L. H. Morris Electric, Inc. v. Hyundai Semiconductor America, Inc.

125 P.3d 1, 125 P.3d 87, 203 Or. App. 54, 2005 Ore. App. LEXIS 1571
CourtCourt of Appeals of Oregon
DecidedDecember 7, 2005
Docket16-98-05206; A119475
StatusPublished
Cited by21 cases

This text of 125 P.3d 1 (L. H. Morris Electric, Inc. v. Hyundai Semiconductor America, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L. H. Morris Electric, Inc. v. Hyundai Semiconductor America, Inc., 125 P.3d 1, 125 P.3d 87, 203 Or. App. 54, 2005 Ore. App. LEXIS 1571 (Or. Ct. App. 2005).

Opinion

*57 WOLLHEIM, J.

In this construction dispute, defendant Scott Company of California appeals a judgment that, among other things, dismissed its construction lien against Hyundai Semiconductor America, Inc., awarded attorney fees, costs, and disbursements to the project’s construction manager, and confirmed an arbitration award. Scott’s appeal raises three issues: (1) Did the trial court err in dismissing Scott’s lien claim against Hyundai in light of the arbitration award? (2) Did the trial court err in granting attorney fees in the lien proceeding not to the owner, but to the general contractor, M+W/Marshall? (3) Did the trial court err in the amount of prejudgment interest it awarded? As explained below, we conclude that the trial court correctly disposed of the lien claim and granted attorney fees, but erred in its calculation of prejudgment interest. Therefore, we reverse and remand for recalculation of prejudgment interest.

This appeal is one small piece of the complex litigation — the “Consolidated Hyundai Plant Litigation”— spawned by disputes that arose from the construction of a more than $1 billion microchip fabrication facility known as the Hyundai E-4 Fab Facility in Eugene, Oregon. Only some of the multitude of players involved in the consolidated litigation are involved in this particular dispute. Hyundai Semiconductor America, Inc., owned the real property on which the improvement took place. M+W/Marshall was Hyundai’s “construction agent” and the construction manager for the construction of the facility. 1 M+W/Marshall entered into a subcontract with Scott Company of California under which Scott was to furnish and install certain mechanical systems (i.e., “HVAC, piping and process piping fabrication and installation”) at the facility.

In July 1996, Scott began furnishing the labor and materials called for in its contract with M+W/Marshall. In the spring of 1998, Scott filed a construction lien for about $13.5 million against the Hyundai property. Disputes eventually arose, and in the consolidated litigation that followed *58 completion of the facility, the various parties sought recovery from one another. Among other claims and cross-claims made by the parties, Scott filed three cross-claims against M+W/Marshall and Hyundai. In its first cross-claim, Scott alleged that M+W/Marshall had breached its contract with Scott. Scott claimed that it had agreed to perform its duties under the subcontract for $29,379,870; that M+W/Marshall had breached the contract; and that, as a result of the breach, Scott had suffered $13,393,549 in damages. In its second cross-claim, Scott asserted an alternative quantum meruit claim against — among others — M+W/Marshall (but not against Hyundai); it claimed damages in the same amount as it claimed under the contract. Finally, Scott asserted a lien foreclosure claim against Hyundai, its lender, and “any and all other named parties claiming any right, interest, title or lien in the Improvement or Property.” 2 It alleged that it had filed the lien noted above in the amount of $13,536,548.51. It also asserted in its cross-claim that, “[a]fter the claim of lien was filed, Scott’s damage summary was revised by its consultant to the amount of $13,393,548.99” — the same amount as the damages Scott claimed in its contract and quantum meruit claims against M+W/Marshall.

