Gargano & Associates, P.C. v. Swider

770 N.E.2d 506, 55 Mass. App. Ct. 256
CourtMassachusetts Appeals Court
DecidedJune 21, 2002
DocketNo. 98-P-984
StatusPublished
Cited by8 cases

This text of 770 N.E.2d 506 (Gargano & Associates, P.C. v. Swider) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gargano & Associates, P.C. v. Swider, 770 N.E.2d 506, 55 Mass. App. Ct. 256 (Mass. Ct. App. 2002).

Opinion

Rapoza, J.

This case comes before us on the consolidation of three appeals3 stemming from contractual dealings between the three plaintiffs, Gargano & Associates, RC. (G & A), and Paul and Sheila Gargano (Garganos), and the defendant, John Swider & Associates (JSA). The Garganos entered into a contract with JSA for the construction of a home, and G & A4 entered into a separate contract with JSA for the renovation of its law office space. In the wake of the performance of those agreements, there followed arbitration proceedings and litigation in the Superior Court, which, in turn, gave rise to the appeals that we consider here: (1) an appeal by the Garganos from the entry of summary judgment in favor of JSA on the Garganos’ claim pursuant to G. L. c. 93A; (2) an appeal by G & A from the entry of summary judgment in favor of JSA on G & A’s claim pursuant to G. L. c. 93A; and (3) an appeal by G & A from a judgment of the Superior Court confirming the arbitration award issued in favor of JSA against G & A. We affirm.

Background. The Garganos contracted with JSA to construct a home in Hyannisport, and G & A entered into a separate contract with JSA to renovate G & A’s law office space in Cambridge. Each contract included a provision stating that contract claims and disputes were to be resolved by arbitration.5 Unhappy with the work performed on their respective projects, both the Garganos and G & A refused to make final payment to the contractor, asserting that JSA had breached its contractual obligations by failing to perform certain work and by completing other tasks in an unworkmanlike manner. In response, JSA [258]*258filed demands for arbitration against both the Garganos and G & A.

In their respective “answering statements” to ISA’s demands for arbitration, G & A and the Garganos claimed to have suffered damages due to ISA’s own breaches and alleged violations of c. 93A. They also disputed the arbitrability of the claims raised, although both subsequently participated in the ensuing arbitrations. After filing their answering statements to ISA’s demands for arbitration, the Garganos and G & A presented a joint demand letter to ISA pursuant to G. L. c. 93A, seeking compensation in the total amount of $225,000.

Following an exchange of discovery, ISA and the Garganos conducted an eleven-day arbitration over the summer months of 1997 regarding the construction of the Hyannisport home. Prior to the hearing, they had agreed to bifurcate the proceedings, with the Garganos’ c. 93A claim to be “revisited” after a decision was rendered relative to the various contract claims. On October 9, 1997, the arbitrator awarded ISA a net amount of $117,279 “in full settlement of all claims and/or counterclaims submitted to this arbitration.” No further action was taken with respect to the c. 93A claim of the Garganos. On March 30, 1998, the arbitration award was confirmed in the Superior Court.

Approximately one month after the arbitrator’s decision in favor of ISA, the Garganos and G & A filed a joint complaint in the Superior Court against the contractor, each alleging the breach of their respective contracts and violations of c. 93A by ISA. ISA subsequently filed a motion to dismiss the complaint, which was converted, by agreement, into a motion for summary judgment. That motion was granted in favor of ISA not only with respect to the contractual claims of the Garganos and G & A, but also with respect to G & A’s claim pursuant to c. 93A, on the ground that the parties had contractually agreed that such claims would be resolved through arbitration. However, the motion judge denied ISA summary judgment as to the Garganos’ c. 93A claim, stating that it could be maintained in Superior Court irrespective of the arbitration provision in the contract because, he concluded, a [259]*259claim brought under G. L. c. 93A, § 9, cannot be involuntarily placed before an arbitrator.6 The judge specifically noted, however, that the award’s impact on the Garganos’ claim under c. 93A was not before him. A separate and final judgment entered in favor of JSA on G & A’s claims, and G & A appealed.

