Hays v. Pigg

515 P.2d 924, 267 Or. 143, 1973 Ore. LEXIS 282
CourtOregon Supreme Court
DecidedNovember 15, 1973
StatusPublished
Cited by16 cases

This text of 515 P.2d 924 (Hays v. Pigg) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hays v. Pigg, 515 P.2d 924, 267 Or. 143, 1973 Ore. LEXIS 282 (Or. 1973).

Opinion

HOLMAN, J.

This is a suit brought by a contractor against the owners for foreclosure of a mechanic’s lien covering the cost of erection of a prefabricated modular home. The trial judge rendered judgment for $18,-551.83, which he found to be the unpaid balance due, plus $1,000 as attorney fees, and foreclosed the lien in that amount. Defendants appealed.

The principal dispute concerns the nature of the parties’ agreement. Plaintiff claims the contract was for the reasonable value of the labor and materials. Defendants contend plaintiff was to construct the home for $21,500 or less.

The contractor helped arrange the financing, and two proposals were secured from the Jackson County Federal Savings and Loan. One was for $22,000 at 7y2 percent interest and the other was for $24,800 at 7% percent interest. Plaintiff told defendants that the lesser amount would be insufficient since defendants would have to use part of the money from the loan to pay for the land on which the home was to be constructed. However, plaintiff told defendants that he was reasonably sure that he could construct the home for approximately $21,500, the balance of the larger *146 loan after deducting other costs and fees, and still have money left over.

Defendants then suggested to plaintiff that they have a written contract setting out their agreement. However, according to defendants, plaintiff said:

“Just trust me because if I have to go to a written contract we’ll have to inflate everything, we’ll have to come up with a figure to make sure there’s lots of cushion, and that will be excessive profits for me. There’s no need for a contract, a written one.”

This statement could mean only that plaintiff was unwilling to enter into a binding contract to build the home for the balance of the loan and that if he was tied to an exact amount, the figure would have to be larger. The plain inference was that, although plaintiff believed he could build the home for the balance of the loan, he was proceeding upon the supposition that if it cost more than anticipated he would expect defendants to bear the cost plus a reasonable profit. Defendants allowed plaintiff to proceed on that assumption. We therefore agree with the finding of the trial judge that there was a contract for the reasonable value of the work and therefore find that no basic inconsistency existed, as contended by defendants, concerning the lien, the pleadings, and the proof.

Defendants next contend that the lien contained overstatements sufficient to invalidate the lien. The lien was for $23,076.83 less the payments thereon. The complaint claimed $23,003.33 less the payments. The difference of $73.50 is explained as being due to a clerical duplication which was not discovered until after the lien was filed. Also, prior to trial the amount claimed by the complaint was reduced approximately $309 as the result of a credit granted by the contractor *147 because of defects and improper instructions concerning the manner in which the home should be erected. At the time of filing the lien, both plaintiff and defendants were aware a credit should be allowed but plaintiff was still negotiating with the seller of the prefabricated home for it. If the credit had not been secured, it is arguable whether the additional cost should have been absorbed by defendants rather than by plaintiff, but plaintiff was under the impression that it should be.

Where a lien contains minor overstatements made in good faith, the lien may be allowed to the extent of the correct amount. In order for the overstatement to invalidate the lien, it must be an intentional one or one made through culpable negligence. Brown v. Farrell, 258 Or 348, 358, 483 P2d 453 (1971); Mercer Steel Co. v. Park Construction Co., 242 Or 596, 599-600, 411 P2d 262 (1966); Boyer v. Dawson, 207 Or 211, 212-13, 293 P2d 739, 295 P2d 159 (1956); Drake Lumber Co. v. Paget Mortgage Co., 203 Or 66, 80-81, 274 P2d 804 (1954). The minor overstatements contained in plaintiff’s lien are not of the kind which renders the lien invalid.

