Northwest Ironworks, Inc. v. Rippling River Development Corp.

691 P.2d 111, 71 Or. App. 144
CourtCourt of Appeals of Oregon
DecidedNovember 21, 1984
Docket82-4-353; CA A27874
StatusPublished

This text of 691 P.2d 111 (Northwest Ironworks, Inc. v. Rippling River Development Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northwest Ironworks, Inc. v. Rippling River Development Corp., 691 P.2d 111, 71 Or. App. 144 (Or. Ct. App. 1984).

Opinion

NEWMAN, J.

Defendants appeal from a judgment foreclosing a construction lien. ORS 87.010. We affirm.

Defendant Rippling River Development Corporation (owner) contracted with Bart Hess Building Contractor, Inc. (Hess), the general contractor, for construction of a restaurant and lounge at Rippling River Lodge.1 Plaintiff orally agreed with Hess to furnish and fabricate the steel beams, trusses and miscellaneous steel for the job. Hess agreed to pay plaintiff $96,510.2 As part of the owner’s “fast track” construction plans, plaintiff began to fabricate the steel before the owner’s architects had completed their drawings. With the assistance of the architects and engineers, plaintiff used the owner’s incomplete architectural drawings to prepare more detailed shop drawings, from which it fabricated the steel in its shop. Although plaintiff sent most of the fabricated steel to the job site before December 1, 1981, it continued to do so throughout December and into January 1982. Hess assembled the steel on-site.

Some of the steel did not fit properly. Two support columns for overhead beams and two “saddles” were too long, because Hess had given plaintiff misinformation about the dimensions of the building foundation. Plaintiff did not fabricate two “hangers,” because they were not shown on the owner’s architectural drawing. Hess asked plaintiff to send a welder to make adjustments to the steel and to add the missing pieces. Plaintiff sent its subcontractor, J & J Welding, to weld on site on December 18 and 21, 1981. In late January 1982, Hess assembled two “triple-column assemblies.” Each contained about 40 pieces that plaintiff had supplied and that supported the second floor and roof of the structure. Except for one angle clip that plaintiff placed on the wrong side of a beam, the pieces complied with the architectural drawings. Certain bolt holes did not line up, although they were placed as specified in the architectural drawings. The owner’s [147]*147engineers permitted plaintiff to weld the pieces together rather than bolt them. Plaintiff sent two employes to the site in late January for three days to do that welding and to replace the angle clip.

On completion the owner paid Hess the full amount that Hess owed to plaintiff, but Hess went bankrupt and did not pay plaintiffs last progress billing for $64,180. On March 10,1982, plaintiff filed a construction lien for $64,198, claiming $67,249.36 for materials and $27,710.64 for labor, less $30,780 that Hess had previously paid. Plaintiffs lien notice described its labor as “welding, steel installation, supervision and inspection, and fabrication.”

Plaintiff did not give a materialman’s notice to the owner within ten days of delivery of the materials for which it claimed a lien. ORS 87.021. Defendants first assign as error that the court found that ORS 87.021(4) excused plaintiff from giving the notice, because it performed “labor upon an improvement.” ORS 87.021 provided:

“(1) Except where materials or supplies are delivered at the request of the owner, a person furnishing materials or supplies for the construction of an improvement and for which a lien may be claimed under ORS 87.010 shall give a delivery notice to the owner of the site. The delivery notice shall be given not later than 10 days after the date of delivery, and is not required for subsequent deliveries.
<<* * * * *
“(3) A lien for material or supplies furnished shall not be enforced unless the notice required by subsection (1) of this section is given.
“(4) A person who performs labor upon an improvement and in addition furnishes material used in the construction of that improvement need not give the notice required by subsection (1) of this section in order to acquire a lien under ORS 87.010.”3 (Emphasis supplied.)

Defendants argue that plaintiffs labor was not “labor upon an improvement,” because its on-site labor only corrected errors in materials that it had supplied and the rest of its labor was [148]*148off-site. Accordingly, defendants argue that plaintiffs lien is invalid, because it did not give a materialman’s notice. We disagree.

*

Plaintiffs on-site labor was “labor upon an improvement” within the meaning of ORS 87.021(4). The statute does not expressly require any particular amount of labor. Plaintiffs on-site labor was not de minimis. See Hays v. Pigg, 267 Or 143, 515 P2d 924 (1973); Robertson, Hay & Wallace v. Kunkle, 69 Or App 99, 105 n 4, 686 P2d 399 (1984); Deal v. Edwards, 51 Or App 203, 204, 624 P2d 1099 (1981). Plaintiffs employes and subcontractor worked on-site for five days. We may attribute to plaintiff the labor of both its employes and its subcontractor. See Timber Structures v. C.W.S.C. Wks., 191 Or 231, 249, 229 P2d 623 (1951); Christman v. Salway et al., 103 Or 666, 686, 205 P 541 (1922).

Defendants assign as error that the court found that plaintiffs on-site labor was required because of errors made by both plaintiff and defendants. We agree with the finding. The architectural drawings and the “fast track” construction program were causes of errors. Plaintiff was not solely responsible for the errors that it corrected on-site. We also agree with the court’s finding that “fabrication of such extensive structural steel in a subcontractor’s shop will seldom be so perfect as to preclude on-site labor.” Moreover, the statute does not exclude plaintiffs labor that merely corrected errors.

Because we hold that plaintiffs on-site labor was “labor upon an improvement” and, accordingly, that plaintiff did not need to give a materialman’s notice to the owner, we do not need to decide if plaintiffs off-site labor, under the facts here, was also “labor upon an improvement.”

Defendants also assign as error the trial court’s finding that the lien was timely filed.4 ORS 87.035(1) provides:

“Every person claiming a lien under ORS 87.010(1) or (2) shall file the claim not later than 90 days after he has ceased to provide labor, rent equipment or furnish materials or 60 days after completion of construction, whichever is earlier.”

[149]*149Plaintiff provided materials into January 1982. The court correctly concluded that the 90-day period did not commence to run before December 10, 1981.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Deal v. Edwards
624 P.2d 1099 (Court of Appeals of Oregon, 1981)
Timber Structures, Inc. v. C. W. S. Grinding & MacHine Works
229 P.2d 623 (Oregon Supreme Court, 1951)
Hays v. Pigg
515 P.2d 924 (Oregon Supreme Court, 1973)
Robertson, Hay & Wallace v. Kunkle
686 P.2d 399 (Court of Appeals of Oregon, 1984)
Christman v. Salway
205 P. 541 (Oregon Supreme Court, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
691 P.2d 111, 71 Or. App. 144, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northwest-ironworks-inc-v-rippling-river-development-corp-orctapp-1984.