KENNETH L. BUETTNER, Judge.
T1 Defendant/Cross-Plaintiff/Appellant/Cross-Appellee Purcell Investments, LLC, (Purcell) appeals from the trial court's March 27, 2009 Journal Entry of Judgment which granted summary judgment against Purcell and Defendant Kerr 3 Construction Group, LLC, in favor of Third-Party Defendant/Cross-Defendant/Appellee/Cross-Appel-lant Express Fire Protection, Inc. (Express). The trial court interpreted 42 00.98.2001 § 142.6 and found that Express's pre-lien notice was timely and therefore its mechanics' lien was valid and enforceable by foreclosure. The trial court dismissed with prejudice Purcell's claims against Express and overruled Purcell's Cross-Motion for Summary Judgment. Finally, the trial court awarded Express $6,159.00 in principal and $858.13 in interest, as well as $2,683.20 in attorney fees and $50.00 in costs. Express appeals the amount of attorney fees awarded. The record presents no dispute of material fact. The dispute is one of law: whether pre-lien notice required by 42 0.8.2001 § 142.6(B) must be sent no later than 75 days after the first or last date materials or labor were supplied. On de novo review of this first impression issue, we find the statute requires pre-lien notice to be sent no later than 75 days after the last day the lien claimant supplied labor, services, materials or equipment on the project. We therefore affirm summary judgment in favor of Express. We find no abuse of discretion in the trial court's decision on the amount of attorney fees, and therefore we also affirm that award.
T2 Summary judgment proceedings are governed by Rule 18, Rules for District Courts, 42 0.8.2001, Ch. 2, App.1. Summary judgment is appropriate where the record establishes no substantial controversy of material fact and the prevailing party is entitled
to judgment as a matter of law. Brown v. Alliance Real Estate Group, 1999 OK 7, 976 P.2d 1043, 1045. The parties agree on the facts material to this dispute. Where the facts are not disputed, an appeal presents only a question of law. Baptist Bldg. Corp. v. Barnes, 1994 OK CIV APP 71, ¶ 5, 874 P.2d 68, 69. In its Petition in Error, Purcell has alleged the issue of law is the interpretation of 42 00.98.2001 § 142.6(B). We review issues of law de novo.
T3 The record shows that Purcell entered a contract with Kerr 3 for the construction of a strip mall on property owned by Purcell in McClain County. Kerr 3 subcontracted with Express, among other parties.
Express first supplied labor, services, materials, or equipment for the project July 17, 2006, and Express last supplied materials, services, labor, or equipment February 20, 2007. Express filed its Lien Statement with the McClain County Clerk April 10, 2007. The parties do not dispute that Express timely filed the lien statement within 90 days of the date on which material was last furnished, as required by 42 0.8.2001 § 148.
T4 However, as a subcontractor, Express also was charged with providing a "pre-lien notice" to the property owner pursuant to 42 0.8.2001 § 142.6
Express mailed its Pre-Lien Notice to Purcell March 28, 2007 and it was received April 2, 2007. The parties purport to dispute whether Express sent the pre-lien notice within the time allowed by
§ 142.6, but the dispute is over when the time allowed by § 142.6 begins.
T5 Whether the 75 days begins after services or materials are first supplied, after they are last supplied, or sometime in between, is unclear. At the hearing on attorney fees, the parties and the trial court agreed the statute was not clear.
"The test for ambiguity in a statute is whether the statutory language is susceptible to more than one reasonable interpretation. Whether language is ambiguous is a question of law." YDF, Inc. v. Schlumar, Inc., 2006 OK 32, 16, 136 P.3d 656. Because the mechanics' lien statutes provide for deadlines triggered by both the beginning and end of Henable service, yet § 142.6 does not include a specific modifier of "after ... supplied," we find § 142.6(B) is susceptible to more than one reasonable interpretation. Accordingly, we find the time limit imposed for providing pre-lien notice is ambiguous as a matter of law.
In construing ambiguous statutory lan
guage, we look to the various provisions of the legislative scheme to determine the legislative intent and the public policy underlying that intent. Id.
