Safeport, Inc. v. Equipment Roundup & Manufacturing, Inc.

60 P.3d 1076, 184 Or. App. 690, 2002 Ore. App. LEXIS 1728
CourtCourt of Appeals of Oregon
DecidedNovember 6, 2002
Docket98C-10775; A112787
StatusPublished
Cited by24 cases

This text of 60 P.3d 1076 (Safeport, Inc. v. Equipment Roundup & Manufacturing, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Safeport, Inc. v. Equipment Roundup & Manufacturing, Inc., 60 P.3d 1076, 184 Or. App. 690, 2002 Ore. App. LEXIS 1728 (Or. Ct. App. 2002).

Opinion

*693 BREWER, J.

Defendant Equipment Roundup & Manufacturing, Inc., appeals a judgment foreclosing its construction lien. It assigns error to the trial court’s denial of its request for attorney fees and to the court’s denial of its motion to reopen the record and amend its pleading to comply with statutory requirements for an award of attorney fees. Defendant also assigns error to the trial court’s grant of priority over defendant’s lien and its costs and disbursements in this action. Finally, defendant challenges the dismissal of its quantum meruit claim against the owner of the foreclosed property. Plaintiff Safeport, Inc., cross-appeals, assigning error to the trial court’s denial of its request for a jury trial on its breach of contract claim. On defendant’s appeal, we reverse and remand with respect to the denial of attorney fees and otherwise affirm. On plaintiffs cross-appeal, we reverse and remand.

Plaintiff is a corporation, the sole shareholder of which third-party defendant Clay Allen serves as plaintiffs president. Allen owns real property on which plaintiff sought to establish a dry-land boat storage business. Plaintiff contracted with defendant to assemble a rack structure that would hold and store boats. Plaintiff agreed to make payments to defendant as the work progressed. During the construction process, problems arose that required extra work. Defendant performed the extra work with plaintiffs approval, but plaintiff later disputed that it was responsible for the charge for that work, which amounted to $20,142.49. Plaintiff also objected that the structure did not meet the specifications required by the contract and informed defendant that it would not make any more payments. As a result, defendant stopped work and filed a construction lien against the improvement and real property for $84,662.49, the amount of the original contract plus the charge for the extra work, less the amount of payments it had already received. Citing ORS 87.057(2), plaintiff demanded a list of materials and supplies with the charges therefor and a statement of the contractual basis for the owner’s obligation. In its written reply, defendant asserted that ORS 87.057(2) requires a lien *694 claimant to furnish such a list or a statement of the contractual basis, and it further stated that the original contract provided the basis for plaintiffs obligation. In addition, defendant included with its written response a list itemizing the labor and material costs for the extra work.

Plaintiff then brought this action against defendant for breach of contract, breach of warranty, breach of the duty of good faith and fair dealing, fraud, and negligence. Plaintiff demanded a jury trial. In its answer, defendant asserted counterclaims for breach of contract based on the amount unpaid on the contract and for quantum meruit. Defendant also brought a third-party claim against Allen and Pioneer Trust Bank (bank), seeking to foreclose its construction lien against the real property and alleging a superior interest to bank’s mortgage lien against the property. In addition, defendant alleged a quantum meruit claim against Allen, asserting that Allen would be unjustly enriched if he were permitted to retain the benefit of the improvement without paying for its reasonable value.

On defendant’s motion for summary judgment, the trial court dismissed all of plaintiffs claims except for its breach of contract claim. The court bifurcated defendant’s lien foreclosure counterclaim from the parties’ contract claims, trying the lien foreclosure claim first. After the foreclosure trial, the court concluded that the lien was valid. The court found that defendant had substantially performed the contract, that it had installed the structures in a good and workmanlike manner, and that any further performance by defendant was excused by plaintiffs refu'sal to pay for the work already performed.