In May 1999, after Scott had filed its cross-claims, M+W/Marshall filed a demand to arbitrate Scott’s contract and quantum meruit claims. Ultimately, the parties stipulated to the arbitration of all “contract and common law claims” that arose out of the construction of the fabrication facility. The remainder of this litigation — really just the lien claim — was stayed and the contract and quantum meruit claims were arbitrated. In February 2001, before the three-arbitrator panel had rendered its award, M+W/Marshall served Scott with a $6,350,000 offer of judgment. In that offer, which was made pursuant to ORCP 54 E, M+W/ Marshall offered to “allow judgment to be taken against it by” Scott, “resolving all claims asserted by Scott” against— among others — Hyundai and M+W/Marshall. 3 Scott rejected the offer.

*59 In October 2001, after six weeks of hearings, the arbitration panel rendered its award. The net total award in favor of Scott, after deducting the backcharges determined in M+W/Marshall’s favor, was $3,058,571.26. With the arbitration award in hand, M+W/Marshall returned to court and moved — in a motion purporting to have been filed “pursuant to ORCP 21” — to dismiss Scott’s remaining cross-claims against it and Hyundai. Specifically, M+W/Marshall sought to have the lien claim dismissed. That motion was based on arguments that the arbitration award had preclusive effect on the lien claim and that the lien claim was grossly overstated. M+W/Marshall also moved — again, “pursuant to ORCP 21” — for an order granting it attorney fees. In support of its motions to dismiss the lien claim and for attorney fees, M+W/Marshall submitted the arbitration award, affidavits, and exhibits to the affidavits. Finally, M+W/Marshall moved for an order confirming the arbitration award. Scott did not object to having the arbitration award confirmed.

After extensive briefing and a hearing, the trial court entered an order that (1) granted M+W/Marshall’s motion for attorney fees, remanding the matter to the chair of the arbitration panel to determine the amount of those fees; (2) dismissed Scott’s remaining claims, specifically the lien claim; and (3) confirmed the arbitration award. After the amount of attorney fees was determined, the trial court entered a judgment awarding M+W/Marshall $1,138,000 in costs, disbursements, and attorney fees. The judgment also provided that Scott’s lien against the Hyundai property was “released, dismissed, vacated and removed as encumbrances against the Property.” It is from that judgment that Scott appeals.

On appeal, Scott makes three assignments of error. First, Scott asserts, the trial court erred in dismissing its lien claim. Second, Scott claims, the trial court erred in awarding M+W/Marshall attorney fees. Finally, Scott argues, the trial court “erred in denying Scott prejudgment interest from September 10, 2001 until entry of judgment.” We address each assignment of error in turn.

*60 I. DISPOSITION OF THE LIEN CLAIM

In its first assignment of error, Scott claims that the trial court erred in dismissing its lien claim against Hyundai. In the trial court, as noted, M+W/Marshall proffered two theories under which it was entitled to have the lien claim dismissed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Okragly v. Keitel
Montana Supreme Court, 2026
JH Kelly, LLC v. Quality Plus Services, Inc.
472 P.3d 280 (Court of Appeals of Oregon, 2020)
IOW LLC v. Breus
D. Arizona, 2019
State v. Yazzie
New Mexico Court of Appeals, 2017
In re Conagra Foods, Inc.
90 F. Supp. 3d 919 (C.D. California, 2015)
Briggs v. Smith
New Mexico Court of Appeals, 2013
Phelps v. 3PD, Inc.
261 F.R.D. 548 (D. Oregon, 2009)
Schiele v. Montes
218 P.3d 141 (Court of Appeals of Oregon, 2009)
Macland v. Allen Family Trust
142 P.3d 87 (Court of Appeals of Oregon, 2006)
State v. Auld
2006 MT 189 (Montana Supreme Court, 2006)
White v. Dept. of Rev.
19 Or. Tax 47 (Oregon Tax Court, 2006)
Ken Hood Construction Co. v. Pacific Coast Construction, Inc.
126 P.3d 1254 (Court of Appeals of Oregon, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
125 P.3d 1, 125 P.3d 87, 203 Or. App. 54, 2005 Ore. App. LEXIS 1571, Counsel Stack Legal Research, https://law.counselstack.com/opinion/l-h-morris-electric-inc-v-hyundai-semiconductor-america-inc-orctapp-2005.