Jenkins v. Evergreen National Indemnity Co.

30 F. App'x 879
CourtCourt of Appeals for the Tenth Circuit
DecidedFebruary 19, 2002
Docket01-5042
StatusUnpublished

This text of 30 F. App'x 879 (Jenkins v. Evergreen National Indemnity Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jenkins v. Evergreen National Indemnity Co., 30 F. App'x 879 (10th Cir. 2002).

Opinion

ORDER AND JUDGMENT *

*880 PORFILIO, Circuit Judge.

After examining the briefs and appellate record, this panel has determined unanimously to grant the parties’ request for a decision on the briefs without oral argument. See Fed. RApp. P. 34(f); 10th Cir. R. 34.1(G). The case is therefore ordered submitted without oral argument.

In this diversity action, plaintiff Dale Jenkins appeals a grant of summary judgment in favor of third-party defendant Evergreen National Indemnity Company on Jenkins’ claim for recovery under a construction bond. Jenkins argues on appeal that the district court erred in holding that his claim was barred by the statutory one-year limitations period for materialmen to bring an action against the surety of a public works contractor. We , determine that, under the circumstances of this case, Evergreen may be equitably estopped from asserting a statute of limitations defense. Accordingly, we reverse the judgment against Jenkins and remand for further proceedings.

FACTUAL BACKGROUND

Jenkins is the assignee of a materials supplier to G.W. Starr Pipeline, Inc., the general contractor for a public works project for the City of Broken Arrow, Oklahoma. Evergreen issued a labor and materialman’s bond on the project, through an employee of its agent, Courtney & Associates. Although the employee wrote the bond in September 1997 and promptly sent a copy to the City for its statutorily-required records, she did so without the authorization of either Evergreen or Courtney. Evergreen’s underwriter accepted the bond in December 1997, but the bond’s existence was not reflected on Evergreen’s computer system.

Jenkins supplied materials to the project through February 18, 1998. Because Starr failed to make payment, Jenkins’ counsel pursued collection efforts against Starr and sought information on the project bond. He made an informal attempt to obtain a copy of the bond from the City, but did not follow through when told that Starr had performed a number of City projects, that the files were closed, and that the bonds on these projects could be obtained only through a formal open records act request. Jenkins’ counsel did not follow through on the open records act request.

Instead, he learned Courtney was Starr’s bonding agent and, on October 16, 1998, sent Starr a demand letter, with copies to Courtney and the City. Evergreen’s claims representative responded to the letter by informing Jenkins that Evergreen had not written a bond covering the supplied materials and advised that the applicable bond was probably issued by Chatham Reinsurance Corporation.

Jenkins filed suit against Chatham on May 25, 1999. Two months later, he discovered through correspondence from Courtney that, in fact, Evergreen had issued the applicable bond. Jenkins then asked for leave of court to amend his complaint to add Evergreen as a third-party defendant and moved to dismiss Chatham by stipulation of the parties. The amended complaint naming Evergreen was filed October 19,1999.

Evergreen moved for summary judgment on the ground that Jenkins’ suit was barred by Okla. Stat. tit. 61, § 2(A), which requires that an action for payment under a bond insuring a public works project is to be filed no later than “one (1) year from the day on which the last of the labor was performed or material or parts furnished.” Evergreen’s premise was that the claimed materials were last supplied on February 18, 1998, therefore Jenkins’ complaint should have been filed before February 18, 1999. Jenkins argued that Evergreen was equitably estopped from asserting a stat *881 ute of limitations defense because, through its agent, it had caused Jenkins to sue the wrong insurance company.

The district court rejected Jenkins’ argument, determining that it may have been “valid if Jenkins had sued Chatham within the one-year period and then tried to have the later claim relate back to the date that Chatham was sued.” Appellant’s App. at 312. The court reasoned, however, that “[wjhether Evergreen knew, or should have known, that [its] information was incorrect is irrelevant” to the summary judgment motion because “[t]he information given to Jenkins by Evergreen might have caused Jenkins to originally sue the wrong party, but it did not cause Jenkins to sue the wrong party after the February 18, 1999 deadline.” Id. at 313. Based on this rationale, the court granted Evergreen’s motion for summary judgment. This appeal followed.

DISCUSSION

On appeal, the district court’s grant of summary judgment is reviewed de novo, see Kaul v. Stephan, 83 F.3d 1208, 1212 (10th Cir.1996), affording no deference to the district court’s legal rulings concerning Oklahoma law, see Salve Regina Coll. v. Russell, 499 U.S. 225, 238-40, 111 S.Ct. 1217, 113 L.Ed.2d 190 (1991). We consider the evidence and all reasonable inferences drawn therefrom in the light most favorable to the nonmoving party. Cooperman v. David, 214 F.3d 1162, 1164 (10th Cir.2000). Summary judgment is proper if the record shows “that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Fed. R.Civ.P. 56(c). To avoid summary judgment, the nonmovant must establish, at a minimum, an inference of the presence of each element essential to the case. Hulsey v. Kmart, Inc., 43 F.3d 555, 557 (10th Cir.1994).

At the outset, we conclude that the district court erred in rejecting Jenkins’ equitable estoppel argument outright: the untimeliness of Jenkins’ suit against Chat-ham does not provide grounds for entry of summary judgment in favor of Evergreen. Instead, the proper focus is on whether Evergreen is estopped from relying on the one-year statute of limitations set out in Okla. Stat. tit. 61, § 2(A). 1

The Oklahoma Supreme Court has held that, with regard to actions on a public works bond, the limitation provision “is subject to waiver and estoppel where the necessary facts are established as in other instances of the application of waiver and estoppel to a statute of limitations.” Phillips Petroleum Co. v. United States Fid. & Guar., Co., 442 P.2d 303, 307 (Okla.1968).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Salve Regina College v. Russell
499 U.S. 225 (Supreme Court, 1991)
Cooperman v. David
214 F.3d 1162 (Tenth Circuit, 2000)
Phillips Petroleum Co. v. United States Fidelity & Guaranty Co.
1968 OK 23 (Supreme Court of Oklahoma, 1968)
Dixon v. Roberts
1993 OK CIV APP 15 (Court of Civil Appeals of Oklahoma, 1993)
Hillers v. Local Federal Savings & Loan Ass'n
1951 OK 57 (Supreme Court of Oklahoma, 1951)
Samuel Roberts Noble Foundation, Inc. v. Vick
1992 OK 140 (Supreme Court of Oklahoma, 1992)
Lacy v. Wozencraft
1940 OK 383 (Supreme Court of Oklahoma, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
30 F. App'x 879, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jenkins-v-evergreen-national-indemnity-co-ca10-2002.