Paragould v. Arkansas Light & Power Co.

284 S.W. 529, 171 Ark. 86, 46 A.L.R. 1186, 1926 Ark. LEXIS 406
CourtSupreme Court of Arkansas
DecidedMay 10, 1926
StatusPublished
Cited by6 cases

This text of 284 S.W. 529 (Paragould v. Arkansas Light & Power Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paragould v. Arkansas Light & Power Co., 284 S.W. 529, 171 Ark. 86, 46 A.L.R. 1186, 1926 Ark. LEXIS 406 (Ark. 1926).

Opinions

This is the second appeal in this case. The opinion on the former appeal is found reported in 146 Ark. 1. On the former appeal it was decided that the Arkansas Light Power Company, hereinafter referred to as the company, had contracted with the city of Paragould, hereinafter referred to as the city, to furnish electrical power to do the pumping for the city's waterworks plant for a period of ten years, and that the company had breached its contract and was liable to the city for the damages resulting from this breach. The cause was remanded on the former appeal for the assessment of the damages.

By the terms of the contract the company agreed to furnish power for a period of ten years at the rates fixed in the contract, which were not in any event to exceed forty per cent. of the bills collected by the city from its consumers, at the rate to the consumers then in effect.

The performance of the contract was begun on February 7, 1917, and continued until July 24, 1918, at which time the company gave notice that, after thirty days, it would discontinue furnishing the city power at the contract rates, and, pursuant to this notice, the company discontinued its service on August 25, 1918, after which time the city resumed the use of the steam power plant with which it had done the pumping prior to the time its contract with the company became effective, and this suit was commenced to recover damages for the breach of the contract

There existed in the city two waterworks improvement districts, known as Districts Nos. 1 and 2, and the city had, pursuant to the provisions of 5739, C. M. Digest, taken over and was operating the steam pumping plant when its contract with the company was made. *Page 88

During the pendency of the litigation, and before the decision of this court on the first appeal, there was passed at the extra session of the General Assembly on February 26, 1920, an act numbered 397, "providing for the formation of an improvement district in the city of Paragould for the purpose of repairing, extending, enlarging, reconstructing, rebuilding and taking over the waterworks system in said city, and providing for additional sources of water supply for the demands of the city."

Pursuant to the power conferred in this special act, Waterworks Improvement District No. 3 was organized. This new district included all the territory embraced in Districts Nos. 1 and 2, and included the entire city, which was an area considerably larger than the original Districts Nos. 1 and 2.

By this special act, District No. 3 superseded Districts Nos. 1 and 2, and the new district took over the waterworks system of the old districts and it was provided that the commissioners of the new district should enlarge and reconstruct the existing districts, and should remain in control thereof and operate the same until all the debts of both the old and the new districts had been paid, after which the control of the system should pass to the city.

The initial ordinance of the city council to make the special act of the General Assembly effective was passed on May 19, 1920, and the final ordinance creating the district and appointing the commissioners was enacted by the city council on July 23, 1920, and the commissioners of the new district qualified thereunder. After the organization of District No. 3 and the qualification of its commissioners, it was moved in the court below that the new district be made a party plaintiff to the action, by reason of its relationship to Districts Nos. 1 and 2, but this motion was overruled, and the trial proceeded between the original parties.

The company admits that, under the decisions of this court on the former appeal, it is liable to the city for the damages occasioned by the breach of its contract, but it *Page 89 insists that the city could and should have minimized its damages by using its power at what it calls its primary rate, and that its liability for the breach of the contract could not extend beyond the time when Improvement District No. 3 was organized. On the other hand, the city contends that it is entitled to recover, as the measure of its damages, the difference between the contract price for the necessary power and the actual costs incurred by it in generating this power, and that it is entitled to recover the total of this difference up to the time of the expiration of the contract between the city and the company.

The cause was submitted to the court without a jury, and the court found that the city was bound by the so-called primary rate, and that the city's right to recover ceased with the creation of Waterworks Improvement District No 3, and a judgment was rendered in accordance with these findings, from which the city has appealed. In order that a final judgment might be rendered upon this appeal, the court further found the damages sustained by the city in the operation of its plant in excess of the contract price, first, to the time of the organization of Waterworks Improvement District No. 3, and second, to the time of the institution of this suit. The correctness of these findings is not questioned by the company, its insistence being that the findings upon which the court based its judgment are correct and that the judgment should be affirmed.

There is, first, much discussion as to the burden of proof, each insisting that this burden rests upon the other. But we are of opinion that, it having been adjudged that the company had breached the contract and was liable for the damages resulting therefrom, the burden of proof was upon the city to establish its damages, but, in so far as it was contended that the damages thus shown might and should have been minimized, that burden was upon the company. The law is so declared in the annotated cases cited in the note to 197 of the chapter on Damages in 8 R.C.L., page 655, and in the text to the section cited it is stated that where it is claimed that expenditures were *Page 90 unreasonably incurred (in performing the service which the defaulting party should have performed), the burden is on the defendant to prove such to be the fact." Arkansas Short Leaf Lbr. Co. v. McInturf, 134 Ark. 284.

It is very earnestly insisted by the company that the city should not have continued to use the plant which it had in use when the contract was made with the company to furnish the necessary power, but that the city should have used the power which the company was prepared to furnish, and would have furnished, at what it calls its primary rate.

The city's plant was equipped to burn coal, and it was shown that the price of coal advanced constantly from the time the original contract between the city and the company was made until 1920, when the price of coal began to decline. The testimony shows that the company operated in a number of cities and towns of the State, and that it had established a rate available to all consumers of its power using the company's 2300 3-phase service. The service in the city of Paragould was a 2-phase service until the spring of 1921, and there is a question whether this service is interchangeable, but, conceding that it is, we do not regard that fact as controlling here, for reasons which will be hereinafter discussed.

It is an admitted fact that the city could not have availed itself of the company's primary rate without changing from a steam to an electrical plant, and to do this additional machinery would have been required, which would have cost $6,000.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bill C. Harris Construction Co. v. Powers
554 S.W.2d 332 (Supreme Court of Arkansas, 1977)
Kohlenberger, Inc. v. Tyson's Foods, Inc.
510 S.W.2d 555 (Supreme Court of Arkansas, 1974)
Sellers v. Orona
265 P.2d 369 (New Mexico Supreme Court, 1954)
Consolidated Cut Stone Co. v. Seidenbach
1937 OK 701 (Supreme Court of Oklahoma, 1937)
Progressive Life Insurance Co. v. Shope
82 S.W.2d 8 (Supreme Court of Arkansas, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
284 S.W. 529, 171 Ark. 86, 46 A.L.R. 1186, 1926 Ark. LEXIS 406, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paragould-v-arkansas-light-power-co-ark-1926.