Meshek v. Cordes

1933 OK 345, 22 P.2d 921, 164 Okla. 40, 1933 Okla. LEXIS 743
CourtSupreme Court of Oklahoma
DecidedMay 31, 1933
Docket21281
StatusPublished
Cited by33 cases

This text of 1933 OK 345 (Meshek v. Cordes) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meshek v. Cordes, 1933 OK 345, 22 P.2d 921, 164 Okla. 40, 1933 Okla. LEXIS 743 (Okla. 1933).

Opinion

MeNEIDD, J.

The question involved in the instant case is whether the district court of Osage county erred in sustaining the separate demurrers of some of the defendants to the petition of plaintiff. The parties will be referred to as they appeared in the trial below.

It appears that the State Highway Commission entered into a certain contract with Osage Construction Company, a copartnership, composed of J. E. Beecher, Ray Betts, and Jim Moss, residents of Osage county, for the improvement of a certain portion of the state highway in Osage county, and that said company executed a statutory bond required by sections 7486 and 7487, C. O. S. 1921 [O. S. 1931, secs. 10983. 10984], wherein it was named as principal and Citizens Trust Company of Pawhuska, Okla., a corporation, was named, as surety. The bond was approved by the Highway Commission, and it required the principal to pay all the indebtedness incurred for the labor and material furnished in the construction of said state highway project. It further appears that said company entered into a contract with P. J. Cordes, a resident of Noble county, for a certain portion of said work, and that said Cordes in turn contracted with Tom Meshek, plaintiff herein, for certain labor and material furnished on said project.

Meshek claims he was not paid for said labor and materials. 1-Ie has filed two suits in an attempt to recover on his claim of indebtedness incurred by reason of this project.

The first action was filed in Noble county, and was thereafter dismissed for tho reason that the court had no jurisdiction over the defendants of Osage county. Plaintiff did not appeal from said order of dismissal.

Thereafter plaintiff filed the instant case in the district court of Osage county on 'May 2i3, 1929. Summons was served on said defendants in Osage county on May 25, 27, 1929. Summons was issued to Noble county for service on P. J. Cordes, which was served on May 24, 1929. Thereafter, on June 25, 1929, the defendants of Osage county filed separate motions to require the plaintiff to *42 make his petition more definite and certain in two respects: First, when the work was completed; and, second, the dates between which the work was done. The defendant Cbrdes filed his answer and cross-petition on July 8, 1929, wherein he sought judgment against the Osage Construction Company and the Citizens Trust Company for the amount they were indebted to him by reason of said project. Thereafter the plaintiff, on August 20, 1929, filed an amendment to his petition, setting forth that he completed the work on or about March 9, 1928, and that the items of labor were performed between October 26, 192-7, and March 9, 1928. The defendants of Osage county, being the defendants in error herein, filed separate demurrers to the amended petition on the grounds that there was a misjoinder of causes of action; misjoinder of defendants; that the petition, as amended, did not state a cause of action; and that any pretended cause of action attempted to be stated was barred by the statute of limitations. On November 4, 1929, the court sustained these demurrers; the plaintiff refused to plead further, and the court dismissed the pretended causes of action.

It is the contention of the plaintiff that the action in Osage county was not barred under sections 7486 and 7487, C. O. S. 1921 [O. S. 1931, secs. 10983, 10984], which sections require that an action on a bond for the recovery of money judgment for labor and materials furnished on a state highway project must be brought within six months from the completion of said public improvement ; that the petition as amended does not show that the Osage- county action was brought more than six months after the completion of said improvement project, and that, even though it was so barred under said sections, it was still maintainable under the provisions of section 190. C. O. S. 1921 [O. S. 1931. sec. 106], providing that when an action fails otherwise than on its merits, a new action may be brought within one year from the date of such failure.

The defendants contend:

1. The action was barred by the provisions of section 7487. C. O. S. 1921, when the suit was filed in Osage county.
2. The action was barred under the provisions of section 7487. C. O. S. 1921, at the time the pretended suit in Noble county was t commenced as to each of these defendants.
3. The pretended suit in Noble county cannot be considered as .a basis for the extension of the one year granted by section 190, C. O. S. 1921.
4. The pretended suit in Noble county will not serve toi grant the privilege of the additional year for the reason that no service was had upon these defendants in error in that suit until after the statute of limitations had already run.
5. The suit in Osage county is not the same as the pretended suit in Noble county, therefore section 190, C. O. S. 1921, has no application.
6. The sustaining of the demurrers and the dismissing of plaintiff’s suit was proper, independent of the statute of limitations.