Defendants next claim that certain lien items should not be allowed because they contained unsegregated lienable and nonlienable charges. The nonlienable charges were the same as those for which the credit of approximately $309 was allowed at the time of trial. One lien item of $462 was for crane rental, of which $132 was subsequently secured as a credit from the manufacturer of the prefabricated home because of misplaced lifting points on the home which necessitated extra crane use. Other challenged items included $65 for the cost of a bathtub which was omitted and for which a credit of $15.00 was subsequently *148 secured for the additional cost' of obtaining another tub; and $14,237.50 for the cost of the home in which some minor damage and imperfections existed and for which credit of approximately $74 was allowed. Extrinsic evidence was necessary to segregate these credits from the items listed in the lien.

The general rule has been that where unsegregated lienable and nonlienable charges are lumped together in the lien as one item so that extrinsic evidence is necessary to segregate them, the right to a lien is lost as to all such unsegregated items. Smith v. Lichtenthaler, 206 Or 584, 586, 294 P2d 334 (1956); Anderson v. Chambliss, 199 Or 400, 414, 262 P2d 298 (1953). The reason for the rule is stated in Benj. Franklin S&L v. Hallmark, 257 Or 436, 441, 479 P2d 740 (1971), to be the right of the owner to know from the face of the lien as filed, the amounts of valid claims which have become a charge upon his property so that he may, in advance of foreclosure, discharge the property from the encumbrance by rendering a payment without incurring the cost of litigation.

In the present case the defendants were at all times aware of the defects and deficiencies in the prefabricated home and of plaintiff’s negotiations with the supplier for a credit on the purchase price. As a result, defendants had sufficient knowledge with which to question the amount of the lien to make sure they received the credit, and they would not have been prejudiced by a lack of information in settlement prior to the commencement of the suit. A simple question would have supplied sufficient information concerning the status of the settlement. Furthermore, another reason exists, discussed next, for not invalidating the lien for the cost of- the prefabricated home.

*149 Defendants contend that in an item-for labor of $1,844.50 three hours were included for work which was actually performed after the date the lien states the work was completed. They claim the cost (about $21) was not lienable and, therefore, the entire amount for labor should be disallowed. We have some cases which justify such a contention. In Wiggins v. Southwood Park Corp., 221 Or 61, 350 P2d 436 (1960), the lien was filed for approximately $30,000 upon which a balance of approximately $1,400 was due. This lien was found to be invalid because a nonlienable item of $72 was included therein.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ornduff v. Hobbs
359 P.3d 331 (Court of Appeals of Oregon, 2015)
Safeport, Inc. v. Equipment Roundup & Manufacturing, Inc.
60 P.3d 1076 (Court of Appeals of Oregon, 2002)
Westwood Construction Co. v. Hallmark Inns & Resorts, Inc.
50 P.3d 238 (Court of Appeals of Oregon, 2002)
A-C Construction, Inc. v. Bakke Corp.
956 P.2d 219 (Court of Appeals of Oregon, 1998)
Northwest Natural Gas Co. v. Chase Gardens, Inc.
933 P.2d 370 (Court of Appeals of Oregon, 1997)
Knez Building Materials Co. v. Bell-Air Estates, Inc.
927 P.2d 608 (Court of Appeals of Oregon, 1996)
Fondren v. K/L COMPLEX LTD.
800 P.2d 719 (Nevada Supreme Court, 1990)
Hitchman v. Burkey
769 P.2d 799 (Court of Appeals of Oregon, 1989)
Alley v. Erbach
747 P.2d 360 (Court of Appeals of Oregon, 1987)
Northwest Ironworks, Inc. v. Rippling River Development Corp.
691 P.2d 111 (Court of Appeals of Oregon, 1984)
Myers v. Oregon Shores Associates, Ltd.
687 P.2d 159 (Court of Appeals of Oregon, 1984)
Robertson, Hay & Wallace v. Kunkle
686 P.2d 399 (Court of Appeals of Oregon, 1984)
Deal v. Edwards
624 P.2d 1099 (Court of Appeals of Oregon, 1981)
Betz Construction, Inc. v. Peterson
614 P.2d 1184 (Court of Appeals of Oregon, 1980)
Farmer's Feed & Supply Co. v. Industrial Leasing Corp.
594 P.2d 397 (Oregon Supreme Court, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
515 P.2d 924, 267 Or. 143, 1973 Ore. LEXIS 282, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hays-v-pigg-or-1973.