Travelers Casualty & Surety Co. of America, Inc. v. Long Bay Management Co.

18 Mass. L. Rptr. 284
CourtMassachusetts Superior Court
DecidedSeptember 7, 2004
DocketNo. 015490BLS
StatusPublished

This text of 18 Mass. L. Rptr. 284 (Travelers Casualty & Surety Co. of America, Inc. v. Long Bay Management Co.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Travelers Casualty & Surety Co. of America, Inc. v. Long Bay Management Co., 18 Mass. L. Rptr. 284 (Mass. Ct. App. 2004).

Opinion

van Gestel, J.

“(T]he arbitration procedure, when selected by the parties to a contract, should be speedy and not subject to delay and obstruction in the courts.” Quirk v. Data Terminal Systems, Inc., 379 Mass. 762, 767 (1980). In these two related actions the parties, with some assistance from the courts as well, have been oblivious to the mandate of the Supreme Judicial Court regarding contractually agreed-upon arbitration. These cases—filed, respectively,.on November 29, 2001, and December 17, 2001—only now have reached that point wherein arbitration, first demanded in September 2000, has resulted in an Award that the initial demanding party now moves to have vacated.

BACKGROUND

The principal defendant Long Bay Management Company, d/b/a Long Bay Builders, Inc. (“LBBI”) has been sued by Travelers Casualty and Surety Company of America, Inc. (“Travelers”), the successor in interest to LBBI’s bonding company, Reliance Insurance Company (“Reliance”), on issues relating to a construction project in which LBBI was the general contractor and the Massachusetts Housing Finance Agency (“MHFA”) was the owner. On November 5, 1997, Reliance, along with other Reliance Insurance Companies, entered into a Continuing Agreement of Indemnity— Contractor’s Form (the “Indemnity Agreement”) with LBBI and each of the other named defendants. In consideration of the Indemnity Agreement, Reliance provided LBBI with payment and performance bonds (the “Bonds”) for a real estate rehabilitation and construction project in Boston called “Theroch I.”

On May 31, 2000, Travelers succeeded to the interests of Reliance with respect to the Bonds referred to in the Indemnity Agreement.

The Theroch I project was to be accomplished in three phases, with MHFA having the right and the obligation to initiate the start of each phase by a specific Notice to Proceed.

Although LBBI substantially completed Phase I of the project, disputes arose between LBBI and the MHFA. As a result of those disputes, in September 2000, LBBI demanded arbitration (the “Arbitration”) against MHFA for payment for extra and additional work and an extension of time for performance. This arbitration, just resolved—at least subject to the resolution of legal proceedings relating to it—bears an American Arbitration Association (“AAA”) Docket No. 11 Y 110 01006 00.

By letter dated January 24, 2001,2 LBBI purported to terminate the Construction Contract on grounds that MHFA was in default of its obligations. The prior demand for arbitration was, accordingly, amended.

[331]*331On February 2, 2001, MHFA purported to terminate LBBI’s right to proceed under Phases II and III of the Construction Contract. MHFA then brought a counterclaim in the Arbitration.

MHFA, on February 5, 2001, called upon Travelers, pursuant to the Bond, to perform. Travelers then notified LBBI that it proposed to enter into an agreement with the MHFA to perform and complete LBBI’s contract, without prejudice to the rights of LBBI and Travelers to seek reimbursement for all damages sustained by them in the Arbitration proceedings and subject to the obligations of LBBI and the other defendants under the Indemnity Agreement. This agreement, between Travelers and MHFA, was executed on August 6, 2001. LBBI was not a party to the agreement between MHFA and Travelers for completion of the Construction Contract.

Travelers then entered into a completion agreement with Bilt-Rite Construction, Inc., a general contractor, to complete the work for $10,650,000.

On March 14, 2001, LBBI amended its demand for arbitration in matter No. 11 Y 110 01006 00. Later, Travelers filed a supplemental and amended submission with the AAA, alleging that Travelers was entitled to recover from MHFA the difference between the funds on hand for the Construction Contract with LBBI and the cost to complete the project if LBBI was correct that it was not in default and that MHFA was the party in default. Travelers was not named by LBBI as a party to the arbitration.

At about the same time, MHFA filed a counterclaim with the AAA against Travelers and LBBI, asserting that Travelers and LBBI were liable for certain of LBBI’s obligations and liabilities under or arising out of the Construction Contract and the Bond.

