Phillips Petroleum Co. v. United States Fidelity & Guaranty Co.

1968 OK 23, 442 P.2d 303, 1968 Okla. LEXIS 297
CourtSupreme Court of Oklahoma
DecidedFebruary 20, 1968
Docket40943
StatusPublished
Cited by27 cases

This text of 1968 OK 23 (Phillips Petroleum Co. v. United States Fidelity & Guaranty Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Phillips Petroleum Co. v. United States Fidelity & Guaranty Co., 1968 OK 23, 442 P.2d 303, 1968 Okla. LEXIS 297 (Okla. 1968).

Opinion

HODGES, Justice.

This is an action by plaintiff Phillips Petroleum Company against defendant United States Fidelity & Guaranty Company to recover on defendant’s surety bond guaranteeing payment by W. E. Logan & Sons, a copartnership, hereafter called principal. Plaintiff sued defendant on the bond to recover for materials plaintiff furnished to principal for performance of its contract with the Oklahoma Highway Department on Federal Aid Project No. F-53 (20), in Tulsa and Okmulgee Counties.

Requirement of the bond and procedure for its enforcement, contemporary with the bond and contract here involved, is set forth in 61 O.S.Supp.1955, §§ 1 and 2, as follows:

“§ 1. Bond to be taken on public works Whenever any public officer shall, under the laws of the State of Oklahoma, enter into contract in any sum exceeding One Hundred Dollars ($100.00) with any person or persons, for the purpose of making any public improvements or constructing any public building or making repairs on the same, such officer shall take, from the party contracted with, a bond with good and sufficient sureties to the State of Oklahoma, in a sum not less than the sum total in the contract, conditioned that such contractor or contractors shall pay all indebtedness incurred for labor, material, rental or repair of machinery or equipment furnished in the construction of said public building or in making said public improvements.
§ 2. Filing of Bond — Action on bond Such bond shall be filed in the office of the clerk of the district *305 court of the county in which such public improvement is to be made or such public building is to be erected, and any person to whom there is due any sum for labor, material, rental or repairs furnished as stated in the preceding sections, or his assigns may bring an action on said bond for the recovery of said indebtedness; provided, that no action shall be brought on said bond after- six (6) months from the completion of said public improvements or public buildings.”

The principal has been fully paid for its work by virtue of its contract with the Oklahoma Highway Department. Delivery by plaintiff of the materials involved to principal and its use of them on the project is stipulated. The project was completed June 27, 1957, and the action was commenced by plaintiff March 10, 1958, more than six months after completion of the project, which forms the basic issue of this appeal. The more than five years delay before trial after commencement of the action is not an issue. Plaintiff pleads waiver and estoppel of the defendant to plead the six (6) months provision of § 2, above, retailing the representations and acts of the defendant which lulled plaintiff into not filing its action within the six month period because of its reliance thereon.

The issues were joined by defendant’s unverified Answer to plaintiff’s Petition and verified account, and plaintiff’s reply to defendant’s answer.

The case was submitted to the trial court without a jury, and judgment was entered for defendant. Attached to the Journal Entry of Judgment was a Memorandum which contained specific findings by the trial court. Plaintiff has appealed.

Plaintiff has presented four propositions of error upon which it seeks reversal. We consider one of them decisive of this appeal. It focuses on the question of defendant’s estoppel to rely upon the limitation provision of 61 O.S.Supp.1955, § 2.

Defendant contends that the limitation provision,

“ * * * that no action shall be brought on said bond after six (6) months from the completion of said improvements or public buildings.”,

is not subject to plaintiff’s plea of waiver or estoppel. Defendant further contends that if the limitation provision is subject to the pleas of waiver and estoppel, the evidence is insufficient to establish either.

The gist of defendant’s position which would deny to plaintiff its plea of estoppel as against the limitation provision of the statute, is that a provision limiting commencement of an action which is contained in a statute which itself creates a new liability and a remedy for its enforcement, is not an ordinary limitation, but is an extinguishment of the remedy. We have recognized the existence of such a distinction in limitation provisions, and have held that when the provision is contained in a statute or statutes which create a new liability and provide for a new remedy for enforcement of that new liability the provision of limitation is not subject to estop-pel. Hiskett v. Wells, Okl., 351 P.2d 300. See also Saak v. Hicks, Okl., 321 P.2d 425.