'.The jpetition filed in the Instant ease shows on its face that another action had been commenced in Noble county on June 30, 1928, and was prosecuted until April 22, 1920, at which time it was dismissed by the court; that summons had been duly issued out of said court and served on P. J. Cordes; that a summons was also issued to Osage county, return of which was never made, against the Citizens Bank & Trust Company of Bawhuska; that said company filed its motion to quash on the ground that upon the date the secretary of said company was served, the president and vice president were within Osage county; that this motion was sustained by the district court of Noble county on November 12, 1928; that thereafter an amended petition was filed; that thereafter an alias summons was issued and served on said Citizens Bank & Trust Company, and also summons was issued and served on, the Osage Construction Company; and that thereafter separate motions to quash on behalf of said Osage Construction Company and Citizens Bank & Trust Company were filed.

These motions were sustained by the district court of Noble county on April 12, 1929, for the reason, as assigned by the district court of Noble county, that the court had no jurisdiction over said defendants.

gection 7487, supra, provides that no action shall be brought on a bond taken on public works after six months from the completion of said public improvements. The amended petition is not demurrable on that ground, because it does not appear from the face of the petition and amendment thereto that the public project involved therein had been completed six months prior to the institution of the present action. The date of the completion of the public project not being shown on the face of the amended petition, the bar of this *43 statute cannot be raised by demurrer, but may be raised by answer. Green Construction Co. v. Empire District Electric Co., 92 Okla. 127, 218 P. 1074; Betz v. Wilson, 17 Okla. 283, 87 P. 844; Chellis v. Coble (Kan.) 15 P. 505; Tucker v. Hudson, 38 Okla. 790, 134 P. 21; Mitchell v. Ripley (Kan. App.) 49 P. 153.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

STATE FARM MUTUAL AUTOMOBILE INSURANCE CO. v. PAYNE
2017 OK 95 (Supreme Court of Oklahoma, 2017)
Hung Duc Bui v. IBP, Inc.
205 F. Supp. 2d 1181 (D. Kansas, 2002)
Ross v. Kelsey Hayes, Inc.
1991 OK 83 (Supreme Court of Oklahoma, 1991)
Wiley Electric, Inc. v. Brantley
1988 OK 80 (Supreme Court of Oklahoma, 1988)
White v. Taylor
1986 OK CIV APP 29 (Court of Civil Appeals of Oklahoma, 1986)
Eaton v. Weaver Manufacturing Co.
582 F.2d 1250 (Tenth Circuit, 1978)
Minker v. St. Louis-San Francisco Railway Co.
574 F.2d 1056 (Tenth Circuit, 1978)
C & C Tile Co. v. Independent Sch. Dist. No. 7 of Tulsa Cty.
1972 OK 137 (Supreme Court of Oklahoma, 1972)
Phillips Petroleum Co. v. United States Fidelity & Guaranty Co.
1968 OK 23 (Supreme Court of Oklahoma, 1968)
Powell v. Chastain
1961 OK 28 (Supreme Court of Oklahoma, 1961)
Crossett v. Andrews
277 P.2d 117 (Supreme Court of Oklahoma, 1954)
Underwood v. Pinson
1953 OK 337 (Supreme Court of Oklahoma, 1953)
May v. City Nat. Bank & Trust Co.
1953 OK 396 (Supreme Court of Oklahoma, 1953)
Myers v. Kansas, O. & G. Ry. Co.
1948 OK 242 (Supreme Court of Oklahoma, 1948)
Anthony v. Barton
1945 OK 342 (Supreme Court of Oklahoma, 1945)
Smith v. Ogle
1945 OK 314 (Supreme Court of Oklahoma, 1945)
Springfield Fire Marine Ins. Co. v. Chadwick
1944 OK 273 (Supreme Court of Oklahoma, 1944)
Haught v. Continental Oil Co.
1943 OK 159 (Supreme Court of Oklahoma, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
1933 OK 345, 22 P.2d 921, 164 Okla. 40, 1933 Okla. LEXIS 743, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meshek-v-cordes-okla-1933.