MHFA and Travelers were content to have Travelers participate in the then pending arbitration. LBBI was not; and the matter came before this Court for decision. On December 17, 2001, this Court ruled that it was “not convinced that there exists a sufficient contractual basis to compel [LBBI] to arbitrate with [Travelers] over an issue that seems not yet ripe and in which no demand for such arbitration between [LBBI] and [Travelers] is outstanding,” and it declined to permit or order Travelers to remain as a party to the arbitration.3 Travelers sought relief from the Appeals Court.

In the meantime, the arbitration between LBBI and MHFA proceeded. It was far from speedy and not subject to delay. The hearings sprawled over 50 hearing-days, from May 2002 to August 2003. LBBI’s case as petitioner covered 39 days, and MHFA as respondent consumed the balance. LBBI presented 11 fact witnesses, and its principal expert testified for six days. Although not provided with the entire transcript, this Court did receive pages numbering as high as 9,545, and this was before the parties presented closing arguments.

It was not until after the close of the evidence in the arbitration claims between LBBI and MHFA that the Appeals Court rendered its decision on Travelers’ appeal.4 The final two paragraphs of the Appeals Court Opinion read as follows:

Pursuant to G.L.c. 251, Sec. 2A, a party may apply to the Superior Court for an order to consolidate one arbitration proceeding with another. The circumstances here warrant a consolidation order. The Long Bay/MHFA arbitration and the MHFA/Travelers dispute arise from the veiy same contract5 and involve common issues of law. Long Bay has not shown it would be unduly prejudiced by consolidating the proceedings.
The Superior Court’s order of December 18, 2001, is vacated, and the case is remanded to the Superior Court for further proceedings consistent with this opinion.

Travelers Casualty and Surety Company of America, Inc. v. Long Bay Management Company, 58 Mass.App.Ct. 786, 792-93 (2003).

Despite the Appeals Court’s direction to this Court in its remand for further proceedings consistent with its opinion, the parties did not come before this Court seeking any further order. Instead, apparently over LBBI’s objection, the Arbitration Panel opened up the hearing, for a short two days, to permit Travelers to put on its case without awaiting any action by the Superior Court. LBBI was not permitted by the Arbitrators to actively participate in this small part of the arbitration hearings.

On April 5, 2004, the Arbitrators executed their Award. On the issues between LBBI and MHFA, the Arbitrators found that LBBI’s actions in terminating its agreement with MHFA “were anticipatory in that it had no basis to terminate the agreement and cease work on September 26, 2000, either at common law or under any specific terms of its Agreement with MHFA.” The Panel then found that “MHFA had a right under the Agreement to terminate the Agreement with LBBI because of its cessation of the work and notice of termination.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Quirk v. Data Terminal Systems, Inc.
400 N.E.2d 858 (Massachusetts Supreme Judicial Court, 1980)
City of Lawrence v. Falzarano
402 N.E.2d 1017 (Massachusetts Supreme Judicial Court, 1980)
Barletta v. French
607 N.E.2d 410 (Massachusetts Appeals Court, 1993)
Cavanaugh v. McDonnell & Co. Inc.
258 N.E.2d 561 (Massachusetts Supreme Judicial Court, 1970)
Floors, Inc. v. B. G. Danis of New England, Inc.
401 N.E.2d 839 (Massachusetts Supreme Judicial Court, 1980)
Stop & Shop Companies, Inc. v. Gilbane Building Co.
304 N.E.2d 429 (Massachusetts Supreme Judicial Court, 1973)
Trustees of Boston & Maine Corp. v. Massachusetts Bay Transportation Authority
294 N.E.2d 340 (Massachusetts Supreme Judicial Court, 1973)
Commerce & Industry Insurance v. Bayer Corp.
433 Mass. 388 (Massachusetts Supreme Judicial Court, 2001)
Drywall Systems, Inc. v. ZVI Construction Co.
761 N.E.2d 482 (Massachusetts Supreme Judicial Court, 2002)
School Committee v. Hanover Teachers Ass'n
761 N.E.2d 918 (Massachusetts Supreme Judicial Court, 2002)
Connecticut Valley Sanitary Waste Disposal, Inc. v. Zielinski
763 N.E.2d 1080 (Massachusetts Supreme Judicial Court, 2002)
Softkey, Inc. v. Useful Software, Inc.
756 N.E.2d 631 (Massachusetts Appeals Court, 2001)
Travelers Casualty & Surety Co. of America, Inc. v. Long Bay Management Co.
792 N.E.2d 1013 (Massachusetts Appeals Court, 2003)
Hague v. Piva
808 N.E.2d 843 (Massachusetts Appeals Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
18 Mass. L. Rptr. 284, Counsel Stack Legal Research, https://law.counselstack.com/opinion/travelers-casualty-surety-co-of-america-inc-v-long-bay-management-co-masssuperct-2004.