§6 Mechanics' liens are statutory liens which protect the right to payment of those supplying material, labor, services, or equipment in the construction, alteration, or repair of any improvement on land. First Nat. Bank of Pauls Valley v. Crudup, 1982 OK 132, 656 P.2d 914, 917; 56 C.J.S. Me-chanies' Liens, § 1. In Oklahoma, statutory provisions for mechanies' Hens are codified at 42 0.9.2001 §§ 141-154. Because such liens are created by statute, they exist in derogation of the common law and therefore must be strictly construed. Riffe Petroleum Co. v. Great Nat. Corp., Inc., 1980 OK 112, 614 P.2d 576, 579. However, once a mechanic's lien is found to exist, it will be liberally enforced. Id. "The purpose of the mechanic's & materi-almen's lien statute is to protect materialmen and laborers, to secure payment of claims, and to give notice to the owners and to third parties of the intent to claim a lien for a definite amount. The recording requirement also protects innocent purchasers." Davidson Oil Country Supply Co., Inc. v. Pioneer Oil & Gas Equipment, 1984 OK 65, 689 P.2d 1279, 1280-1281.
T7 Oklahoma law protects property owners by requiring subcontractors to give owners notice of mechanics' liens, which allows owners to withhold payment to the general contractor until they are sure the subcontractor will be paid by the general contractor.
The Oklahoma Supreme Court long ago explained that the lien and notice statute:
fully provides protection to the owner by staying action by the contractor against the owner for 60 days against having impressed upon his property liens of subma-terialmen for material furnished in the erection of a building. That the defendant did not avail itself of such protection against loss, but paid the contractor prior to the expiration of the 60 days from the time the material was furnished, for the payment of which the lien is invoked, cannot be considered as defeating the lien. 'The provisions of the mechanies' lien law should be interpreted so as to carry out the object had in view by the Legislature in enacting it, namely, the security of the classes of persons named in the act, upon its provisions being in good faith substantially complied with on their part.!
Free access — add to your briefcase to read the full text and ask questions with AI
KENNETH L. BUETTNER, Judge.
T1 Defendant/Cross-Plaintiff/Appellant/Cross-Appellee Purcell Investments, LLC, (Purcell) appeals from the trial court's March 27, 2009 Journal Entry of Judgment which granted summary judgment against Purcell and Defendant Kerr 3 Construction Group, LLC, in favor of Third-Party Defendant/Cross-Defendant/Appellee/Cross-Appel-lant Express Fire Protection, Inc. (Express). The trial court interpreted 42 00.98.2001 § 142.6 and found that Express's pre-lien notice was timely and therefore its mechanics' lien was valid and enforceable by foreclosure. The trial court dismissed with prejudice Purcell's claims against Express and overruled Purcell's Cross-Motion for Summary Judgment. Finally, the trial court awarded Express $6,159.00 in principal and $858.13 in interest, as well as $2,683.20 in attorney fees and $50.00 in costs. Express appeals the amount of attorney fees awarded. The record presents no dispute of material fact. The dispute is one of law: whether pre-lien notice required by 42 0.8.2001 § 142.6(B) must be sent no later than 75 days after the first or last date materials or labor were supplied. On de novo review of this first impression issue, we find the statute requires pre-lien notice to be sent no later than 75 days after the last day the lien claimant supplied labor, services, materials or equipment on the project. We therefore affirm summary judgment in favor of Express. We find no abuse of discretion in the trial court's decision on the amount of attorney fees, and therefore we also affirm that award.
T2 Summary judgment proceedings are governed by Rule 18, Rules for District Courts, 42 0.8.2001, Ch. 2, App.1. Summary judgment is appropriate where the record establishes no substantial controversy of material fact and the prevailing party is entitled
to judgment as a matter of law. Brown v. Alliance Real Estate Group, 1999 OK 7, 976 P.2d 1043, 1045. The parties agree on the facts material to this dispute. Where the facts are not disputed, an appeal presents only a question of law. Baptist Bldg. Corp. v. Barnes, 1994 OK CIV APP 71, ¶ 5, 874 P.2d 68, 69. In its Petition in Error, Purcell has alleged the issue of law is the interpretation of 42 00.98.2001 § 142.6(B). We review issues of law de novo.
T3 The record shows that Purcell entered a contract with Kerr 3 for the construction of a strip mall on property owned by Purcell in McClain County. Kerr 3 subcontracted with Express, among other parties.
Express first supplied labor, services, materials, or equipment for the project July 17, 2006, and Express last supplied materials, services, labor, or equipment February 20, 2007. Express filed its Lien Statement with the McClain County Clerk April 10, 2007. The parties do not dispute that Express timely filed the lien statement within 90 days of the date on which material was last furnished, as required by 42 0.8.2001 § 148.
