Greenleaf Engineering & Construction Co. v. Teradyne, Inc.

447 N.E.2d 9, 15 Mass. App. Ct. 571, 1983 Mass. App. LEXIS 1277
CourtMassachusetts Appeals Court
DecidedMarch 31, 1983
StatusPublished
Cited by15 cases

This text of 447 N.E.2d 9 (Greenleaf Engineering & Construction Co. v. Teradyne, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greenleaf Engineering & Construction Co. v. Teradyne, Inc., 447 N.E.2d 9, 15 Mass. App. Ct. 571, 1983 Mass. App. LEXIS 1277 (Mass. Ct. App. 1983).

Opinion

Cutter, J.

This dispute grows out of two contracts, each dated April 3, 1980. The first (Contract No. 1), between *572 Teradyne, Inc. (Teradyne), and Greenleaf Engineering & Construction Company, Inc. (Construction), provided that Construction was to perform services as project manager/construction manager with respect to the renovation of 1000 Washington Street, Boston. The second contract (Contract No. 2), between Teradyne and Greenleaf Engineers, Inc. (Engineers), provided that Engineers was to furnish other professional services as project engineer on the same renovation. Contract No. 2, but not Contract No. 1, contained a broad provision for arbitration.

Construction brought this action against Teradyne on April 21, 1982, to recover a fee for services related to Contract No. 1. The complaint alleged that on July 31, 1981, Construction and Teradyne had executed a settlement agreement. 2 In that Teradyne had released Construction “from all claims for costs and expenses due to any asserted failure” to perform under Contract No. 1. Construction under that agreement was to negotiate a settlement fee with Teradyne “as soon as practicable.”

Teradyne in its answer filed a counterclaim against Construction and also a third-party claim joining as third-party defendants Engineers and Sidney J. Greenleaf, individually. Both the counterclaim and the third-party claim asserted counts in contract, fraud, misrepresentation, and negligence against Construction, Engineers, and Greenleaf, as well as counts under G. L. c. 93A, § 11.

Greenleaf, as president of Construction and of Engineers, respectively, had signed both Contract No. 1 and Contract No. 2. It appeared, from pleadings (and exhibits thereto) and affidavits, that Greenleaf was a director and a shareholder of Construction. Engineers and Construction had the same mail address. Engineers apparently had been in existence for some time before negotiations for the two *573 contracts were completed. Construction, however, was not organized as a corporation until shortly before the contracts were signed.

A vice-president of Teradyne, Owen Robbins, by affidavit stated that he had dealt almost entirely theretofore with Greenleaf as the president of “Engineers and the controlling person in . . . [that] company” and had been persuaded by him that Greenleaf should assume “the dual roles of Project Engineer and Project Manager/Construction Manager.” Robbins’s affidavit, however, reveals that he, for Teradyne, knew that he was dealing with two separate corporations.

On a motion by Engineers, a Superior Court judge ordered Teradyne and Engineers to proceed to arbitration on the issues between them, as required by Contract No. 2. He denied Teradyne’s motion to require Construction to arbitrate its claims against Teradyne under Contract No. 1 and the settlement agreement, and stayed (pending arbitration) further court proceedings in the controversy between Teradyne and Engineers. Teradyne’s motions (G. L. c. 231, § 118) for relief from these interlocutory orders were denied by a single justice of this court. The case is before us on Teradyne’s appeal from the orders of the Superior Court. We agree with those orders essentially on the grounds concisely stated by the Superior Court judge. Because the orders under review are closely related, we discuss them both, although only one of the orders (that denying Teradyne’s motion to compel Construction to arbitrate) would seem to be appealable under G. L. c. 251, § 18, inserted by St. 1960, c. 374, § 1. See School Comm. of Agawam v. Agawam Educ. Assn., 371 Mass. 845, 846-848 (1977).