The first question to be decided, then, is whether 61 O.S.1961, §§ 1 and 2 create a new liability or a new right and provide for a new remedy, neither of which would exist independent of these sections.

Defendant cites one case, Metropolitan Casualty Ins. Co. of N. Y. v. Dolese Bros. Co., 163 Okl. 36, 20 P.2d 569, interpreting the sections herein involved which is authority for its position. The pertinent portion of the Court’s opinion in that case follows:

“The section provides a remedy in derogation of the common law, and provides for the maintenance of an action against a surety on the bond, which, in the absence of the statute could not be maintained. The action authorized by *306 the statute can be maintained only when it is commenced within six months from the date the public improvement is completed. The burden was upon the plaintiff to show that the action was commenced within the authorized time. See Glazier v. Heneybuss et al., 19 Okl. 316, 91 P. 872; Chouteau v. Hoss et al., 118 Okl. 76, 246 P. 844; Zahn v. Obert et al., 60 Okl. 118, 159 P. 298; Chicago Bridge & Iron Works v. Walker et al., 120 Okl. 244, 251 P. 478; and Taylor Bros. v. Gill et al., 126 Okl. 293, 269 P. 236, 54 A.L.R. 979.”

Of the cases cited with approval in the above quotation, only Chicago Bridge & Iron Works v. Walker, supra, deals with the statutes here under consideration. The others deal with statutes clearly of the creative variety.

In Chicago Bridge & Iron Works, supra, the surety defendant pleaded the six month provision, which the Court called a “statute of limitation”, and, although applying the provision as a bar to that action, held,

“The parties might have done everything prior to the passage of the statutes [§§ 7486 and 7487, C.O.S.1921, and now 61 O.S.1961 §§ 1 and 2] that was enumerated and required in section 7486 in relation to the builders bond.”,

and

“The right of action in favor of builders and materialmen on the bond will be barred, unless the action be commenced within six months from the date of the completion of the public inprovements or public building, unless the acts or conduct of the surety against whom the judgment is sought operates to estop such surety from pleading the limitation.” (Emphasis supplied.)

and in its discussion of the six month provision, the Court said:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

VANGUARD BUILDERS, INC. v. GRANITE RE, INC.
2015 OK CIV APP 35 (Court of Civil Appeals of Oklahoma, 2014)
Thaxton v. Beneficial Mortgage Co.
2006 OK CIV APP 101 (Court of Civil Appeals of Oklahoma, 2006)
Jenkins v. Evergreen National Indemnity Co.
30 F. App'x 879 (Tenth Circuit, 2002)
Cruse v. Board of County Commissioners
1995 OK 143 (Supreme Court of Oklahoma, 1995)
Eskridge v. Ladd
1991 OK 3 (Supreme Court of Oklahoma, 1991)
Fischer v. Atlantic Richfield Co.
774 F. Supp. 616 (W.D. Oklahoma, 1989)
Golsen v. ONG Western, Inc.
756 P.2d 1209 (Supreme Court of Oklahoma, 1988)
Trent Ex Rel. Trent v. Board of County Commissioners
755 P.2d 615 (Supreme Court of Oklahoma, 1988)
Matter of Estate of Speake
1987 OK 61 (Supreme Court of Oklahoma, 1987)
Szarkowski v. Reliance Insurance Co.
404 N.W.2d 502 (North Dakota Supreme Court, 1987)
Jarvis v. City of Stillwater
1987 OK 5 (Supreme Court of Oklahoma, 1987)
Hart v. Bridges
1979 OK 31 (Supreme Court of Oklahoma, 1979)
Oklahoma Gas and Electric Company v. Chez
1974 OK 99 (Supreme Court of Oklahoma, 1974)
Lister v. Great American Insurance
484 P.2d 156 (Utah Supreme Court, 1971)
Gasteam Radiator Co. v. United States Fidelity & Guaranty Co.
1970 OK 121 (Supreme Court of Oklahoma, 1970)
Adams v. Wolff
190 P.2d 665 (California Court of Appeal, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
1968 OK 23, 442 P.2d 303, 1968 Okla. LEXIS 297, Counsel Stack Legal Research, https://law.counselstack.com/opinion/phillips-petroleum-co-v-united-states-fidelity-guaranty-co-okla-1968.