Stricker v. Taylor

975 P.2d 930, 158 Or. App. 608, 1999 Ore. App. LEXIS 218
CourtCourt of Appeals of Oregon
DecidedFebruary 24, 1999
Docket95-3142; CA A97531
StatusPublished

This text of 975 P.2d 930 (Stricker v. Taylor) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stricker v. Taylor, 975 P.2d 930, 158 Or. App. 608, 1999 Ore. App. LEXIS 218 (Or. Ct. App. 1999).

Opinion

*610 LANDAU, P. J.

Defendants appeal a judgment entered against them in an action for hen foreclosure, ORS 87.060, and breach of contract. We reverse and remand for entry of a modified judgment.

Defendants own property in Lincoln County on which they planned to construct a multistory hotel. In the fall of 1994, defendant H. H. Taylor (Taylor) met with plaintiff Andy Strieker, P. E., 1 a licensed civil and structural engineer, to discuss hiring plaintiff to prepare designs for the project and to advise Taylor on how to build the project. Taylor told plaintiff that he thought the building could be constructed with a wood frame for approximately $900,000. On October 27,1994, plaintiff sent a proposal to Taylor, which provided, in part:

“The billing rate for this project is $65 per hour for design review and structural design. Substantial changes to the design may be cause for an increased design fee. In this event, additional charges will be presented to you prior to proceeding with any changes.
“TOTAL PRICE (not to exceed) = $7200
“* * * Prior to proceeding with this project, I will require a $1000 retainer.”

(Boldface in original.) The next day, Taylor faxed a letter to plaintiff seeking further details on what areas were covered by plaintiffs proposal. On October 29, 1994, plaintiff responded to Taylor’s letter and advised him that he would provide work on “[s]ite utilities” and “[ljandscaping and parking areas” “as needed as an extra item. Cost will be up to $500 depending on what is required by” the appropriate agencies. Plaintiff also stated that any additional reports required by Lincoln County or by the state would be subject to additional fees. Defendants paid plaintiff a retainer in January 1995, and plaintiff began work on the project. On January 30,1995, plaintiff advised Taylor that, contrary to Taylor’s expectations, the building would cost not $900,000, but between *611 $1,200,000 and $1,350,000. Plaintiff also advised Taylor that, to comply with applicable building codes, the building would have to be built with a steel framework.

Taylor was unhappy with plaintiffs conclusions and told plaintiff that he wanted a wood building designed to reduce construction costs as much as possible. By early April 1995, plaintiff completed the designs for a steel frame hotel. Plaintiff offered an alternative design idea to Taylor that called for reducing the hotel by one story and modifying its design so that it could be built out of wood and that the costs would be reduced. Taylor did not communicate with plaintiff for several weeks and, at the end of April 1995, told plaintiff that he was not going to pay him for the work he had done because he was disappointed that the designs did not fit the target price. On April 26,1995, plaintiff resigned. On May 8, 1995, plaintiff sent a letter to Taylor attaching his final invoice:

“Attached you will find my final invoice, plus the previously unpaid invoice, for the subject project. The new invoice contains only the hours worked in April and brings the total amount under the not to exceed price that I quoted you for the full set of plans including the site drainage plan and design ($7200 + $500).”

Taylor refused to pay the outstanding balance. Plaintiff served a Notice of Right to Lien on Taylor and, on June 16, 1995, filed a lien against defendants’ property. The face of the lien stated a total due of $9,035, with a credit of $3,510 for sums already paid, leaving a balance due of $5,525. Attached to the lien were invoices totaling $7,540.

A month later, plaintiff filed his complaint, alleging three claims: breach of contract, quantum meruit, and lien foreclosure. Defendants answered, denying the allegations in the complaint and asserting counterclaims for professional negligence and breach of contract. At trial, plaintiff testified that he prepared a summary of all of the hours he worked and that his lawyer prepared the hen of $9,035 based on that summary. The breach of contract action also was based on that amount. After a bench trial, the trial court found in favor of plaintiff on the breach of contract and lien foreclosure claims. The judgment awarded plaintiff a net amount of *612 $5,525 on the breach of contract claim, with interest from April 26, 1995, and granted the lien foreclosure in the amount of $5,525, along with attorney fees on the lien claim.

On appeal, defendants make two assignments of error. First, they assign error to the granting of the lien foreclosure. They argue that, because the lien was intentionally overstated, the trial court should have granted their motion to dismiss that claim. Secondly, defendants assign error to the trial court’s award of $9,035 on the breach of contract claim. Defendants assert that, at most, the trial court should have awarded $7,200, the not-to-exceed contract price. Plaintiff argues that the lien foreclosure award was proper because the amount was not overstated and that, even if it was overstated, the error was not fraudulent or so grossly negligent as to invalidate the lien. Similarly, on the breach of contract claim, plaintiff argues that evidence supports the trial court’s judgment that plaintiff was owed $9,035 under the contract.

We review lien foreclosure judgments de novo. A-C Construction, Inc. v. Bakke Corp., 153 Or App 41, 45, 956 P2d 219, rev den 327 Or 553 (1998). After carefully reviewing the record, we agree with defendants that the lien amount of $9,035 was overstated. The terms of plaintiffs contract for engineering services were defined and clarified in the correspondence between plaintiff and Taylor from October 27 to October 29, 1994. The terms of the contract included a “not to exceed” price of $7,200, with the understanding that if designs for “site utilities” and “landscaping and parking areas” were needed, up to an additional $500 would be added to the contract price. The contract also provided that “additional charges would be presented to [defendants] prior to proceeding with any changes.” We find no evidence that there was a change to that contract term, that plaintiff “presented” any “additional charges” to defendants before incurring them, or that defendants agreed to any additional fees, including the fees for site utilities and landscaping and parking areas. Moreover, plaintiffs letter of May 8, 1995, acknowledges that plaintiffs total bill for his work on the project did not exceed the contract price. Accordingly, defendants are not liable for any amount beyond the stated contract price of $7,200.

*613 Defendants assert that, because the hen was overstated, the lien must fail in its entirety. Defendants argue that plaintiff’s neghgence in filing the overstated hen was sufficiently extreme to require invalidation because plaintiff never communicated to defendants that he claimed $9,035 before the hen was filed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brown v. Farrell
483 P.2d 453 (Oregon Supreme Court, 1971)
J. W. Copeland Yards v. Phillips
550 P.2d 438 (Oregon Supreme Court, 1976)
Snyder v. Schram
577 P.2d 935 (Oregon Supreme Court, 1978)
A-C Construction, Inc. v. Bakke Corp.
956 P.2d 219 (Court of Appeals of Oregon, 1998)
Bartels v. McCullough
201 P. 733 (Oregon Supreme Court, 1921)
Becerril v. Hakanson
776 P.2d 1306 (Court of Appeals of Oregon, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
975 P.2d 930, 158 Or. App. 608, 1999 Ore. App. LEXIS 218, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stricker-v-taylor-orctapp-1999.