Bartholomew v. James

246 P. 771, 76 Mont. 359, 1926 Mont. LEXIS 93
CourtMontana Supreme Court
DecidedMay 29, 1926
DocketNo. 5,923.
StatusPublished
Cited by9 cases

This text of 246 P. 771 (Bartholomew v. James) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bartholomew v. James, 246 P. 771, 76 Mont. 359, 1926 Mont. LEXIS 93 (Mo. 1926).

Opinion

MR. CHIEF JUSTICE CALLAWAY

delivered the opinion of the court.

During the years 1921 and 1922 George C. James was in the possession of a tract of land near Bozeman under a contract to purchase the same from Y. J. Kuinders. In September, 1921, James employed the plaintiff to build a greenhouse upon the land. There was no definite contract; the plaintiff made an estimate of the cost, and it was arranged that the building should be constructed by day labor. In addition to the labor, plaintiff was to, and did, furnish material for the building which was incorporated therein. On June 9, 1922, plaintiff filed a lien to secure the sum of $317.90 for labor and materials furnished in the construction of “that certain building consisting of a greenhouse, with ground dimensions about 30 feet by 62 feet, set on a concrete foundation with an addition built thereon now upon that certain lot, piece or parcel of land” *361 (describing it). In November, 1923, Kuinders commenced an action against James to declare a forfeiture of the contract under which James held possession of the land, and a decree in Kuinder’s favor was entered in January, 1924.

The amount claimed by plaintiff in his lien being unpaid, on January 4, 1924, he began an action to obtain judgment against James for the foreclosure of the lien. Kuinders and two others were made defendants. The plaintiff prayed that the amount claimed by him, with all costs including attorney’s fees, be adjudged a lien upon the buildings and that the buildings be sold under the order and decree of the court, in accordance with the statutes, and in conformity with the procedure of the court. The defendant Kuinders alone answered. After trial the court entered judgment and decree in favor of the plaintiff for the amount claimed, an attorney’s fee, and costs, with direction that the buildings be sold under execution to satisfy the same. From this judgment the defendant Kuin-ders has appealed.

1. The important question of fact in the case is whether the lien was filed in time. Plaintiff alleged in his complaint that between the fifteenth day of September, 1921, and the fourteenth day of March, 1922, both dates inclusive, he furnished the labor and materials for, and which actually were used in, the construction of “those certain buildings consisting of greenhouses and hothouses, one of which has ground dimensions of about 30 feet by 62 feet, set on a concrete foundation, and the other of which has ground dimensions of about 16 feet by 25 feet, and is located about 24 feet west of the building first above described, and which last mentioned building is described as an addition to said first mentioned building in the lien of the plaintiff heretofore filed.”

The principal building, which we shall refer to as the greenhouse, was substantially completed about the middle of November of that year and James occupied it at that time. The total cost of plaintiff’s labor and materials at that time was $446.40, and James had paid on the account sums amounting to $108. On December 27, 1921, he paid $25 more, which left a balance *362 due plaintiff on December 31, 1921, of $313.40, according to a statement plaintiff rendered James on that day. A small amount of work was done by plaintiff upon the greenhouse on January 15, 1922.

At the trial it was admitted that with the exception of the March 14th items the work and labor done and materials furnished by the plaintiff had been under a continuous open account and this was stipulated to include the item of January 15, 1922. Kuinders, referred to hereafter as the defendant, denied that plaintiff had done any work or furnished any material in the month of March. Plaintiff testified that upon March 14, 1922, he and one of his employees performed labor on the greenhouse amounting to $3.75, and placed therein a sash of the value of $3. At the same time, plaintiff said, he furnished material which went into the other building, “the addition,” of the value of $5.20. March 16, 1922, James paid plaintiff $9.25 on account. Plaintiff testified further that the original plan of the greenhouse contemplated four ventilator sashes. Three of these were put in during the main construction. The space for the fourth was boarded over prior to ceasing work in November; to that extent the building was unfinished ; plaintiff knew he still had to complete that part of the work; the fourth sash when placed in the building became a part of it and enhanced the structure to that extent.

The evidence is in sharp conflict upon this feature of the case. Counsel for defendants insists that it preponderates decidedly against the plaintiff and urges us to order judgment for his client. But the trial court had the superior advantage of hearing the testimony and observing the witnesses as they testified. There is substantial testimony to uphold the court’s finding in plaintiff’s favor, and, following the time-honored rule, we shall not disturb it.

But it is insisted that the facts proven demonstrate that the items of March 14th do not constitute a part of a continuous open account between plaintiff and James. This argument is based chiefly upon the lapse of time between the date work ceased in November, 1921, and March 14, 1922. Mere *363 lapse of time, while a circumstance of importance, is not conclusive upon the question. Whether the work and materials, commencing with the first item and ending with that of March 14, 1922, were furnished under one contract — under a continuous open account — was one of fact. (Western Iron Works v. Montana P. & P. Co., 30 Mont. 550, 77 Pac. 413; Morrow v. Dahl, 66 Mont. 251, 213 Pac. 602.) In Helena Steam-Heating & Supply Co. v. Wells, 16 Mont. 65, 40 Pac. 78, this court held the rule to be that when all the items of an account relate to one transaction, between the same parties, the account is to be deemed continuous regardless of different times of delivery, and the account dates from the day of the last item. The fact that plaintiff at various times rendered James statements of account does not of itself change the situation.

If the testimony of the plaintiff is true, and the court so found it, the item of March 14th, consisting of the ventilator sash and labor amounting to $6.75, was a bona fide one. It was therefore sufficient to sustain the lien. The item was contemplated in the original plan of the greenhouse. It was not a subterfuge for securing a lien. (Aldritt v. Panton, 17 Mont. 187, 42 Pac. 767.)

2. There was installed in the greenhouse by some one other than the plaintiff a heating plant with many connecting pipes. This the court held to constitute a part of the building, essential for the purpose for which it was erected, and adjudged that the lien of the plaintiff extends to and covers the whole of said building, including its entire heating plant and water system. Counsel for defendant contends this adjudication of the court is erroneous, and asks the question: “Is the heating plant a fixture within the meaning of the law, and subject to removal under the lien as a part of the building?” The question must be answered in the affirmative.

The testimony showed that the heating plant and steam-pipes are a part of the building.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Beck v. Hanson
589 P.2d 141 (Montana Supreme Court, 1979)
Frank J. Trunk & Son, Inc. v. DeHaan
391 P.2d 353 (Montana Supreme Court, 1964)
Cushing Country Club v. Boardman Company
1963 OK 83 (Supreme Court of Oklahoma, 1963)
Walsh-Anderson Company v. Keller
362 P.2d 533 (Montana Supreme Court, 1961)
Caird Engineering Works v. Seven-Up Gold Mining Co., Inc.
111 P.2d 1267 (Montana Supreme Court, 1940)
Dewey Lumber Co. v. McQuirk
30 P.2d 475 (Montana Supreme Court, 1934)
Interstate Lumber Co. v. Rider
19 P.2d 644 (Montana Supreme Court, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
246 P. 771, 76 Mont. 359, 1926 Mont. LEXIS 93, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bartholomew-v-james-mont-1926.