Brown v. Farrell

483 P.2d 453, 258 Or. 348, 1971 Ore. LEXIS 453
CourtOregon Supreme Court
DecidedMarch 31, 1971
StatusPublished
Cited by13 cases

This text of 483 P.2d 453 (Brown v. Farrell) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brown v. Farrell, 483 P.2d 453, 258 Or. 348, 1971 Ore. LEXIS 453 (Or. 1971).

Opinion

HOLMAN, J.

The Browns contracted with Abrams and Rosbach (A&R) for the construction by A&R of a fourplex. A&R subcontracted the plumbing work to Farrell and the electrical work to Allen. Farrell and Allen filed mechanic’s liens for labor and materials. Farrell brought a suit to foreclose his lien against the Browns and A&R and also made Allen a party defendant because Allen’s lien was of record. Allen filed a counterclaim to foreclose his lien. A&R then filed a counterclaim and a suit for an accounting against Allen. *351 Almost simultaneously with the commencement of the above-descrihed litigation by Farrell, the Browns and A&R. commenced a proceeding against Farrell to remove the cloud of Farrell’s lien from the Browns’ property.

The cases were consolidated for the purposes of trial and appeal. The trial court held the Farrell lien invalid and the Allen lien valid in an amount slightly smaller than the sum for which the lien was filed. It also allowed a small recovery on A&R’s counterclaim against Allen. Farrell appealed from the holding that his lien was invalid and the Browns and A&R appealed from the foreclosure of Allen’s lien. A&R also appealed from the amount of their recovery on its counterclaim against Allen. The other parties to the litigation, who have not been mentioned, are unimportant to the issues raised upon appeal.

We will first dispose of the litigation between Farrell on one side and the Browns and A&R on the other. The trial court held that Farrell’s lien was invalid because it was not timely filed. ORS 87.035 requires that a mechanic’s lien which is filed by other than the original contractor must be filed wdthin 45 days after the completion of the construction, or wdthin 45 days after the lienor has ceased to perform work or to furnish materials. Farrell’s complaint alleged that the work was done between the 13th day of May and the 25th day of September and that the lien was filed *352 on the 21st day of October. The lien form, a copy of which was made part of the complaint, stated that it was filed within 45 days of the time the work was performed and materials were furnished by Farrell. The complaint to foreclose the lien did not allege the date of the completion of the construction or that the lien was filed 45 days after such time. One of the bases for the Browns’ and A&R’s complaint to remove a cloud from the Browns’ title was that the lien was not filed within 45 days of Farrell’s last performing work or furnishing materials. This allegation was denied only, and Farrell did not answer by alleging that his lien was filed within 45 days of the completion of the construction.

Upon proof, it was shown that Farrell substantially completed such work as he did on May 20, not on September 25. He returned on September 25 to repair a washer and to attend to some other minor matter. The trial court held that the work performed on September 25 was of such minor consequence that it could not be construed to extend the time within which he furnished materials or worked. The court, therefore, invalidated the lien because it was not filed within 45 days of Farrell’s last work or his furnishing of his last materials. The building was not completed until sometime in November, long after the time Farrell had filed his lien. Thus, the lien was filed within 45 days after the completion of the construction. The trial judge held that

“* * * notwithstanding that the plaintiff had the statutory right to file the lien within forty-five days after the ‘completion of the construction’, * '* * he chose to allege his cause of suit upon a theory that the lien was filed within forty-five days after the plaintiff ‘ceased performance’, ,and the *353 case was at issue and tried upon that theory. The plaintiff having made the election to proceed upon that theory now has the burden to establish the truth of the allegations of his complaint.”

We agree with the trial court’s holding that the work performed on September 25 was inconsequential and that it did not extend the time within which Farrell performed work on the structure. We disagree, however, with the trial judge concerning the limitation of the issues by the pleadings. We believe his refusal to uphold the lien because it stated it was-filed within 45 days of the time Farrell ceased to' furnish labor and materials, when it was not, was. overly technical. The fact that the pleadings so alleged by setting forth the lien in the complaint was not harmful to A&R and the Browns in preparing for or in trying their case. The Browns and A&R testified as to the time of the completion of the building. There is no question that the lien was filed before the budding was completed and, thus, within the requisite time provided by statute. They could not have changed this fact by any preparation for trial.

The Browns and A&R also contend that the lien did not contain a true statement of Farrell’s claim as required by ORS 87.035, and, therefore, it was invalid. The lien was filed for $2,806, of which $1,124.01 was for materials, $112.40 for profit, and $1,569.59 for labor. The materials which were furnished were all itemized in the lien. Only about $700 of the labor was furnished and all claims for labor were lumped together in one item.

Farrell, after completing the roughing-in of the plumbing, did not go back and finish the job because he became concerned, apparently justifiably, about *354 whether he was going to be paid. When he filed his lien, he filed it as if the work had been completed even though this was not the case. He excuses himself by saying that at the time he filed the lien he did not know whether he was going to complete the job or not. It is clear that he had no right to a lien for work he had not performed, and, therefore, he should not have filed the lien as he did. The labor which was performed was lumped with that which was not performed, and, therefore, no recovery for labor can be had regardless of the intent with which the extra labor was included. Benj. Franklin S&L v. Hallmark, 257 Or 436, 479 P2d 740 (1971).

The more difficult question is whether Farrell should be entitled to a lien for the materials which he did furnish and which were separately itemized in the lien. There are many Oregon cases which say that where the lien is negligently or fraudulently overstated it will be invalidated in its entirety. We have no quarrel with the statement that where fraud is involved, equity should not lend its powers to the foreclosure of the lien. However, we do not believe that negligence alone ought to defeat a lien in all circumstances. We think the rule was properly stated by Mr. Justice McBride in Bartels v. McCullough, 102 Or 66, 201 P 733 (1921):

“In Mason v. Germaine, supra, the court discussing this subject under a similar statute remarked :

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Myhre v. Potter
507 P.3d 772 (Court of Appeals of Oregon, 2022)
L. H. Morris Electric, Inc. v. Hyundai Semiconductor America, Inc.
125 P.3d 1 (Court of Appeals of Oregon, 2005)
Westwood Construction Co. v. Hallmark Inns & Resorts, Inc.
50 P.3d 238 (Court of Appeals of Oregon, 2002)
Stricker v. Taylor
975 P.2d 930 (Court of Appeals of Oregon, 1999)
A-C Construction, Inc. v. Bakke Corp.
956 P.2d 219 (Court of Appeals of Oregon, 1998)
Scottsdale Memorial Health Systems, Inc. v. Clark
759 P.2d 607 (Arizona Supreme Court, 1988)
Leffler v. Spindler
686 P.2d 1045 (Court of Appeals of Oregon, 1984)
Robertson, Hay & Wallace v. Kunkle
686 P.2d 399 (Court of Appeals of Oregon, 1984)
Central Coast Electric, Inc. v. Mendell
672 P.2d 1224 (Court of Appeals of Oregon, 1983)
J. W. Copeland Yards v. Phillips
550 P.2d 438 (Oregon Supreme Court, 1976)
Hays v. Pigg
515 P.2d 924 (Oregon Supreme Court, 1973)
John L. Jersey & Son, Inc. v. Bud Bailey Construction Co.
499 P.2d 817 (Oregon Supreme Court, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
483 P.2d 453, 258 Or. 348, 1971 Ore. LEXIS 453, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brown-v-farrell-or-1971.