Fondren v. K/L COMPLEX LTD.

800 P.2d 719, 106 Nev. 705, 1990 Nev. LEXIS 128
CourtNevada Supreme Court
DecidedNovember 7, 1990
Docket20603
StatusPublished
Cited by6 cases

This text of 800 P.2d 719 (Fondren v. K/L COMPLEX LTD.) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fondren v. K/L COMPLEX LTD., 800 P.2d 719, 106 Nev. 705, 1990 Nev. LEXIS 128 (Neb. 1990).

Opinion

*707 OPINION

Per Curiam:

Facts

In 1983, Appellant Ellanor Ann Fondren (Fondren) leased space in a commercial building she owned on Tahoe Boulevard in Incline Village, Nevada, to Ralph Spinelli (Spinelli). The space leased by Fondren to Spinelli was designed to accommodate a restaurant and it was Spinelli’s intent to open a new restaurant, “Tahoe Junction.”

Remodeling began on the leased space in May 1983. In the process of remodeling the restaurant, Spinelli contracted with respondents K/L Complex d/b/a Allan King & Friends (King), Excalibur Products, Ltd. (Excalibur), and Toledo Manufacturing Company, Inc. (Toledo). King performed a variety of services including development of design and layout drawings, performance of process inspections, review of the installation of kitchen equipment and preparation of all areas to comply with health department regulations. Toledo provided “custom built” items to match the design and layout of the restaurant. This included, in part, booths, wine bottle displays and storage, and associated pilasters and moldings and two mirrored sections which were installed on an existing wall. Excalibur supplied kitchen equipment.

Following remodeling, Tahoe Junction opened for business in September 1983. However, a fire on October 3, 1985 caused substantial damage to the interior of the premises and forced the permanent closure of the establishment.

On October 11, 1985, King, Toledo and Excalibur executed mechanics’ liens against the premises. King claimed a mechanics’ lien for design, consulting services and labor. Toledo’s lien was for the value of goods it supplied to the premises. Excalibur claimed a lien for the deficiency it suffered in the resale of the equipment they repossessed. In April, 1984, Tahoe Junction filed for protection under the U.S. Bankruptcy Code but the premises reverted back to Fondren. Eventually, Excalibur and Toledo retook possession of the property they had supplied and an action was brought to foreclose on the liens.

*708 On December 28, 1988 the trial court granted respondents’ motion for partial summary judgment concerning the issue of whether or not the mechanics’ liens had been properly perfected. The trial court then heard evidence on the remaining issues and entered judgment foreclosing the mechanics’ liens. This appeal was taken by Fondren. She raises three issues.

Discussion

Fondren first challenges the trial court’s entry of partial summary judgment on the issue of the perfection of the mechanics’ liens. The essential facts are not in dispute. 1 The material facts regarding the issue of the perfecting of the mechanics’ liens show that Fondren failed to record a notice of non-responsibility and that respondents King, Toledo and Excalibur did not deliver a pre-lien notice to Fondren. Fondren simply argues that the trial court failed to properly apply the law to the given facts. 2 To support her argument, Fondren relies on NRS 108.234 for the proposition that it places lessors, upon whose property improvements are being made and who fail or elect not to file a notice of nonresponsibility, on the same footing as an owner who is having a general contractor improve his property. Based on this reliance *709 on NRS 108.234, Fondren asserts that the trial court’s reliance on Board of Trustees v. Durable Developers, 102 Nev. 401, 724 P.2d 736 (1986), was erroneous and the partial summary judgment must be reversed. This argument is meritless.

We have previously held:

[Substantial compliance with the technical requirements of the lien statutes is sufficient to create a lien on the property where, as here, the owner of the property receives actual notice of the potential lien claim and is not prejudiced.

Board of Trustees v. Durable Developers, Inc., 102 Nev. 401, 410, 724 P.2d 736, 743 (1986).

Additionally, it has been held that:

[T]he purpose of the pre-lien statute is to put the owner on notice of work and materials furnished by third persons with whom he has no direct contact.
If the owner fails to file a notice of nonresponsibility within the time provided in the law, after knowledge of the construction, the statute provides that the construction is at the instance of the owner. It is a “direct contract.”

Matter of Stanfield, 6 B.R. 265, 269 (Bankr.D.Nev. 1980) (emphasis in original).

In this case, it is clear that Fondren had actual knowledge of the construction on her property. It was understood by both Fondren and Spinelli that substantial remodeling would be required when the lease was negotiated. Additionally, Fondren’s attorney regularly inspected the progress of the remodeling efforts. These inspections were on behalf of Fondren. See Gould v. Wise, 18 Nev. 253, 3 P. 30 (1884) (actual knowledge of owner’s agent will be imputed to the owner for purposes of this statute). Fondren could easily have protected herself by filing a notice of non-responsibility. She had actual knowledge of the work being performed on her property.

Furthermore, a pre-lien notice was not required. This reasoning is supported by a line of cases from California, including M. Arthur Gensler, Jr. & Associates, Inc. v. Larry Barrett, Inc., 103 Cal.Rptr. 247, 499 P.2d 503 (1972), which is very similar to the instant case on its facts. In Gensler, as here, the lessor argued that the lien claims were barred because there had been no pre-lien notice as required by Section 1193(a) of the California Code of Civil Procedure. The court in Gensler held that:

[I]f a lien claimant contracts directly with the lessee, and the lessor knows of the construction and fails to file a notice of *710 nonresponsibility, such claimant then has a “direct contract with the owner” for the purposes of section 1193.

Id. at 255, 499 P.2d at 511.

The purpose underlying the notice requirement is to provide the owner with knowledge that work and materials are being incorporated into the property. The failure to serve the pre-lien notice does not invalidate a mechanics’ or materialmen’s lien where the owner received actual notice. See Board of Trustees v. Durable Developers, supra.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ILIESCU, JR. VS. STEPPAN
2017 NV 25 (Nevada Supreme Court, 2017)
West Charleston Lofts I, LLC v. R & O Construction Co.
915 F. Supp. 2d 1191 (D. Nevada, 2013)
Hardy Companies, Inc. v. SNMARK, LLC
245 P.3d 1149 (Nevada Supreme Court, 2010)
Leasepartners Corp. v. Robert L. Brooks Trust
942 P.2d 182 (Nevada Supreme Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
800 P.2d 719, 106 Nev. 705, 1990 Nev. LEXIS 128, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fondren-v-kl-complex-ltd-nev-1990.