KH Funding Co.)
541 B.R. 308 (D. Maryland, 2015)
Moser v. Bank of Tyler (In re Loggins)
513 B.R. 682 (E.D. Texas, 2014)
Campbell v. Hanover Insurance
457 B.R. 452 (W.D. North Carolina, 2011)
Richardson v. Bullock (In Re Bullock Garages Inc.)
338 B.R. 784 (C.D. Illinois, 2006)
Chrysler Credit Corp. v. Hall
312 B.R. 797 (E.D. Virginia, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
262 B.R. 638, 2000 WL 33321165, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lubman-v-ca-guard-masonry-contractor-inc-in-re-gem-construction-corp-vaeb-2000.