ASB CONSTRUCTION v. Bateman

863 P.2d 516, 124 Or. App. 638, 1993 Ore. App. LEXIS 1897
CourtCourt of Appeals of Oregon
DecidedNovember 17, 1993
Docket9106-03509 CA A74292 (Control), CA A75270
StatusPublished
Cited by2 cases

This text of 863 P.2d 516 (ASB CONSTRUCTION v. Bateman) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ASB CONSTRUCTION v. Bateman, 863 P.2d 516, 124 Or. App. 638, 1993 Ore. App. LEXIS 1897 (Or. Ct. App. 1993).

Opinion

*640 LANDAU, J.

This is a consolidated appeal arising from plaintiffs action to foreclose a construction lien. The main issue is whether plaintiff is entitled to recover additional attorney fees for the arbitration of contract claims that formed the basis of the lien.

Plaintiff, a building contractor, agreed to provide certain construction work for defendants. 1 The agreement, between plaintiff and defendants provided for arbitration of their contractual disputes. It also provided that the duties described “shall be in addition to and not a limitation of duties, obligations, rights and remedies otherwise imposed or available at law.” The contract did not mention attorney fees. During the course of plaintiffs construction work, a dispute arose between the parties over the work. Plaintiff filed a construction lien and gave the proper notice. Defendants demanded arbitration. Plaintiff then filed this action to foreclose its lien and to recover costs and attorney fees. The parties then stipulated to abatement of that action pending arbitration.

The arbitrator awarded plaintiff $193,879 and provided that “the parties shall each pay their own costs and attorneys’ fees.” Defendants were to pay $128,879 immediately and the balance when plaintiff had satisfied the liens of various subcontractors. About a month later, defendants paid plaintiff $128,879, and the parties stipulated to an order rescinding abatement of the foreclosure action. Defendants then filed their answer, affirmative defenses and counterclaims to plaintiffs remaining claim in the foreclosure action for the balance of the arbitration award.

Plaintiff moved for summary judgment foreclosing its lien, and it submitted a cost bill that included $54,159.95 for attorney fees, including fees related to the arbitration. Defendants cross-moved for summary judgment on the grounds that they had paid all that was due at that time, and *641 no additional amount was owed until plaintiff paid the subcontractors’ liens and that plaintiff was not entitled to attorney fees for the arbitration. Plaintiff subsequently satisfied the subcontractors’ liens and attached evidence of that to its responsive memorandum. The court granted summary judgment to plaintiff in the amount of $46,991 plus interest, denied defendant’s cross-motion and left costs and attorney fees for later determination.

Defendants tendered $47,860, the principal amount due plus interest, as “final payment under the Arbitration Award.” Plaintiff refused that tender, because the amount did not include payment of any attorney fees. Plaintiff then filed a motion for costs and attorney fees. It argued that it was entitled to fees for the arbitration under Harris v. Dyer, 292 Or 233, 637 P2d 918 (1981). According to plaintiff, in Harris, the court held that the plaintiff in a foreclosure action may recover attorney fees for an arbitration of the underlying dispute if attorney fees are allowed by the contract at issue. Plaintiff argued that it was entitled to attorney fees in this action, because its construction contract with defendants contained a reservation of rights provision identical to the one found in Harris to permit the collection of attorney fees. Defendants disagreed.

At the .hearing on plaintiffs motion, the trial judge said:

“THE COURT: Basically, the only thing that distinguishes this case from [Harris v.] Dyer is that the arbitrator expressly denied attorney fees. * * * I tend to agree * * * that Harris is on point, but I think that it’s a very ill-considered decision. The realities of the marketplace just cannot permit this kind of thing. * * * And it totally destroys the whole concept which has been common practice in the construction industry for a number of years. * * * Well, I am going to do this — let me — one further look. Where is the [arbitration award]? * * * I thought it expressly — it doesn’t expressly deny the attorney’s fees, does it? * * * I’m going to allow $2500 for attorney’s fees.
“[PLAINTIFF’S COUNSEL]: 2500?
“THE COURT: Right.
“[PLAINTIFF’S COUNSEL]: And is that ruling based upon the fact that Your Honor doesn’t feel that [plaintiff is] entitled to—
*642 “THE COURT: Attorney’s fees for the arbitration.
“[PLAINTIFF’S COUNSEL]: Attorney’s fees in the arbitration award?
“THE COURT: Right. And that’s what I think is a reasonable fee, considering — I am taking into account not just the time, but I am taking into account that basically there’s no indication throughout this proceeding that the contractor wasn’t going to be paid, and those are the only reasonable costs that I think should be required — that the other parties should be required to pay.
(l i-i Hí ifc sfc
“ [Considering the result and what was in controversy here, I think, basically, all of this effort has been directed at trying to recover the fees for the arbitration proceeding, and I am not saying that’s an illegitimate effort, but I don’t think that that’s what the fees that you’ve in — that’s what the fees that you’ve incurred appear to be primarily.
“It seems to me $2500 should be more — would be more than sufficient for — to handle this lien in the ordinary course of business, where the other side had satisfied its obligations in a timely manner throughout.” (Emphasis supplied.)

After a hearing, the court entered a supplemental money judgment awarding plaintiff $2,500 for attorney fees and $487 for costs. See ORCP 68C(5)(b). Defendants then tendered payment of both judgments, but plaintiff again refused to accept it. Defendants then tendered the full amount to the trial court. The court entered an amended order disbursing the funds and satisfying the judgments. Plaintiff appeals from the supplemental judgment awarding attorney fees and costs.

Plaintiff first assigns error to the trial court’s refusal to award any attorney fees for the arbitration. It argues that this case is squarely controlled by Harris, and that the trial court erred in ignoring that case. We review the question of entitlement to attorney fees as a question of law. Pelett v. Welch, 71 Or App 761, 763-64, 694 P2d 574 (1985).

In Harris, the Supreme Court considered whether former ORS 87.060(4) 2 permitted a party to a foreclosure *643 action to recover attorney fees for an arbitration of the underlying contract dispute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

L. H. Morris Electric, Inc. v. Hyundai Semiconductor America, Inc.
125 P.3d 1 (Court of Appeals of Oregon, 2005)
Wilkes v. Zurlinden
932 P.2d 584 (Court of Appeals of Oregon, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
863 P.2d 516, 124 Or. App. 638, 1993 Ore. App. LEXIS 1897, Counsel Stack Legal Research, https://law.counselstack.com/opinion/asb-construction-v-bateman-orctapp-1993.