T4 However, as a subcontractor, Express also was charged with providing a "pre-lien notice" to the property owner pursuant to 42 0.8.2001 § 142.6
Express mailed its Pre-Lien Notice to Purcell March 28, 2007 and it was received April 2, 2007. The parties purport to dispute whether Express sent the pre-lien notice within the time allowed by
§ 142.6, but the dispute is over when the time allowed by § 142.6 begins.
T5 Whether the 75 days begins after services or materials are first supplied, after they are last supplied, or sometime in between, is unclear. At the hearing on attorney fees, the parties and the trial court agreed the statute was not clear.
"The test for ambiguity in a statute is whether the statutory language is susceptible to more than one reasonable interpretation. Whether language is ambiguous is a question of law." YDF, Inc. v. Schlumar, Inc., 2006 OK 32, 16, 136 P.3d 656. Because the mechanics' lien statutes provide for deadlines triggered by both the beginning and end of Henable service, yet § 142.6 does not include a specific modifier of "after ... supplied," we find § 142.6(B) is susceptible to more than one reasonable interpretation. Accordingly, we find the time limit imposed for providing pre-lien notice is ambiguous as a matter of law.
In construing ambiguous statutory lan
guage, we look to the various provisions of the legislative scheme to determine the legislative intent and the public policy underlying that intent. Id.
§6 Mechanics' liens are statutory liens which protect the right to payment of those supplying material, labor, services, or equipment in the construction, alteration, or repair of any improvement on land. First Nat. Bank of Pauls Valley v. Crudup, 1982 OK 132, 656 P.2d 914, 917; 56 C.J.S. Me-chanies' Liens, § 1. In Oklahoma, statutory provisions for mechanies' Hens are codified at 42 0.9.2001 §§ 141-154. Because such liens are created by statute, they exist in derogation of the common law and therefore must be strictly construed. Riffe Petroleum Co. v. Great Nat. Corp., Inc., 1980 OK 112, 614 P.2d 576, 579. However, once a mechanic's lien is found to exist, it will be liberally enforced. Id. "The purpose of the mechanic's & materi-almen's lien statute is to protect materialmen and laborers, to secure payment of claims, and to give notice to the owners and to third parties of the intent to claim a lien for a definite amount. The recording requirement also protects innocent purchasers." Davidson Oil Country Supply Co., Inc. v. Pioneer Oil & Gas Equipment, 1984 OK 65, 689 P.2d 1279, 1280-1281.
T7 Oklahoma law protects property owners by requiring subcontractors to give owners notice of mechanics' liens, which allows owners to withhold payment to the general contractor until they are sure the subcontractor will be paid by the general contractor.
The Oklahoma Supreme Court long ago explained that the lien and notice statute:
fully provides protection to the owner by staying action by the contractor against the owner for 60 days against having impressed upon his property liens of subma-terialmen for material furnished in the erection of a building. That the defendant did not avail itself of such protection against loss, but paid the contractor prior to the expiration of the 60 days from the time the material was furnished, for the payment of which the lien is invoked, cannot be considered as defeating the lien. 'The provisions of the mechanies' lien law should be interpreted so as to carry out the object had in view by the Legislature in enacting it, namely, the security of the classes of persons named in the act, upon its provisions being in good faith substantially complied with on their part.!
It therefore clearly appears that any payment made to the original contractor by the owner, prior to the expiration of 60 days, is paid at his own risk, and if, during said time a subcontracting materialman files his lien and gives notice to the owner, as is admitted in this case, the lien of such subcontracting materialman is a valid one upon the lands and buildings embraced in the original contract. That such subcontracting materialman has a direct lien upon the condition of filing same and giving notice to the owner,. ...
W.E. Caldwell Co. v. John Williams-Taylor Co., 1915 OK -, 50 Okla. 798, 150 P. 698, 699-700 (citations omitted).
18 Prior to 1977, mechanies' liens were granted to subcontractors who 1) had filed a lien statement within 90 days after the date labor or services were last provided and 2) had served written notice of the lien on the owner of the land. 42 0.8.1971 § 148. Oklahoma courts held that this notice must be given "within a reasonable time" after filing the lien statement. Curry v. Morgan, 1958 OK 36, 321 P.2d 973, 974; Unmion Bond & Investment Co. v. Bernstein, 1914 OK 162, 139 P. 974, 40 Okla. 527.
