Benj. Franklin Federal Savings & Loan Ass'n v. Hallmark, Inc.

479 P.2d 740, 257 Or. 436, 1971 Ore. LEXIS 486
Oregon Supreme Court·Decided January 27, 1971·Published·Cited by 11 cases

Opinion

HOLMAN, J.

This is a suit to foreclose a mortgage held by plaintiff which secured a residence construction loan made to the defendant Hallmark, Inc. Defendants Jack Largent Co., Inc., and T So J Masonry, Inc., are each the holder of a mechanic’s and materialmen’s lien upon the improvement pursuant to ORS 87.010 (1). The two lienors (hereinafter referred to as defendants) have appealed from a decree of the trial court holding that plaintiff’s mortgage has priority over their liens.

Plaintiff loaned the money to Hallmark to construct the improvement. Defendants contracted directly with Hallmark to do the work and to furnish *438 the materials for a lump sum price. Hallmark did not pay defendants and they filed their liens. The liens did not segregate charges for labor from charges for materials. Plaintiff’s mortgage was recorded before defendants did any work or furnished any materials. No notice of the delivery of materials was given by defendants to plaintiff. The basis for the trial court’s holding that plaintiff’s mortgage had priority over defendants’ liens was defendants’ failure to give such notice.

The issue presented is rather narrow. It involves construction of ORS 87.025 (3) which provides that before a lien for materials and supplies has priority over a previously recorded mortgage on either land or buildings, notice must be given as prescribed therein to the mortgagee. A lien for labor has such priority without the giving of any notice. The question presented here is what the effect is upon the priorities where the lien lumps both labor and materials and no notice of the delivery of materials has been given to the mortgagee. The statute is silent on the subject and there are no cases directly in point.

*439 OES 87.020 (1) requires notice to the owner of property by one who supplies materials to a contractor before a lien for such supplies can be enforced. Like ORS 87.025, it does not require notice of labor performed. It is a parallel or similar situation to the present case insofar as notice is concerned because in neither instance does the person to whom notice must be given have any contractual relationship with the person furnishing the materials. However, ORS 87.020, the owners’ notice statute, has a provision that ORS 87.025, the mortgagees’ notice statute, does not. Subsection (5) provides that where the lien is for both labor and materials, no notice is necessary to secure a lien that is prior to the owner’s interest. This subsection was added by ch 602, § 1, Oregon Laws 1967. No similar section was added to ORS 87.025.

*440 Prior to the amendment to ORS 87.020, which added the provision that no notice was necessary to the owner where both labor and materials were furnished to the contractor, there were at least two decisions holding that where both labor and materials were furnished by the same claimant, and no notice was given of the delivery of the materials to the owner, there was no valid lien for materials; and where there was no segregation of labor and materials in the lien, the lien was void because of the lumping together of lienable and non-lienable items. Lakeview Drilling Co. v. Stark et al, 210 Or 306, 314, 310 P2d 627 (1957) and Johnson v. Alm et al, 121 Or 285, 288, 254 P 803 (1927).

Presumably, subsection (5) of ORS 87.020 was enacted to negative the result of these eases. The legislature did not enact a similar provision as part of ORS 87.025 which relates to the notice to mortgagees. Because we cannot distinguish between the notice provisions relating to owners prior to the 1967 amendment and the present provisions relating to notice to mortgagees, we are forced to conclude that Lakeview and Johnson control the present question and that it was not the intention of the legislature to relax the notice requirements to mortgagees, where both labor and materials were furnished, as it relaxed them in relation to owners.

It can be argued that Lakeview and Johnson have no application to the present situation because the rule preventing the lumping of lienable and nonlienable items is relevant only to the existence of a valid lien and in the present case there is no question of the validity of the lien. It is a valid lien. The only question is one of priority. Whether such an argu *441 ment is valid and whether the lumping rule is relevant to the priority as well as to the validity of the lien depends upon the rationale behind the rule. We have found no Oregon eases which discuss the rationale, though literally dozens of cases have either applied or refused to apply the rule, depending upon the circumstances. Our investigation leads us to believe that the prevailing rationale behind the rule is that the owner of the improvement has a right to know, from the face of the lien as filed, the amount which has become a charge upon the property so that he may, in advance of foreclosure, discharge the property of the encumbrance by tender or payment. Harris v. Harris, 9 Colo App 211, 219, 47 P 841 (1897); Scheibner v. Cohnen, 108 Mich 165, 167, 65 NW 760 (1895) (Mr. Justice Grant dissenting); Edgar v. Salisbury et al, 17 Mo 271, 272 (1852); Nelson v. Withrow, 14 Mo App 270, 277 (1883); Boyle v. Mining Co., 9 NM 237, 252, 50 P 347 (1897).

Free access — add to your briefcase to read the full text and ask questions with AI

Benj. Franklin Federal Savings & Loan Ass'n v. Hallmark, Inc., 479 P.2d 740, 257 Or. 436, 1971 Ore. LEXIS 486 (Or. 1971).

479 P.2d 740 (Benj. Franklin Federal Savings & Loan Ass'n v. Hallmark, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Safeport, Inc. v. Equipment Roundup & Manufacturing, Inc.
60 P.3d 1076 (Court of Appeals of Oregon, 2002)
Knez Building Materials Co. v. Bell-Air Estates, Inc.
927 P.2d 608 (Court of Appeals of Oregon, 1996)
Hitchman v. Burkey
769 P.2d 799 (Court of Appeals of Oregon, 1989)
Myers v. Oregon Shores Associates, Ltd.
687 P.2d 159 (Court of Appeals of Oregon, 1984)
Robertson, Hay & Wallace v. Kunkle
686 P.2d 399 (Court of Appeals of Oregon, 1984)
Betz Construction, Inc. v. Peterson
614 P.2d 1184 (Court of Appeals of Oregon, 1980)
Farmer's Feed & Supply Co. v. Industrial Leasing Corp.
594 P.2d 397 (Oregon Supreme Court, 1979)
Hays v. Pigg
515 P.2d 924 (Oregon Supreme Court, 1973)
Cal-Roof Wholesale, Inc. v. Contractors West, Inc.
497 P.2d 1181 (Oregon Supreme Court, 1972)
Brown v. Farrell
483 P.2d 453 (Oregon Supreme Court, 1971)