Cushing Country Club v. Boardman Company

1963 OK 83, 381 P.2d 856, 1963 Okla. LEXIS 375
CourtSupreme Court of Oklahoma
DecidedApril 9, 1963
Docket39731
StatusPublished
Cited by4 cases

This text of 1963 OK 83 (Cushing Country Club v. Boardman Company) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cushing Country Club v. Boardman Company, 1963 OK 83, 381 P.2d 856, 1963 Okla. LEXIS 375 (Okla. 1963).

Opinion

JOHNSON, Justice.

In .the early part of 1959, the Cushing Country Club contracted with Loftin Construction Co., Inc. to build a swimming pool on the premises of the club near Cushing, Oklahoma. Construction was begun in May, 1959. In August, 1959, the pool was tendered to the club. After testing the pool, the club rejected it as incomplete and not constructed in compliance with specifications. Alterations and additional materials were added to the pool in February, 1960, by Loftin Construction Co.

The defendant in error, Boardman Company, hereinafter referred to as plaintiff, furnished materials used in the construction of the pool in June, July and August, 1959.

After the rejection of the pool, the Boardman Company on February 2, 1960, furnished materials and labor to complete the pool according to specifications. The materials so installed consisted of a flow-rate indicator and strainer basket. These were not installed to replace defective materials previously installed. They were called for by the original contract and had never been installed. On February 9, 1960, the Boardman Company filed its lien for a total sum of $3,253.73, covering all materials and labor furnished by Boardman Company in the construction of such pool.

On June 17, 1960, plaintiff filed suit seeking judgment for its debt and foreclosure of lien. Upon trial the court rendered judgment for plaintiff. After the overruling of motion for new trial, defendant Cushing Country Club appeals.

Only one proposition for reversal is urged, namely:

“The trial court erred in allowing the plaintiff, Boardman Company, a lien for the value of that material furnished between June 5, 1959, and August 17, 1959, when the evidence in the trial court proved conclusively that the material'furnished in February, 1960, was furnished pursuant to a completely separate and distinct transaction.”

The statute under which a subcontractor’s lien is obtained is 42 O.S.1961 § 143. The pertinent language with which we are concerned here is: “ * * * by filing with the clerk of the district court * * * within ninety (90) days after the date upon which material was last furnished or labor last performed under such subcontract, * * It is necessary to determine whether the items furnished and labor last furnished were in connection with the entire subcontract or were only the items furnished in February, 1960, or a separate arrangement so that the furnishing of same did not authorize a lien for all of the materials furnished and labor performed in the summer of 1959.

Ordinarily, the furnishing of labor or the materials to remedy a defect subsequent to completion of contract will not extend the time for filing a lien. See Norman v. Hearne and Tittle, 145 Okl. 217, 292 P. 332; Taylor Bros. v. Gill, 126 Okl. 293, 259 P. 236, 54 A.L.R. 979; Jones v. Balsley, 27 Okl. 220, 111 P. 942.

But such is not the case here. This is not a case where defective materials or parts were replaced. In this instance, the items required by the specifications had never been furnished. The contract was *858 not fully performed nor the project complete until these items were installed.

Two things must be determined: 1. Is the finding of the facts by the trial court sustained by the evidence; and, 2., what is the law applicable to the facts as found to exist.

In considering the first of these, it should be borne in mind that the trial court had before it the witnesses. It could judge their demeanor and apparent truthfulness. Therefore, it is not incumbent upon this court to disturb the trial court’s findings unless against the clear weight of the evidence. In Thomas v. Owens, 206 Okl. 50, 241 P.2d 1114, we said:

“In an action of equitable cognizance, presumption is in favor of the trial court’s finding, and it will not be set aside on appeal unless against the clear weight of the evidence.”

Again, in The H. E. Leonhardt Lumber Co. v. Ed Wamble Distributing Co., Okl., 378 P.2d 771, we said:

“Whether a lien statement is filed within the statutory time limit is a question of fact to be determined from the evidence.”

The particular portion of the record under attack reads:

“The Court finds from the evidence that the swimming pool had not been completed so as to comply with the contract entered into between defendant and Loftin Construction Company, and in February of 1960 the plaintiff with the full knowledge and consent and at the request of defendant, Cushing Country Club, performed additional work as set forth in the exhibit, and also at the consent of the Loftin Construction Company; That this was done to complete the contract of Loftin Construction Company with the defendant and to comply with the requirements of the State Health Inspector, and therefore this case is governed by the principles of law as indicated and the annotation of 54 ALR 988 start-on that page and the cases thereunder, supported by the authority of [Joplin Sash & Door Works v. Oklahoma Presbyterian College for Girls, 36 Okl, 547], 129 Pac. 40, an Oklahoma case, which was confirmed in [Consolidated Cut Stone Co. et al. v. Seidenbach et al., 181 Okl. 578], 75 Pac. (2) 442. * * * ”

The evidence in the record supporting the finding of the court may be epitomized as-follows:

Paul Witt, an employee of The Boardman Company, testified as follows:

* * * * * *
Now, had you previously delivered a Flow Rate Indicator to Mr. Loftin ? a
Mr. Loftin — yes, I delivered several throughout the year. He had picked up one specifically for the Cushing job, but I believe they said they moved it to the Town House Motel in Fayetteville, Arkansas, and would need to replace this one. c
But this had not been put on this job until you put it on in February, 1960? a
Not to my knowledge, it had not been installed.
sK ⅜: ⅜ ⅜ :jc
Now, as a result of that did you attach this Filter Flow device that you testified that you installed on February 3rd, 1960? a
Yes. c
Did that complete, then, your subcontract with Mr. Loftin? a
Yes. c
Now, were you doing this as an individual, Mr. Witt, or were you doing it as an employee of the Boardman Company? a
As an employee of the Boardman Company.
Did you bill him individually for your services, or did the Board-man Company bill him? a
Yes.
*859 "Q. I’ll ask you if that is the last item that appears in our Exhibit 'A’ attached to the petition showing the material furnished, the one dated February 3rd, 1960, for $51.00?
“A: Yes.
* * * * * *
■“Q. Mr. Witt, in the opening statement of Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones v. Purcell Investments, LLC
2010 OK CIV APP 15 (Court of Civil Appeals of Oklahoma, 2009)
Richardson v. H. E. Leonhardt Lumber Co.
1964 OK 15 (Supreme Court of Oklahoma, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
1963 OK 83, 381 P.2d 856, 1963 Okla. LEXIS 375, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cushing-country-club-v-boardman-company-okla-1963.