Taylor Bros. v. Gill

1927 OK 286, 259 P. 238, 126 Okla. 293, 54 A.L.R. 979, 1927 Okla. LEXIS 144
Supreme Court of Oklahoma·Decided September 13, 1927·No. 17605·Published·Cited by 11 cases

Opinion

LESTER, J.

The parties to this action appear in this court in the same relation as in the district court.

The plaintiffs brought an action against the defendants for the balance alleged to be due them on account of having furnished to the defendants certain plumbing fixtures together with labor performed in installing the same.

One of the defendants, John Semke, had entered into a contract with the defendant Mattie Gill to erect a certain building on a lot located in the Harndale addition of Oklahoma City.

Semke during the progress of the work made a contract with the plaintiffs to furnish and install certain plumbing fixtures in said building.

It appeared that there was an unpaid balance due the plaintiffs, and the plaintiffs sought judgment against the defendant Semke for the balance due on said contract, and also a judgment foreclosing a lien against the property of the defendants Mattie Gill and B. P. Gill.

The two lastmamed defendants filed a general denial to the plaintiffs’ petition. The cause was tried to the court and resulted in a judgment in favor of the plaintiffs for the unpaid balance against John Semke. but the court denied a recovery against the defendants Mattie Gill and B. P. Gill. Prom the judgment of the court in favor of the defendants Gill, the plaintiffs have perfected their appeal to this court.

Prom an examination of the record, together with the briefs filed in the case, we find that there is but one question for review here.- It is shown by the record that the building was completed on or about the 20th day of August, 1924. The defendants *294 Gill took possession of the building on August 30, 1924.

The plaintiffs filed their lien claim in the office of the court clerk of Oklahoma county, Okla., on the 6th day of November, 1924. The defendants Gill contended that the contract had been completed long prior to the 60-day period in which the plaintiffs filed their lien claim under section 7463, O. 0. S. 1921.

It appears that shortly after the defendants Gill took possession of the said property, they found that a certain tank which had been installed by the plaintiffs was defective. Semke, the principal contractor, called the attention of the plaintiffs to the condition of the tank, whereupon the plaintiffs removed said tank and substituted another one on the 10th day of September, 1924, and the substitution of this tank has caused the question to be raised as to whether the lien of the plaintiffs, which was filed on the 6th day of November, 1924, was within 60 days after the date upon which material was last furnished or labor last performed under the subcontract, as provided by section 7463, O. O. S. 1921.

No charge was made by the plaintiffs in replacing the substituted tank.

Joe Taylor, on behalf of the plaintiffs, testified in part, as follows (O.-M. 36) :

“Q. Now, on September 10th, all you did was to put in a new tank in the closet in the place of a defective one, is that right? A. Yes. Of course the plumber might have done other work there. I can’t say as to that. Q. Did you make any extra charge for that new tank? A. No, sir.”

The plaintiffs in their brief cite only the following statement of law to sustain their proposition:

“The provisions of the mechanic’s lien law should be interpreted so as to carry out the object had in view by the Legislature in enacting it, namely, the security of the classes of persons named in the act upon its provisions being in good faith substantial y complied -with ” Eberle v. Drennan, 40 Okla. 59, 136 Pac. 162.

We have examined this case from which the above statement is taken, and we find that the facts there were wholly different from the facts in the instant case, nor do we believe, under the most liberal construction •that may be given the provisions of the mechanic’s lien law, that a failure to file the lien claim within statutory time can be excused.

In the case of Bryan v. Orient Lumber & Coal Co., 55 Okla. 370, 156 Pac. 897, it was said:

“While the law providing for a material-man’s lien should be liberally construed to effectuate the object of the law, it is a condition precedent to the establishment of such lien that the proper lien statement be filed with the clerk of the proper district court, within the time provided by section 3863, Bev. Laws 1910, if the party seeking the lien be an original contractor, and within the time provided by section 3864, Bev. Laws 1910, if the parties seeking the lien be a subcontractor; and such subcontractor must also give notice of the filing of such lien statement to the owner.”

And in the body of the opinion the court said :

“The materialman’s lien is a creature of statute; and while it must be liberally construed to effect the beneficent purpose of the law, yet it is a condition precedent to effectuating a lien that the lien statement be filed in the office of the clerk of the district court of the proper county within the time prescribed by law, and such time must be estimated from the time the last item of material was furnished.”

The rule is well established also that work of the nature relied on by the plaintiffs in this case for an extension of the time within which to file their lien statement does not effect such an extension. The case of Jones v. Balsley & Rogers, 27 Okla. 220, 111 Pac. 942, appears to be the first case decided by this court on that question. The case arose prior to statehood and was governed by the Arkansas statutes, but the provisions of the Arkansas statutes applicable were similar in all essential respects to our present statutes. The following quotation from the body of the opinion shows the facts upon which the opinion was based and the conclusion of the court thereon:

“The lien was filed on the 29th day of April, 1903. The claim of lien filed does not show that any material was furnished within the 60 days next preceding that date, except there is a charge made on March 4,1903, for ‘4 Lights Glass, 20x33’; but the master found that this item of material was furnished to take the place of broken glass, and that no extra charge was made therefor. * * * It is not contended that the lien was filed in time unless the item furnished on March 4th extended the time within which to file it for the next last item was furnished on the 23-'d day 0f the preceding January. But the furnishing of material gratuitously, to take the place of defective material theretofore furnished and charged, does not operate to extend the statutory time for filing the lien. Homeopathic Assn. v. Harrison. 120 Pa. 28. 13 Atl. 501, Congdon *295 v. Kendall, 53 Neb. 282, 73 N. W. 659, King et al. v. Shipbuilding Co., 50 Ohio St. 320, 34 N. E. 436, Cole v. Clark. 85 Me. 336, 27 Atl. 186, 21 L. R. A. 714.”

The decision of the court is summarized in the fourth paragraph of the syllabus as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Taylor Bros. v. Gill, 1927 OK 286, 259 P. 238, 126 Okla. 293, 54 A.L.R. 979, 1927 Okla. LEXIS 144 (Okla. 1927).

1927 OK 286 (Taylor Bros. v. Gill) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Phillips Petroleum Co. v. United States Fidelity & Guaranty Co.
1968 OK 23 (Supreme Court of Oklahoma, 1968)
Cushing Country Club v. Boardman Company
1963 OK 83 (Supreme Court of Oklahoma, 1963)
H. E. Leonhardt Lumber Co. v. Ed Wamble Distributing Co.
1963 OK 17 (Supreme Court of Oklahoma, 1963)
Liberty Plan Co. v. Francis T. Smith Lumber Co.
1961 OK 30 (Supreme Court of Oklahoma, 1961)
California Nursery Co. v. United States
102 Ct. Cl. 173 (Court of Claims, 1944)
Bailey Meter Co. v. Owens-Illinois Glass Co.
108 F.2d 468 (Seventh Circuit, 1939)
Metropolitan Casualty Ins. Co. v. Dolese Bros. Co.
1933 OK 4 (Supreme Court of Oklahoma, 1933)
Morgan v. O'Malley Lumber Co.
7 P.2d 252 (Arizona Supreme Court, 1932)
Clark v. Oklahoma Electric Co.
1930 OK 174 (Supreme Court of Oklahoma, 1930)