Ryndak v. Seawell

1904 OK 42, 76 P. 170, 13 Okla. 737, 1904 Okla. LEXIS 29
CourtSupreme Court of Oklahoma
DecidedMarch 4, 1904
StatusPublished
Cited by27 cases

This text of 1904 OK 42 (Ryndak v. Seawell) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ryndak v. Seawell, 1904 OK 42, 76 P. 170, 13 Okla. 737, 1904 Okla. LEXIS 29 (Okla. 1904).

Opinion

*741 Opinion of the court by

PANCOAST, J.:

Numerous objections were made in the court below, both to the sufficiency of the pleadings and to the introduction of evidence. All contentions, however, are abandoned in this court, save three; the first of which is that the demurrer to the petition of plaintiff below should have been sustained, because there was no allegation in the petition that the material sold and for which claim was made, was used in the construction of the building upon which the lien was claimed; second, that as to the material claimed to have been sold the contractor Matkin, the plaintiff was not a subcontractor, under the evidence, but a mere material man, and not entitled to any lien; third, that as to the material sold to the contractor Matkin, and for which plaintiff below claimed as a.' sub-contractor, there was n<o proof of the service of notice upon the owner as required by statute.

It is true that there is no direct allegation contained in the petition that the lumber sold to the contractor was used in the building. Was the defect in the petition in this respect properly challenged by the demurrer ?

The first ground of the demurrer, that there was a defect of parties, certainly did not reach this proposition. The second, that there were several causes of action improperly joined, did not reach, it. The third, that the petition did not state facts sufficient to constitute a cause of action, did not reach it. A general demurrer will not reach this proposition. The foreclosure of a mechanic’s lien is only ancillary to the main cause of action. The basis of the cause of action was the debt claimed to be due the plaintiff. The petition was sufficient as a cause of action upon an open account, *742 and even if the action as to the mechanic's lien had been eliminated, . still there was a, good cause of action stated in the petition. The mechanic's lien statement was sufficient for its purpose- The petition is defective, in that it does not contain a direct allegation that the material was,used in the-construction of the building. No proper objection, however,, being taken to the petition to reach this defect, either before or after pleading,. or on the trial of the ease,, it was waived, and the petition will be considered here as if the proper amendment had been made. (El Reno Electric Light & Telephone Company v. Jennison, 5 Okla. 760; Mulhall v. Mulhall, 3 Okla. 304.)

•More particularly should this rule be adhered to, there being no objection made to the introduction of evidence because of this defect in the petition. The record discloses that .there was ample evidence of the lumber having been used in the building, and this evidence was offered and introduced without any objection whatever that the petition did not contain an allegation that the lumber was so used. The-objection, in this respect, is. more or less a technical one, and, in order to have any force in this court, should have been urged in the proper way in the court below. This was not done; indeed, no effort was made in that direction.

Again, it will be noted that the answer and demurrer ' were both filed upon the same day. This is not the correct practice; and it is the rule, under codes like ours, that where an answer is filed before a decision is had upon a demurrer already on file, and there is but one cause of action stated in the petition, the answer will supersede the demurrer. We think that is the effect of filing the demurrer and the answer *743 upon the same day in this case. The answer should be held to have superseded the demurrer, and the trial to have proceeded as though no demurrer had been filed.

' The objection that the material man was not a subcontractor under the evidence, and was not entitled to any lien, is not well taken. The statement for a lien showed that a part of the lumber was furnished to the contractor Mat-kin and a part to Ryndak direct, the material man claiming to be a sub-contractor. The evidence was introduced, and the case was tried out principally .upon this theory, although the instructions to the jury were to the effect that if Ryn-dak, in. the cancellation of his contract with Matkin, assumed the obligations ' for the material purchased by Matkin, he then became personally responsible for them. Counsel’s argument that Seawell was not a sub-contractor within the meaning of the mechanic’s lien law, is very ingenious to.say the least; but we think their construction in this respect is a very narrow one, and is not borne out by the authorities upon this subject. It is true that the statute should not be enlarged 'beyond its express provisions; but it is equally true that it should not receive such a narrow construction as to exclude from its application persons or classes who are intended to be placed - within its protection. The rule that statutes in derogation of the common law shall be strictly construed, has no application here. This statute under contemplation should receive a liberal interpretation. Of course, it should not be so construed as to reach out and bring within its provisions persons not included within it, or so as to confer special privileges upon.them..