T9 In 1977, the legislature deleted the requirement of written notice to the owner from § 148 and instead included the notice requirement in a new statute. 42 0.8.Supp. 1977 § 148. The new section directed that "on the date of the filing of the hen statement, a motice of such lien shall be mailed ... to the owner of the property on which the lien attaches...." 42 O.8.Supp. 1977 § 148.1 (emphasis added). Section 148.1 also directed that the notice was to be mailed by the county clerk. Id. In 1979, § 148.1 was again amended to provide that notice must be mailed "within one (1) business day after the date of filing of the lien statement ..." 42 O.S.Supp.1979 § 148.1 (emphasis added).
10 In 2000, § 148.1 was changed more dramatically. The previous § 148.1 was renamed subsection A, and a subsection B was added. Section 148.1(B) provided that a lien claimant who was owed payment by a contractor was required to send written notice of the unpaid amount to the property owner and the contractor "not later than the tenth day of the third month following each month in which the unpaid" services or materials were furnished.
111 That language lasted only one year, when in 2001, § 142.6 was added, and the language from § 148.1(B) quoted above was deleted. Section 142.6 has not been amended since, nor has it been interpreted. The longstanding rule that notice to the owner is an inherent element of a mechanic's lien's validity has evolved from requiring notice within a reasonable time after the filing of the lien, to requiring notice at the time of the lien statement, and now to the deadline in § 142.6.
The trial court's interpretation of the statute effectively gives the owner 15 days notice before the lien statement must be filed-if the pre-lien notice is filed within 75 days and the lien statement is filed within 90 days, both from the last date lienable services or materials were supplied.
12 Both its name and the text of § 142.6 establish that a subcontractor's "pre-lien" notice must be filed before the lien statement.
As noted above, a subcontractor has up to 90 days after the last date materials or labor are supplied in which to file the lien statement. The Oklahoma Supreme Court has explained that "a subcontractor has a 'Henable claim' upon the commencing of work or furnishing of materials .... such lienable claim remains inchoate throughout the construction period and for 90 days after the date upon which the subcontractor last furnished materials or performed labor. . . ." Shawver & Son, Inc. v. Tefertiller, 1989 OK 60, 772 P.2d 396, 399.
18 In its brief opposing summary judgment, Purcell relied on the language in § 142.6(B)(2), stating that a subcontractor need only file one pre-lien notice, which will "protect the claimant's lien rights for any subsequent supply of material, services, ... furnished during the course of a construction project." Purcell contended this language established that the legislature intended for the pre-lien notice to be filed within 75 days of the date materials were first provided, based on Purcell's assertion that there would be no need for a pre-lien notice to remain effective for subsequent supplies if the notice could be filed after the materials were last supplied. At first blush, Purcell's contention appears reasonable. However, effectively, such an interpretation would require every person providing services or materials which could possibly be subject to a mechanic's lien to file a pre-lien statement, even if the subcontractor is being paid, as a precautionary measure in case payments later stop more than 75 days after labor or materials are first provided, but before the project ends. We will not presume the legislature intended for every subcontractor to give a pre-lien notice, regardless of whether he is being paid. If the legislature had such an intent, it could simply have included all subcontractors in the § 142.1 requirement of notice prior to first commencing work on owner-occupied dwellings. The 75 days after provision is superfluous if all subcontractors must give notice.
Additionally, even before the enactment of § 142.6, the Oklahoma Supreme Court noted that a mechanic's lien claimant is not required to file a separate lien statement for each order of materials. Roofing & Sheet Metal Supply Co. v. Golzar-Nejad Khalil, Inc., 1996 OK 101, 925 P.2d 55, 59. The court noted its previous holding that where materials are ordered at different times, but all for use on one construction project, the orders form one account on which a lien statement may be filed within 90 days after the last material was furnished. Id. citing Cushing Country Club v. Board-
man, Co., 1963 OK 83, 381 P.2d 856. In the case of large projects, the subcontractor may have no way of knowing the lien amount, or whether one will be required, within 75 days of first providing services, before final payment is due.
T15 We next note that the lien notice requirement remains in § 148.1, which leads to the question whether the new provision for a "pre-lien notice" is a new, additional notice required, rather than a modification of the existing notice requirement. The title of the bill creating § 142.6 suggests that the bill addressed the existing notice requirements for liens and, as noted above, notice of liens has been required since long before § 142.6.