A second arbitration hearing was held before a different arbitrator in February, 1998, concerning the dispute over work done by JSA at G & A’s law office in Cambridge. On April 22, 1998, the arbitrator awarded JSA a net amount of $60,167.38 and specifically noted that G & A was awarded nothing on its c. 93A claim. That award was also subsequently confirmed in the Superior Court, and G & A appealed.

On April 30, 1998, JSA filed a second motion for summary judgment claiming that, despite the motion judge’s prior ruling to the contrary, the Garganos’ c. 93A claim could not be pursued in Superior Court, ostensibly because it had already been submitted to binding arbitration during the summer months of 1997.7 On May 29, 1998, the same motion judge who had initially denied JSA’s first motion for summary judgment as to the Garganos’ c. 93A claim allowed its second such motion. The judge concluded that by raising their c. 93A claim in the 1997 arbitration proceeding, the Garganos were foreclosed from pursuing the same relief in Superior Court. The Garganos appealed from the ensuing judgment.

Discussion. “Summary judgment will be upheld when, ‘viewing the evidence in the light most favorable to the nonmoving party, all material facts have been established and the moving party is entitled to a judgment as a matter of law.’ ” Metropolitan Property & Cas. Ins. Co. v. Choukas, 47 Mass. App. Ct. 196, 199 (1999), quoting from White v. Boston, 428 Mass. 250, 251-[260]*260252 (1998). Considering the facts in that light, we review the claims raised in this appeal.

1. Garganos ví. JSA. The Garganos first assert that it was error for the motion judge to grant ISA’s second motion for summary judgment on the ground that they had voluntarily submitted their G. L. c. 93A, § 9, claim to arbitration under the contract, thus foreclosing any consideration of the same claim in the Superior Court. They also contend that whether their § 9 claim was submitted to the arbitrator constitutes a genuine issue of material fact.

Before proceeding to court with a claim under G. L. c. 93A, § 9, a consumer is under no obligation to exhaust other remedies, including arbitration provisions provided by contract. See Hannon v. Original Gunite Aquatech Pools, Inc., 385 Mass. 813, 816 (1982). See also Greenleaf Engr. & Constr. Co. v. Teradyne, Inc., 15 Mass. App. Ct. 571, 574-575 (1983). General Laws c. 93A, § 9(6), states as follows:

“Any person entitled to bring an action under this section shall not be required to initiate, pursue or exhaust any remedy established by any regulation, administrative procedure, local, state or federal law or statute or the common law in order to bring an action under this section ...” (emphasis supplied).

See Hannon v. Original Gunite Aquatech Pools, Inc., 385 Mass. at 826 (provisions of G. L. c. 93A, § 9(6), apply to arbitration, which is “comprehended within either ‘common law’ or statutory remedies”).

The issue here is whether the Garganos can voluntarily submit a § 9 claim to arbitration and still maintain the right to bring that claim in Superior Court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Julsonnet v. Tophills Inc.
D. Massachusetts, 2024
Hug v. Gargano & Associates, P.C.
923 N.E.2d 1065 (Massachusetts Appeals Court, 2010)
Stop & Shop Supermarket Co. v. Loomer
837 N.E.2d 712 (Massachusetts Appeals Court, 2005)
Gossels v. Fleet National Bank
2005 Mass. App. Div. 144 (Mass. Dist. Ct., App. Div., 2005)
Frullo v. Landenberger
814 N.E.2d 1105 (Massachusetts Appeals Court, 2004)
Beals v. Commercial Union Insurance
808 N.E.2d 824 (Massachusetts Appeals Court, 2004)
1-A Equipment Co. v. Icode, Inc.
2003 Mass. App. Div. 30 (Mass. Dist. Ct., App. Div., 2003)

Cite This Page — Counsel Stack

Bluebook (online)
770 N.E.2d 506, 55 Mass. App. Ct. 256, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gargano-associates-pc-v-swider-massappct-2002.