We think that where a material man enters into a con *744 tract with a contractor to furnish material for a building, which the contractor has agreed to build, and where the material man has knowledge of such contract, and makes his contract in relation thereto with the understanding that the material is to be used by the contractor in the building, he thereby becomes a sub-contractor within the meaning of the mechanic’s lien law, and if the material is used in the construction of the building, he is entitled to a lien. A subcontract is one made under a previous contract; and a subcontractor is one who takes a portion of a contract from the principal contractor.

In this case, Matkin had a contract for the construction of the entire building, which included the furnishing of all the material to be used therein. Seawell contracted with Matkin to furnish the material for the building. In doing so, he agreed to perform a part of the contract which Mat-kin had obligated himself to perform. Why, under such circumstances, should not Seawell be held to be a sub-contractor within the meaning of the mechanic’s lien law ? The statute provides that any person who shall furnish material under contract with a contractor, may obtain a lien. This means, of course, that a sub-contractor must contract with reference to the original contract. He must have knowledge of such original contract, and that the material is to be furnished for the property, and is to go to the betterment thereof; and the material must actually be used in the construction of the improvement to be made. When material is furnished under such circumstances, the material man becomes, within the meaning of the mechanic’s lien law, a sub-contractor, and is entitled to a lien under the pro *745 visions oí that act. (Springfield Boiler & Manufacturing Company v. Best [Kan.], 65 Pac. 239.)

The remaining contention is that there was no

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Welling v. American Roofing & Sheet Metal Co.
1980 OK 131 (Supreme Court of Oklahoma, 1980)
Poole v. Putensen
274 N.W.2d 277 (Supreme Court of Iowa, 1979)
J. T. Weybrecht's Sons Co. v. Hartford Accident & Indemnity Co.
161 Ohio St. (N.S.) 436 (Ohio Supreme Court, 1954)
Hardware Mut. Casualty Co. v. Hilderbrandt
119 F.2d 291 (Tenth Circuit, 1941)
Rogers v. Crane Co.
1937 OK 340 (Supreme Court of Oklahoma, 1937)
Standard Accident Insurance v. Deep Rock Oil Corp.
1937 OK 150 (Supreme Court of Oklahoma, 1937)
Standard Accident Insurance v. Basolo
1937 OK 149 (Supreme Court of Oklahoma, 1937)
Huddleston v. Nislar
72 S.W.2d 959 (Court of Appeals of Texas, 1934)
Utah Const. Co. v. United States
15 F.2d 21 (Ninth Circuit, 1926)
Dolese Bros. Co. v. Andrecopulas
1925 OK 171 (Supreme Court of Oklahoma, 1925)
He-to-op-pe v. Hanna
109 Okla. 126 (Supreme Court of Oklahoma, 1924)
In Re Wah-Kon-Tah-He-Um-Pah's Estate
1924 OK 1087 (Supreme Court of Oklahoma, 1924)
Price v. Preston
1924 OK 829 (Supreme Court of Oklahoma, 1924)
Mobley v. Leeper Bros. Lbr. Co.
1923 OK 185 (Supreme Court of Oklahoma, 1923)
Levy v. Tradesmen's State Bank
1920 OK 45 (Supreme Court of Oklahoma, 1920)
Simmons v. Chestnut-Gibbons Grocery Co.
1918 OK 270 (Supreme Court of Oklahoma, 1918)
First Nat. Bank of El Reno v. Davidson-Case Lumber
1915 OK 999 (Supreme Court of Oklahoma, 1915)
Antene v. Jensen
1915 OK 258 (Supreme Court of Oklahoma, 1915)
C. E. Sharp Lumber Co. v. Kansas Ice Co.
1914 OK 366 (Supreme Court of Oklahoma, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
1904 OK 42, 76 P. 170, 13 Okla. 737, 1904 Okla. LEXIS 29, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ryndak-v-seawell-okla-1904.