VANGUARD BUILDERS, INC. v. GRANITE RE, INC.

2015 OK CIV APP 35, 348 P.3d 1093, 2014 Okla. Civ. App. LEXIS 114, 2015 WL 2058806
Court of Civil Appeals of Oklahoma·Decided November 25, 2014·No. 112,507·Published·Cited by 2 cases

Opinions

P. THOMAS THORNBRUGH, Judge.

{1 Vanguard Builders, Inc. (Vanguard), appeals a summary judgment in favor of Granite Re, Inc. (Granite), decided on the grounds that Vanguard did not file suit within the applicable limitations period to recover on a statutory bond made pursuant to 61 0.9.2011 §§ 1 and 2. We vacate the summary judgment for the reasons set forth below, and remand for further proceedings.

BACKGROUND

T 2 This appeal comes to us pursuant to 12 O.S8.2011 § 994, from a summary judgment made early in the underlying case. As a result, many of the facts which are recited for background are disputed. For the purposes of this opimion, we recite the disputed facts as alleged by Vanguard without commenting on any final disposition of these facts.

T3 Vanguard is a metal building, roofing, and siding contractor. In February 2011, Vanguard entered into a contract with the L. Wallace Construction Company, Inc., and Trilogy Development Group, Inc. (LWCC/Trilogy),1 to perform part of the construction of a gymnasium at Wilson Public Schools (School) in Wilson, Oklahoma. Trilogy was the main contractor, and Vanguard was a subcontractor. Pursuant to 61 O.S. 2011 §§ 1 and 2 (Bonding Statute), Trilogy obtained the required statutory bond (Bond) from Granite as surety, to cover any payments due to subcontractors if the main contractor defaulted. Trilogy paid Vanguard regular progress payments, but withheld a 10% "retainage." The total of the withheld payments was $37,600.

T4 Vanguard completed its portion of the work on January 20, 2012, and invoiced LWCC for the remaining $37,600 as final payment. LWCC replied that it was not required to make a final payment to Vanguard until final payment by School, which was due only on "substantial completion" of the project. LWCC told Vanguard that Sehool had not yet made this payment. Vanguard checked periodically with LWCC in the following months, but received a similar response.

T5 On October 1, 2012, after LWCC had again asserted that School had not paid, Vanguard inquired of School concerning the delay in payment. School informed Vanguard that all sums due to Trilogy had been paid. Vanguard later learned that Trilogy had received a final payment from School some four months earlier, on May 31, 2012.

[1095]*1095T6 On October 8, 2012, Vanguard notified Granite that LWCC had defaulted, and demanded payment of the $37,600 as a final payment pursuant to the Bond. Granite contacted Trilogy regarding the default. Trilogy replied that it disputed the claim for return of the $87,600 retainage because Vanguard had "gone over its allotted time" during several phases of construction. Later, Trilogy apparently informed Granite that it did not have to pay Vanguard because Vanguard was liable for a "charge back" due to alleged damage to School's gymnasium floor.

T7 Eleven weeks after notification, the dispute as to whether Trilogy was required to make the payment to Vanguard still had not been resolved. Vanguard states that, during this period, Granite represented that it would eventually pay, but that it could not do so until Trilogy determined the final amount owed to Vanguard. However, on February 4, 2013, one year and fifteen days after Vanguard last performed work at School, Granite denied the claim on the Bond.

1 8 On March 21, 2013, Vanguard filed suit against the Defendants. Vanguard's petition included a claim against Granite for payment of the $37,600, plus interest. On July 12, 2018, Granite filed a motion for summary judgment, alleging that Vanguard had failed to file suit to recover on the Bond within the one-year statute of limitation provided by the Bonding Statute. The district court granted Granite's motion. Vanguard appeals.

STANDARD OF REVIEW

T 9 "A moving party is entitled to summary judgment as a matter of law when the pleadings, affidavits, depositions, admission or other evidentiary materials establish that no genuine issue of material fact exists." Smith v. City of Stillwater, 2014 OK 42, ¶ 21, 328 P.3d 1192 (citing Miller v. David Grace, Inc., 2009 OK 49, ¶ 10, 212 P.3d 1223; and Davis v. Leitner, 1989 OK 146, ¶ 9, 782 P.2d 924). "In reviewing the grant or denial of summary Judgment, this Court views all inferences and conclusions to be drawn from the evidentiary materials in a light most favorable to the nonmoving party." Id. "Because a grant of summary judgment is purely a legal issue, this Court's standard of review on appeal is de novo." Id.

ANALYSIS

I. THE BONDING STATUTE

A. Statutory Text and Purpose

T 10 The statutory language in question is found in 61 0.$.2011 § 2(A), which states in relevant part:

Any person to whom there is due any sum for labor, material or repair to machinery or equipment, furnished as stated in Seetion 1 of this title, the heirs or assigns of such person, may bring an action on the bond for the recovery of the indebtedness, provided that no action shall be brought on the bond after one (1) year from the day on which the last of the labor was performed or material or parts furnished for which the claim is made.

This language originates in R.L1910, §§ 3881 and 3882.

At that time, § 8882 provided that:

. no action shall be brought on said bond after six months from the completion of said public improvements or public buildings.

In 1965, the Legislature amended the Bonding Statute, changing the limitations period from six months to one year. In 1968, the Legislature again amended the statute, changing the occurrence that triggered the running of the limitation period from the "completion of the building" to "the day on which the last of the labor was performed ... for which such claim is made." 1968 Okla,. Sess. Laws. ch. 77 § 2.

¶ 11 In Boren v. Thompson & Associates, 2000 OK 3, ¶ 16, 999 P.2d 438, the Oklahoma Supreme Court identified two "fundamental objective[s]" of the Bonding Statute: the first is "protecting laborers and materialmen on public construction projects who have no lien rights against public land or improvements"; the second is "saving the public from all liability for liens for material and labor furnished on public improvements." Id.

[1096]*1096B. Vanguard's Arguments and the Statutory Text

112 Vanguard brings two arguments. The first is that the right to call on the Bond did not accrue until the amount due was finally decided, and the limitation period thus did not begin to run until the right to payment was determined. The second is that Vanguard's right to payment did not accrue until the project was "substantially complete," i.e., at the time payment was made by School on May 31, 2012; hence, Vanguard had one year from that date to file suit.

1183 Both of these arguments appear to fail, since neither the date the payment was due, nor the date of substantial completion, trigger the running of the limitation period.

Free access — add to your briefcase to read the full text and ask questions with AI

VANGUARD BUILDERS, INC. v. GRANITE RE, INC., 2015 OK CIV APP 35, 348 P.3d 1093, 2014 Okla. Civ. App. LEXIS 114, 2015 WL 2058806 (Okla. Ct. App. 2014).

2015 OK CIV APP 35 (VANGUARD BUILDERS, INC. v. GRANITE RE, INC.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

VANGUARD BUILDERS, INC. v. GRANITE RE, INC.
2015 OK CIV APP 35 (Court of Civil Appeals of Oklahoma, 2014)