Robertson, Hay & Wallace v. Kunkle

686 P.2d 399, 69 Or. App. 99
CourtCourt of Appeals of Oregon
DecidedJuly 11, 1984
DocketA8108-05279; CA A26635
StatusPublished
Cited by5 cases

This text of 686 P.2d 399 (Robertson, Hay & Wallace v. Kunkle) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Robertson, Hay & Wallace v. Kunkle, 686 P.2d 399, 69 Or. App. 99 (Or. Ct. App. 1984).

Opinion

*101 BUTTLER, P. J.

Plaintiff brought this action to foreclose a lien for labor and materials used in the construction of facilities on land leased by defendant Kunkle from the Port of Portland. Defendant First Interstate Bank of Oregon (First Interstate) contends that plaintiffs lien is invalid and that, because of Kunkle’s default on a note given it to finance the construction, it is entitled to foreclose its mortgage on Kunkle’s leasehold interest securing that note. The court determined that plaintiffs lien is valid and superior to the claims of all others 1 and entered a decree foreclosing that lien and also a judgment for plaintiff against Kunkle for $480,581.52. 2 First Interstate appeals. On de novo review, we affirm.

On September 27, 1979, plaintiff, a contractor, and Kunkle, a developer, entered into a contract for the construction of an air cargo facility to be known as Building D at the Portland International Airport. Building D was to be constructed by plaintiff on premises owned by the Port of Portland and leased to Kunkle for a 20-year period, partially for that purpose. The terms of both the lease and the construction contract required, as part of the project, construction of a paved passageway to permit vehicles to be used for loading and unloading air cargo and also the performance of electrical work, excavation and grading for road preparation, curb striping, security fencing and landscape services. Although most, if not all, of that additional work was to be performed off *102 the leased premises, Kunkle’s project engineer testified that the work was vital and necessary for the use and operation of Building D on the leased premises.

Construction was completed in April, 1981, at which time Kunkle owed plaintiff $575,849. On June 23 or 24, 1981, plaintiff filed a lien for that amount. Plaintiff thereafter timely notified Kunkle and First Interstate of the filing of the lien and of its intention to foreclose if the amount claimed was not paid. It was not, and this action followed.

First Interstate recognizes that a valid lien filed pursuant to ORS 87.010(1) is preferred to all prior liens, mortgages or encumbrances, ORS 87.025(2), but contends that plaintiffs lien contains unsegregated lienable and nonlienable claims and is, therefore, invalid. Hays v. Pigg, 267 Or 143, 515 P2d 924 (1973). First, it contends that more than $50,000 of the lien claim relates to work performed off the leased premises, such as landscaping and the excavation and grading of the parking area, and is nonlienable under ORS 87.010(1), under which plaintiff claims its lien, because that statute permits a lien only for labor performed on and materials incorporated in an “improvement,” which includes:

“* * * any building, wharf, bridge, ditch, flume, reservoir, well, tunnel, fence, street, sidewalk, machinery, aqueduct and all other structures and superstructures, whenever it can be made applicable thereto.” ORS 87.005(5) (Emphasis supplied.)

That broad language led the court in Tri-City Bldg. Center v. Wagner, 21A Or 581, 582, 548 P2d 961 (1976), to conclude that blacktopping and a site-obscuring fence were “improvements” that were to be considered in determining the date of completion of construction under ORS 87.035. We conclude that all of the work, except landscaping, comes within the broadly construed definition of “improvement.”

Although First Interstate concedes that ORS 87.010(2) permits a lien for the “preparation of a lot or parcel of land,” and that “preparation” is defined in ORS 87.005(9) to include “excavating, surveying, landscaping, demolition and detachment of existing structures, leveling, filling in, and other preparation of land for construction,” it maintains that plaintiff claimed a lien only under subsection (1) of the statute. However, First Interstate’s contention is that the *103 claim for landscaping is nonlienable and that, because that nonlienable claim was not segregated in the lien, the entire lien is void. The lien asserts a construction lien under a contract for construction of Building D on the described premises. ORS 87.010 gives plaintiff the right to claim that lien. Subsection (2) permits a claim for landscaping; however, a lien claim under that subsection does not have priority over a prior mortgage. Because the bank has not contended that a portion of the lien claimed is not prior to its mortgage, but only that the claim was nonlienable, its argument fails. 3 Accordingly, we conclude that plaintiff has a lien for all of the work and materials involved in that portion of its claim, unless a lien may not be claimed for them because they were performed and provided off the leased premises.

Although the definition of “improvement” (ORS 87.005(5)) may not be sufficiently broad to encompass landscaping, excavation and other work performed outside the property line in every situation, we believe that it is here. Kunkle’s lease required that that work be done as part of the improvements, and it is apparent that the Port required Kunkle to perform that work because, as Kunkle’s project engineer testified, it was vital and necessary for the operation of the main structure. In carrying out his obligation under the lease, Kunkle required plaintiff to perform that work under the construction contract. After the construction contract was executed, First Interstate made its loan to Kunkle, secured by a mortgage on Kunkle’s leasehold interest. It is difficult to believe that it would have made that loan unless it was satisfied that Kunkle had undertaken to comply with his lease obligations. Furthermore, it is reasonable to assume that all of those improvements enhanced the value of the bank’s security in Kunkle’s leasehold. Under the circumstances here, we conclude that the questioned claims relating to labor and materials performed and supplied off the leased premises are lienable under ORS 87.010.

First Interstate also challenges the trial court’s refusal to invalidate the lien, because it contains an unsegregated, nonlienable charge of $41,450 for materials delivered to

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A-C Construction, Inc. v. Bakke Corp.
956 P.2d 219 (Court of Appeals of Oregon, 1998)
Northwest Natural Gas Co. v. Chase Gardens, Inc.
933 P.2d 370 (Court of Appeals of Oregon, 1997)
Knez Building Materials Co. v. Bell-Air Estates, Inc.
927 P.2d 608 (Court of Appeals of Oregon, 1996)
Alley v. Erbach
747 P.2d 360 (Court of Appeals of Oregon, 1987)
Northwest Ironworks, Inc. v. Rippling River Development Corp.
691 P.2d 111 (Court of Appeals of Oregon, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
686 P.2d 399, 69 Or. App. 99, Counsel Stack Legal Research, https://law.counselstack.com/opinion/robertson-hay-wallace-v-kunkle-orctapp-1984.