McGlumphy v. Jetero Const. Co., Inc.

1978 OK 154, 593 P.2d 76, 1978 Okla. LEXIS 562
CourtSupreme Court of Oklahoma
DecidedDecember 5, 1978
Docket48719
StatusPublished
Cited by11 cases

This text of 1978 OK 154 (McGlumphy v. Jetero Const. Co., Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McGlumphy v. Jetero Const. Co., Inc., 1978 OK 154, 593 P.2d 76, 1978 Okla. LEXIS 562 (Okla. 1978).

Opinion

LAVENDER, Vice Chief Justice:

Jetero Construction Co., Inc. (Jetero) was the general contractor on two separate construction projects owned by different entities. One, a motel, was located in Tulsa, Oklahoma. The other, an apartment complex, was located in Ft. Smith, Arkansas. Jetero’s electrical sub-contractor on both projects was Marvin Lasater, d/b/a Lasater Electric Company (Lasater). D. McGlum-phy, d/b/a Mae’s Electric Supply (Mac’s) was an electrical material supplier for Lasa-ter. There were other construction projects where this same relationship existed between these entities of general contractor, electrical sub-contractor, and supplier.

Mac’s claimed money was owed him for materials furnished for the Tulsa, Ft. Smith, and other projects, and subsequently filed materialman’s lien against the Tulsa and Ft. Smith projects in the proper counties where the projects were located. Jete-ro claims it cancelled its sub-contracts on these two projects with Lasater for failure to keep the projects free of lien claims, and claims additional expense in securing other completion of the electrical subcontracts. Lasater claims monies owed to him for completed electrical work on the projects.

To relieve the two real estate developments from the recorded liens, Mac’s entered into a written agreement with Jetero and Travelers Indemnity Company (Travelers). That agreement bound Jetero and Travelers to pay Mac’s claims, or parts thereof, ultimately determined by adjudication to be a lien, with Mac’s releasing its recorded liens. Suit by any of the parties to the agreement could be brought in the District Court of Tulsa County as to both projects. Other than litigating both claims in the same forum, there was no waiver of any objections, defenses, claims, rights, causes of action or remedies with Oklahoma law applicable to the Oklahoma and Arkansas law applicable to the Arkansas lien.

Mac’s brings an action against Jetero and Travelers containing a cause of action for each of the two projects. He pleads the agreement and asks judgment for payment of materials furnished and attorney fees. Jetero denies and pleads certain defenses. By counterclaim and by making Lasater a third.party defendant, Jetero seeks to impress particular funds paid by Lasater to Mac’s with a trust to pay lienable items on the project generating that particular payment. Jetero also seeks Lasater to Indemnify it from any recovery of Mac’s against Jetero, and money judgment against Lasa-ter for additional expenses required to complete Lasater’s electrical sub-contract on the two projects. Lasater cross-petitions against Jetero for money judgment against Jetero on alleged performed, but unpaid, electrical work on the two projects.

Trial was to the court. Judgment entered for Mac’s as sought in the petition, including attorney fees and denying any relief against that materialman, with Jetero and Travelers recovering a judgment in indemnity against Lasater for the amounts Jetero and Travelers were required to pay Mac’s. Jetero recovered judgment against Lasater for cost of completing the electrical sub-contracts. Lasater recovered judgment against Jetero for unpaid work performed on the sub-contracts. Both Jetero and La-sater were denied attorney fees as against each other. Jetero and Travelers appeal.

Though Mac’s original action is correctly based on the written agreement between that materialman, the general contractor and Travelers, we do not agree with Mac’s contention his action was on a “judicial bond.” The written agreement was an agreed-to mechanism whereby the real estate developments would be free of filed liens. Judicial energy was conserved by allowing litigation to proceed under the agreement in one forum with Oklahoma law applicable to the Oklahoma lien and Arkansas law applicable to the Arkansas lien. There were no waiver of objections, defenses, claims, rights, causes of action, or remedies under the laws of either state. Plead lien rights must be considered in this appeal.

*80 As to Mac’s recovery, Jetero’s and Traveler’s principal arguments are (1) material was sold on an open account and without a contract as to particular projects so as not to create a lien on individual projects; (2) lien trust fund statutes require payment on lienable items on the project generating the payment funds; and (3) failed to perfect the materialman’s lien under Arkansas law on the Arkansas project through proper notice. As to Lasater’s recovery, Jetero and Travelers contend there should be no recovery, for Lasater breached the sub-contract by failure to keep the projects free of lien claims.

Mac’s contends (1) as a materialman, performing part of the sub-contract, he is entitled to a lien on the projects; (2) payments to him from the sub-contractor could be applied as agreed to the oldest purchase owed and not to the material sold to the project generating the payment; and (3) substantial compliance with the Arkansas law to perfect that lien.

Lasater adopts the same positions as Jetero and Travelers except as to Lasater’s recovery; there contending, breach does not bar recovery for unpaid, but performed work.

For a materialman to be entitled to a lien under 42 O.S.1971, § 143 there need not be a direct contractual relation with the owner or the original contract, but it is essential that such materialman have knowledge of such a contract and furnish his materials in compliance with the original contract with the degree the material-man is removed from the original contractor being immaterial. Rogers v. Crane Co., 180 Okl. 139, 68 P.2d 520 (1937). In Rogers, supra, contention was made that notations or job numbers on invoices bore no legal significance and that fixtures were purchased by the sub-contractor in the course of ordinary trade with those purchases divorced from the improvement contract involving installation. This position was rejected. See also Dolese Bros. Co. v. Andre-copulas, 113 Okl. 18, 237 P. 844 (1925), Case 2.

In present case, general contractor argues the sale of electrical supplies to the electrical sub-contractor was in the ordinary course of trade with no connection to any particular contract to install or to any particular construction project. And, the material sale was without any contract and under an “open account” of the sub-contractor with the materialman.

The form of the indebtedness is not the vital element relative to a material-man lien. Open account, in legal as well as in ordinary language, means an indebtedness subject to future adjustment, and which may be reduced or modified by proof. 1 In Liberty Plan Co. v. Francis T. Smith Lumber Co., Okl., 360 P.2d 500 (1961), the indebtedness involving a materi-alman’s lien was in the form of a note. The lien there was upheld. However, there is no materialman’s lien if the seller relies wholly on the credit of the purchaser with no intention to resort to the lien statutes. Schuman v. Teague, 195 Okl. 328, 156 P.2d 1010 (1945). The definition of a sub-contractor, “as one who has entered into a contract, expressed or implied, for the performance of an act with a person who has already contracted for its performance,” has been applied to materialman’s liens. Dolese Bros. Co., supra.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fowler & Peth, Inc. v. Regan (In Re Regan)
326 B.R. 175 (D. Colorado, 2005)
Osborne v. Mollman Water Conditioning, Inc.
2003 OK CIV APP 20 (Court of Civil Appeals of Oklahoma, 2002)
Spectrum Paint Co. v. Chambers (In Re Chambers)
226 B.R. 915 (N.D. Oklahoma, 1998)
In Re Tefertiller
772 P.2d 396 (Supreme Court of Oklahoma, 1989)
Shawver & Son, Inc. v. Tefertiller
1989 OK 60 (Supreme Court of Oklahoma, 1989)
State Ex Rel. Oklahoma Bar Ass'n v. Lobaugh
1988 OK 144 (Supreme Court of Oklahoma, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
1978 OK 154, 593 P.2d 76, 1978 Okla. LEXIS 562, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcglumphy-v-jetero-const-co-inc-okla-1978.