Beach v. Stamper

74 P. 208, 44 Or. 4, 1903 Ore. LEXIS 2
Oregon Supreme Court·Decided November 16, 1903·Published·Cited by 13 cases

Opinion

Mr. Justice Wolverton,

after stating the facts in the foregoing terms, delivered the opinion.

The vital question to be considered is whether the liens claimed by plaintiff and Stamper can legally attach to the four dwellings for the lump sum which each has alleged to be due him. In plaintiff’s case the materials were furnished and used indiscriminately upon the buildings. It is' so declared in his claim of lien, and it is practically conceded, that the amount or value thereof used upon each house is not susceptible of segregation. In the case of Stamper it is stated generally in his claim of lien that the labor was performed upon all the buildings, but the statement of the account or demand segregates the value performed on each as follows: Labor on house No. 1, $32; No. 2, $40; No. 3, $22; No. 4, $28. The evidence also tends to support the claim in this form. This court has decided, upon a very careful and clear discrimination of adjudicated cases, that one who, under a single contract for a specified lump sum or price, has performed labor or furnished materials which were used indiscriminately in. the construction of several houses, erected separately, but upon adjoining lots owned by the same person, is entitled to claim a lien upon all the houses and lots jointly, and to include them all in one notice: Willamette Mills Co. v. Shea, 24 Or. 40 (32 Pac. 759). The controlling feature which induced the decision was that the contract for construction was single, embracing all the buildings for a lump and inseparable sum or price, thus treating the property as a whole and inseverable. “In such case,” it is said, “the contract relates to no particular building, but treats them as a whole, though they are, in point of fact, separate and distinct buildings.” ’ This is clearly manifest from the cases cited and discussed. Wall v. Robinson, 115 Mass. 429, is quoted from in part as follows: “In the case at bar [7] the petitioners have performed labor upon several buildings situated upon the same lot under an entire contract for an entire price. We think such a case is within the purpose of the statute and the intention of the legislature. The parties by their contract have connected the several buildings, and treated them as one estate. * * We are of opinion that when labor is performed or furnished under an entire contract in the erection or repair of several buildings owned by the same person and situated upon the same lot, a lien attaches upon the whole estate for the whole value of the labor performed, if the other conditions of the statute are fulfilled.” So, from Lax v. Peterson, 42 Minn. 214, 219 (44 N. W. 3): “But how have the parties to these building contracts treated the property, and not how the owner intends to use it after the completion of the houses, is the question. By contracting for the erection of these four houses under one entire contract, they have connected the two city lots and the several buildings, and treated the whole as one tract or estate.” And again, from Phillips v. Gilbert, 101 U. S. 721, 725: “The contract was one, and related to the row as "an entirety, and not to the particular building separately. The whole row was one building, within the meaning of the law, from having been united by the parties on one contract, as one general piece of work.”

It is by reason of this condition that the courts have been enabled to construe statutes relative to mechanics’ liens which generally employ the term “building,” or its equivalent iú the singular, as embracing more than structures separately situated, simply because the parties have treated the several structures by their contract as but a single one. In such case the lien asserted may be claimed and maintained upon the whole as if but one structure in fact. The doctrine has been carried even further in Fullerton v. Leonard, 3 S. Dak. 118 (52 N. W. 325), thus empha[8] sizing the principle. There two owners, each of a separate lot, joined in a contract for the erection of several buildings. The subcontractor, who furnished materials to be used in the construction of all under an entire contract with the builder, was allowed his single lien against the whole of the several buildings and the two lots upon which they stood as a single structure and estate; the court saying, among other things: “A joint lien upon several buildings, situated upon different lots, owned by the same persons, could not be maintained where a separate contract had been entered into by the owner and contractor; for by the several contract the inference would be that a separate account should be kept with each building. ' Not so when the contract covered several buildings to be erected for a gross amount without regard to the cost of each. So, if two or more several owners of lots or parcels of land wish to jointly contract for the erection of several buildings, to be situated upon the several pieces, for a definite and' specific sum in gross for all, without regard to the cost of either one, a joint lien may be asserted upon all for any balance due for the erection of such buildings.” The contract is therefore the controlling feature that unites the several structures and enables the court to say that they are but one building within the spirit and reasonable intendment of the statute. Other cases are cited by the learned chief justice who wrote the opinion in the case alluded to, to the same purpose, but it is unnecessary to refer to them further here.

Free access — add to your briefcase to read the full text and ask questions with AI

Beach v. Stamper, 74 P. 208, 44 Or. 4, 1903 Ore. LEXIS 2 (Or. 1903).

74 P. 208 (Beach v. Stamper) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Dimitre Electric Co. v. Paget
151 P.2d 630 (Oregon Supreme Court, 1944)
State Ex Rel. Sauers v. C. J. Montag Co.
286 P. 995 (Oregon Supreme Court, 1930)
National Loan & Exchange Bank of Columbia v. Argo Development Co.
139 S.E. 183 (Supreme Court of South Carolina, 1927)
Boise-Payette Lumber Co. v. Felt
258 P. 169 (Idaho Supreme Court, 1927)
Warrenton Lumber Co. v. Smith
245 P. 313 (Oregon Supreme Court, 1926)
McCormack v. Bertschinger
237 P. 363 (Oregon Supreme Court, 1925)
Exchange Nat. Bank v. Okeya Oil & Gas Co.
1924 OK 707 (Supreme Court of Oklahoma, 1924)
Christman v. Salway
205 P. 541 (Oregon Supreme Court, 1922)
Sheldon v. Chicago Bonding & Surety Co.
190 Iowa 945 (Supreme Court of Iowa, 1921)
Crane Co. v. Erie Heating Co.
112 P. 430 (Oregon Supreme Court, 1910)
Smith v. Wilcox
71 P. 708 (Oregon Supreme Court, 1903)