Puget Sound Power & Light Co. v. Sparger

252 P. 544, 142 Wash. 85, 1927 Wash. LEXIS 1039
CourtWashington Supreme Court
DecidedJanuary 19, 1927
DocketNo. 20164. Department Two.
StatusPublished
Cited by1 cases

This text of 252 P. 544 (Puget Sound Power & Light Co. v. Sparger) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Puget Sound Power & Light Co. v. Sparger, 252 P. 544, 142 Wash. 85, 1927 Wash. LEXIS 1039 (Wash. 1927).

Opinion

Bridges, J.

Demurrers to the amended complaint having been sustained, the plaintiff elected to stand upon its pleading, and a judgment was entered dismissing the action. .

*86 As stated by the complaint, the facts are these: On April 28, 1923, the city of Seattle entered into a contract with the respondent Sparger, whereby the latter obligated himself to construct a- certain public improvement. Shortly thereafter, he executed a bond to the city for the purpose of complying with the statutes hereinafter mentioned, the respondent, The Aetna Casualty & Surety Company, being the surety. In September, 1923, Sparger entered into a written contract with the appellant, Puget Sound Power & Light Company, whereby it was to furnish to the contractor electric energy for light and power purposes in connection with the performance of the work. Under this contract, power and light were furnished, the value of which was a designated sum, which has not been paid. The contractor never completed the improvement, and the city at no time has accepted the work. On January 14, 1924, the city declared the contractor to have forfeited his contract,, refused to permit him to further proceed with the work, and ejected him from the premises.

About a year and seven months after the city had terminated the contract, and on August 7,1925, the appellant filed with the proper city officer its notice of claim against the bond taken by the contractor for the amount due it, and about four months later, and on December 3, 1925, the appellant filed with the proper city officer its notice of lien on the fund reserved by the city from moneys earned by the contractor. At the time the latter was ejected from the premises, he had earned under his contract, and was entitled to receive from the city, $10,967.60, out of which the city had paid to various creditors of the contractor, for work, materials and provisions, $6,726.15, and there remained in its hands $4,241.45, that amount being more than sufficient to pay the appellant’s demand. It will *87 thus be noticed’that by this action the appellant sought not only recovery against the bond, but also to establish a lien against the fund remaining in the hands of the city. We will first dispose of the claim against the bond.

Section 1159, Rem. Comp. Stat. [P. C. § 9724], provides that, when any municipality shall let a contract similar to that involved here, it shall require the contractor to furnish a bond, conditioned that he shall not only faithfully perform his contract but also “pay all laborers, mechanics and subcontractors and materialmen, and all persons who shall supply such person or persons, or subcontractors, with provisions and supplies for the carrying on of such work.”

Section 1161, Rem. Comp. Stat. [P. C. § 9727], provides that all persons intended to be protected by the bond shall have a right of action on it, “provided, that such persons shall not have any right of action on such bond for any sum whatever, unless within thirty (30) days from and after the completion of the contract with an acceptance of the work” by the city, notice be filed with the proper city officer that the bond will be looked to for payment. It is appellant’s contention that it has thirty days after the completion of the work contracted for within which to give the statutory notice, and that, since the complaint alleges that the work has not yet been completed, the notice was filed in time. The respondent surety company contends that the notice, must be filed within thirty days after the termination of the contract by the action of the city, that being, it is asserted, the “completion of the contract,” and that, since such notice was not filed for several months after that time, it is too late.

While there are statutes of several states that are similar to ours, there is only one which has been called *88 to our attention, or which we have found, that is almost identical, and that is the statute of Tennessee. Our statute provides that the notice of claim against the bond shall be filed within thirty days from and after “the completion of the contract” and the acceptance of the work. The Tennessee statute provides that the notice shall be filed within thirty days after “the contract is completed.” In the case of City of Bristol v. Bostwick, 139 Tenn. 304, 202 S. W. 61, it was held that where a contractor on a public building was enjoined from continuing the work, the filing of claims within thirty days from the time of the issuance of the injunction was a sufficient compliance with the statute, the court, holding that the contract was completed when the injunction was lawfully issued, saying that

“When the principal contractor abandons the work, as when his affairs are placed in the hands of a receiver, so far as he is concerned, he has terminated his contract. He has completed all the work he intends to do thereunder, and for the purpose of filing laborers’ claims such a contract is completed.”

When the case again came before the court it appeared that the city of Bristol had taken over the contract and completed it, and the court held “that the legal termination of the contract occurred on March 26, 1917, when the work was taken over by the city, and that only such claims as were properly filed within 30 days after such date come within the executed bond.” City of Bristol v. Bostwick, 146 Tenn. 205, 240 S. W. 774.

In the case of Kimball v. Parks, 151 Tenn. 103, 268 S. W. 117, the question was again before the court. The facts there were that the contractor became insolvent and quit the work, which was finished by the surety. Within thirty days after the contractor abandoned the work, a materialman served notice of *89 his claim, against the bond. After citing the cases above mentioned, the court said:

“The circumstance that the surety took over the work does not remove this case from the authority of those cited, in our opinion, nor does it defer the liability of the surety, nor postpone the time for filing claims, for materials already furnished. The principal contractor, to cover whose default the bond was required, has none the less abandoned the job, although the job is completed by the surety, instead of by the city. ’ ’

The foregoing cases certainly support the view taken by the respondent surety company. There are other cases, however, which must be noticed.

In the case Hull v. Massachusetts Bonding & Ins. Co., 86 Kan. 342, 120 Pac. 544, the statute provided that no action should be commenced on the bond “after six months from the completion of said public improvements or public buildings.” The court held that, where the contractor abandoned the work, suit might be commenced on the bond at any time within six months after the improvement or building is actually finished, no matter by whom. In Coyle v. United States Gypsum Co., 64 Okl. 153, 166 Pac.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Puget Sound Bridge & Dredging Co. v. Jahn & Bressi
268 P. 169 (Washington Supreme Court, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
252 P. 544, 142 Wash. 85, 1927 Wash. LEXIS 1039, Counsel Stack Legal Research, https://law.counselstack.com/opinion/puget-sound-power-light-co-v-sparger-wash-1927.