The title of the bill does not suggest that the legislature intended to create an additional notice, such that the "pre-lien" notice would be required, followed by the § 148.1 notice. Instead, we find § 142.6 simply elaborates on the long-standing requirement of notice of a mechanies' and material-man's lien. By contrast, § 142.1 provides for a specific type of notice, along with a separate deadline of before commencement of work, for potential Hens against owner-occupied dwellings. That section has been interpreted as providing for a "specific pre-en-foreement notice of potential materialman's liens." C & C Tile and Carpet Co., Inc. v. Aday, 1985 OK CIV APP 8, 697 P.2d 175.
{16 The content of the $ 142.1 notice required for owner-occupied dwellings differs dramatically from the content required in the § 142.6 pre-lien notice. Those differences also support a finding that the pre-lien notice is not analogous to the notice for owner-occupied dwellings and do not support a finding that the pre-lien notice is required early in the project, as the notice for owner-occupied properties is required before lienable labor or materials are first provided.
{17 As noted above, in interpreting an ambiguous statutory provision we look to the purpose and intent of the statutory scheme. Our decision in this case is supported by the fact that none of the purposes of the mechanics' lien statutes would be served by adopting Purcell's interpretation that pre-lien notice must be given within 75 days after labor or materials were first supplied. Purcell's interpretation would serve only to render otherwise valid liens unenforceable despite timely notice to the owner, before the lien statement was filed, at a time when the owner remained able to protect his interests. Notice to the owner before the lien statement is filed protects the interests of owners and subcontractors. On the other hand, declaring a lien unenforceable solely by virtue of making notice of a lien due before payment is due (and indeed before it is known whether a lien will be necessary) serves only to benefit the property owner at the unnecessary expense of the subcontractor.
T 18 We recognize that the legislature may have intended to require pre-lien notice to be filed early in a project, as urged by Purcell. Nevertheless, because as noted above, historically, notice of a lien was required to be given at the time of filing the lien statement, along with the fact that owners are still protected by the timing rules in the mechanics lien statutes, we do not find an intent to institute such a sweeping change in policy with § 142.6. This is particularly so because such change would not further the purpose of the lien statutes. In the Journal Entry, the trial court announced "(the applicable time to serve pre-lien notice is not prior to performing labor or supplying materials; but rather, no later than seventy-five (75) days after the last date of work." We affirm the trial court's finding that Express's pre-lien notice was timely under the statute. However, we clarify that under § 142.6(B), the time period for pre-lien notice is not 75 days after the last date of work; it is 75 days after the
lien claimant last supplied lienable services or materials on the job.
119 For the reasons expressed above, we conclude the trial court correctly interpreted § 142.6(B). The statute requires a pre-lien notice to be given no later than 75 days after labor, services, material or equipment have last been supplied by the lien claimant.
120 In its cross-appeal, Express complains that the trial court abused its discretion in the amount of attorney fees it awarded. Express was entitled to an award of fees because it prevailed in an action to enforce a lien. 42 00.98.2001 § 176; 12 0.8. 2001 § 986. Where a party is entitled to an award of fees, the determination of the amount is left to the trial court's discretion, and we will not disturb that finding absent an abuse of discretion. Finnell v. Seismic, 2003 OK 35, ¶ 8, 67 P.3d 339. In its Motion to Assess Costs and Attorney's Fees, Express sought an award of $8,277.25 in attorney fees.
Purcell objected, in part based on its claim that the amount of fees requested exceeded the amount of the lien. At the hearing on attorney fees, the parties stipulated that $89.42 was a proper blended hourly rate. In the Journal Entry, the court awarded $2,683.20, which was based on 80 hours at $89.44 per hour. The court indicated it reduced the amount to which the parties stipulated based on the amount of Express's lien. The trial court acted within its discretion in making the fee award. The trial court has discretion to award fees lower than the amount of hours actually billed after consideration of the factors announced in State ex rel. Burk v. City of Oklahoma City, 1979 OK 115, 598 P.2d 659. Southwestern Bell Telephone Company v. Parker Pest Control, Inc., 1987 OK 16, 737 P.2d 1186.
AFFIRMED.
MITCHELL, C.J. (sitting by designation), and BELL, P.J., concur.