In a post-trial hearing, the court awarded defendant the amount of the lien claim less $8,100 for remaining work to be performed under the contract. The court also concluded that plaintiff did not have a right to a jury trial on its breach of contract claim, because ORS 87.060(3) directs that, if the lien is allowed, the court will resolve all other pleaded issues. Having concluded in the lien foreclosure proceeding that defendant had not breached the contract, the court dismissed plaintiffs breach of contract claim. The court also dismissed *695 defendant’s quantum meruit claim, concluding that defendant had failed to sustain its burden of proof with respect to that claim.

Defendant then submitted a statement for attorney fees. After conducting an evidentiary hearing, the court determined that an award of attorney fees was justified but nevertheless declined to make such an award because defendant had failed to plead and prove that it had furnished plaintiff with a list of materials and the charge therefor or a statement of contractual basis for the lien, as required by ORS 87.057(3).

Finally, the court determined that defendant’s lien was entitled to priority over bank’s mortgage, but only as to the segregated portion of the labor charge, $12,980.75. The court found that defendant had failed to provide bank with notice of the materials portion of the charge. The court awarded defendant its costs and disbursements but did not provide that those costs were entitled to priority over bank’s mortgage.

ATTORNEY FEES

We begin by addressing defendant’s assignments of error relating to the denial of its petition for attorney fees. Defendant argues that the trial court erred in denying attorney fees pursuant to ORS 87.060(5), which provides:

“When notice of intent to foreclose the lien has been given, pleaded and proven as provided for in ORS 87.057, the court, upon entering judgment for the lien claimant, shall allow as part of the costs all moneys paid for the filing or recording of the lien and all moneys paid for title reports required for preparing and foreclosing the lien. In a suit to enforce a lien perfected under ORS 87.035 the court shall allow a reasonable amount as attorney fees at trial and on appeal to the party who prevails on the issues of the validity and foreclosure of the lien.”

ORS 87.057, in turn, provides, in part:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Perma Treat, Inc. v. Toma Investments, LLC
344 Or. App. 725 (Court of Appeals of Oregon, 2025)
RLF Liquidating, LLC v. McDonald Brothers, Inc.
507 P.3d 758 (Court of Appeals of Oregon, 2022)
Dreyer v. PGE
453 P.3d 580 (Court of Appeals of Oregon, 2019)
Day v. Day
450 P.3d 1 (Court of Appeals of Oregon, 2019)
Alexander v. State
390 P.3d 1109 (Court of Appeals of Oregon, 2017)
Willamette Landing Apartments - 89, LLC v. Burnett
382 P.3d 512 (Court of Appeals of Oregon, 2016)
Springville Corp. v. Stoel Rives LLP
372 P.3d 14 (Court of Appeals of Oregon, 2016)
Classen v. Arete NW, LLC
254 P.3d 216 (Court of Appeals of Oregon, 2012)
Jensen v. Duboff
291 P.3d 738 (Court of Appeals of Oregon, 2012)
Caldeen Construction, LLC v. Kemp
273 P.3d 174 (Court of Appeals of Oregon, 2012)
Cox v. C & H REFORESTERS, INC.
245 P.3d 139 (Court of Appeals of Oregon, 2010)
Verizon Northwest, Inc. v. Main Street Development, Inc.
693 F. Supp. 2d 1265 (D. Oregon, 2010)
Staten v. Steel
191 P.3d 778 (Court of Appeals of Oregon, 2008)
Ballard v. City of Albany
191 P.3d 679 (Court of Appeals of Oregon, 2008)
O'HARA v. David Blain Construction, Inc.
173 P.3d 1257 (Court of Appeals of Oregon, 2007)
Butchart v. Baker County
166 P.3d 537 (Court of Appeals of Oregon, 2007)
McDowell Welding & Pipefitting, Inc. v. United States Gypsum Co.
149 P.3d 173 (Court of Appeals of Oregon, 2006)
In RE McBRIDE
348 B.R. 539 (D. Idaho, 2004)
Forsi v. Hildahl
96 P.3d 852 (Court of Appeals of Oregon, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
60 P.3d 1076, 184 Or. App. 690, 2002 Ore. App. LEXIS 1728, Counsel Stack Legal Research, https://law.counselstack.com/opinion/safeport-inc-v-equipment-roundup-manufacturing-inc-orctapp-2002.