Green Construction Co. v. Empire District Electric Co.

1923 OK 619, 218 P. 1074, 92 Okla. 127, 1923 Okla. LEXIS 798
CourtSupreme Court of Oklahoma
DecidedSeptember 18, 1923
Docket14248
StatusPublished
Cited by7 cases

This text of 1923 OK 619 (Green Construction Co. v. Empire District Electric Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Green Construction Co. v. Empire District Electric Co., 1923 OK 619, 218 P. 1074, 92 Okla. 127, 1923 Okla. LEXIS 798 (Okla. 1923).

Opinion

Opinion by

RUTH, 0.

On April 23, 1921, the Empire District Electric Company, defendant in error, and hereafter designated as plaintiff, filed its petition in the district court for Ottawa county against the Green Construction Company, one of the plaintiffs in error, and hereinafter designated as defendant, and the Southern Surety Company, plaintiff in error, hereinafter designated as surety, in which said petition the plaintiff alleges that on or about the 12th day of December, 1919, the Green Construction Company entered into a contract with the town of Cardin, whereby the siaid construction company was to extend the water works and sewer plant, pumping machinery and equipment, and erect a steel water tower and tank for said town, and that the Green Construction Company, on the 13th day of December, 1919, executed to the state of Oklahoma a statutory bond, in which said bond the Southern Surety Company became surety for the construction company, and the conditions of the said obligation or bond, after-reciting that a certain contract between the said Green Construction Company with the town of Cardin was entered into, provides in the usual form, that in default of the principal to pay for all labor and material necessary to complete the said contract, this bond should remain in full force and enect, said bond being- in the sum of $48,160.

The plaintiff further alleges that one S. S. Potter was employed by the Green Construction Company as its purchasing- agent, and as such purchasing- agent, S. S. Potter, acting for the Green Construction Company, purchased from the plaintiff two K. W. 2200 B. S. Phase transformers, which said transformers were used in the construction of the water works and sewer system in the town of Cardin under the contract aforementioned and the same were so used, and that the contract price for the. said transformers was $420 and that the Southern Surety Comparty was surety on the bond of the Green Construction Company, and that demand had been made upon Green Construction Company for payment for the said transformers, which payment had been refused, and therefore the plaintiff brings this action against the construction company, and the surety company, upon the statutory bond, copy of which bond is set up and made a part of the plaintiff’s petition.

In the original petition, the town of Cardin and S. S. Potter were made parties defendant, but suit was dismissed as against the town of Cardin and S. S. Potter prior to the trial of this cause. To this petition, the Southern Surety Company files its answer, denying that the Green Construction Company purchased the transformers from the plaintiff and denying that the construction company owes the plaintiff anything, and further answering alleges that the claim of the plaintiff as against the defendant surety company was barred by the statute of limitation at the' time the suit was instituted, for the reason that more than six months had elapsed since the completion of the public improvements involved in the contract relating to the pumping plant, and recites the substance of section 3882, Rev. Laws 1910, wherein it is specifically provided that no action shall be brought on said bond after six months after the completion of said improvements or said public building.

The Green Construction Company, after filing its answer, consisting of a general denial, obtained leave of the court to file its amended answer, -in which it admits the execution of the written contract to complete the work according to plans and specifications, but alleges that the contract, plans, and specifications have been lost and that they have no copy of same, but that the said plans and specifications and contract in no manner set forth and describe the said transformers as part of the pumping machinery and that the words “pumping machinery and equipment” were never intended by the contracting parties to comprise or take into consideration the transformers, that they were to be used in reducing the current so that same was capable of being delivered to the town of Oardin.

The construction company further denies that it ever purchased the transformers or that any officer or agent in its employ was ever authorized to purchase said transformers, or that the construction company ever offered to pay for the same.

To the various answers, the plaintiff filed its reply and the cause came on for trial on the 20th day of October, 1922, before a Jury in the district court of. Ottawa county, and after trial had, the jury returned its verdict in favor of the plaintiff and against the defendants, and upon refusal of the court to grant a new trial, this cause is regularly brought here for review.

The, first contention that will be considered by this court is that of the surety company, wherein it is claimed the action was barred by the statute of limitations, by reason of the fact that the same was not brought within six months after the com *129 pletion of the contract, the claim being made that the contract was completed aDout July 20, 1920, and action was not filed until April, 1921.

Section 3881, Rey. Laws 1910, provides that:

“Whenever any public officer shall, under the laws of the state, enter into contract in any sum exceeding $100, with any person or persons for purpose of making any public improvements, or constructing any public buildings. or making repairs on the same, such officer shall take from the party contracted with, a bond with good and sufficient sureties to the state of Oklahoma, in a sum not less than the sum total in the contract, conditioned that such contractor or contractors shall pay all indebtedness incurred for labor or material furnished in the construction of said public building or in making said public improvements.”

Section 3882, Rev. Laws 1910, provides:

“Such bond shall be filed in the office of the clerk of the district court of the county in which such public improvement is to be made or such public building is to be erected; and any person to whom there is due any sum for labor or material furnished, as stated in the preceding section, or his assigns, may bring an action on said bond for the recovery of said indebtedness; Provided, that no action shall be brought on said bond after six months from the completion of said public improvements or public buildings.”

The surety company relying upon this statute requested the court to instruct the jury that this action was barred by the statute of limitations, in that it was not brought within six months after the completion of the public improvements referred to in the plaintiff’s petition. The surety company further requested the court to instruct the jury that the term “completion” of public improvements had been judicially determined by some of our courts, and that as a matter of law, where public improvements are built by a contractor and turned over to a city or municipality and the contractor abandons ail further work on them, this act of his is a completion or bringing to an end or termination of his work and this act on his part tolls the statute of limitations. They further requested the court to instruct the jury that the word “completion” as used in the stature is synonymous with s”ch words and phrases as “bringing to a close”, “termination”, “ending”, etc., and if the jury finds the defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Georgia State Savings Ass'n v. Elias
1943 OK 47 (Supreme Court of Oklahoma, 1943)
McDonald v. Bruhn
1942 OK 175 (Supreme Court of Oklahoma, 1942)
Meshek v. Cordes
1933 OK 345 (Supreme Court of Oklahoma, 1933)
Federal Intermediate Credit Bank v. Cosby
1928 OK 635 (Supreme Court of Oklahoma, 1928)
Reed v. Anderson
1927 OK 334 (Supreme Court of Oklahoma, 1927)
Puget Sound Power & Light Co. v. Sparger
252 P. 544 (Washington Supreme Court, 1927)
Chicago Bridge & Iron Works v. Walker
1926 OK 813 (Supreme Court of Oklahoma, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
1923 OK 619, 218 P. 1074, 92 Okla. 127, 1923 Okla. LEXIS 798, Counsel Stack Legal Research, https://law.counselstack.com/opinion/green-construction-co-v-empire-district-electric-co-okla-1923.