1. Teradyne argues that the relationship among Greenleaf (as an individual), Construction, and Engineers is close and that Greenleaf’s influence in the affairs of Engineers and Construction is pervasive, particularly with respect to his and the corporations’ participation in both contracts. From this Teradyne contends that Engineers’ *574 obligation to arbitrate under Contract No. 2 should be treated as binding upon Construction under Contract No. 1.

The trial judge on this record was not required to regard the tripartite relationship among Construction, Engineers, and Greenleaf as so interwined that it was necessary for Construction to submit to arbitration its claims under Contract No. 1 and the settlement agreement (neither of which provided for arbitration). Teradyne had dealt sufficiently with Construction and Engineers separately, at least in negotiating the settlement agreement, as to permit the trial judge to treat the corporations as separate entities with respect to arbitration. The record, at least at this stage, does not show fraudulent, unconscionable, or ambiguous behavior, requiring disregard of the corporate entity of either corporation. See the discussion in My Bread Baking Co. v. Cumberland Farms, Inc., 353 Mass. 614, 618-621 (1968), and cases there cited at 619 n.7. The trial judge concluded that the case came within the general rule laid down in Galdi v. Caribbean Sugar Co., 327 Mass. 402, 407-408 (1951), and Westcott Constr. Corp. v. Cumberland Constr. Co., 3 Mass. App. Ct. 294, 297-299 (1975), and reasonably refused to order a consolidated arbitration, including Construction’s claims. 3 See Stop & Shop Cos. v. Gilbane Bldg. Co., 364 Mass. 325, 328-330 (1973). See also Danvers v. Wexler Constr. Co., 12 Mass. App. Ct. 160, 162-167 (1981).

2. Teradyne also contends that its claim against Engineers under G. L. c. 93A, § 11, cannot be referred to arbitration. Such a result is not required by Hannon v. Original Gunite Aquatech Pools, Inc., 385 Mass. 813, 825-827 (1982). In that case (brought under c. 93A, § 9) it was held that c. 93A, § 9(6), inserted by St. 1973, c. 939, precluded the issuance of a stay of court proceedings during arbitration in an action under § 9 by a consumer. Subsections (6) to (8) of § 9 expressly make it unnecessary for consumer plaintiffs to *575 exhaust broadly defined administrative and other remedies before proceeding under c. 93A, § 9. As the trial judge properly pointed out, no such provision appears in § 11 (as inserted by St. 1972, c. 614, § 2) which provides a c. 93A remedy to a “person who engages in the conduct of any trade or commerce and who suffers any loss” as a result of practices defined in c. 93A, § 2. See the discussion in 1 Alperin & Chase, Consumer Rights and Remedies, §§ 126 & 140 (1979 & Supp. 1981). See also J. & J. Enterprises, Inc. v. Martignetti, 369 Mass. 535, 540-541 (1976). 4

The trial judge correctly declined to apply to the present case the principles of Wineland v. Marketex Intl., Inc., 28 Wash. App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mongeon v. Arbella Mutual Insurance
15 Mass. L. Rptr. 619 (Massachusetts Superior Court, 2002)
Gargano & Associates, P.C. v. Swider
770 N.E.2d 506 (Massachusetts Appeals Court, 2002)
Drywall Systems, Inc. v. ZVI Construction Co.
761 N.E.2d 482 (Massachusetts Supreme Judicial Court, 2002)
Drywall Systems, Inc. v. ZVI Construction Co.
747 N.E.2d 168 (Massachusetts Appeals Court, 2001)
Rigatti v. LPG USA
12 Mass. L. Rptr. 52 (Massachusetts Superior Court, 2000)
Albertson v. Magnetmakers LLC
11 Mass. L. Rptr. 173 (Massachusetts Superior Court, 2000)
Seacoast Motors of Salisbury, Inc. v. Chrysler Corp.
959 F. Supp. 52 (D. Massachusetts, 1997)
Turner Bros. Construction v. Trustees of Nichols College
3 Mass. L. Rptr. 636 (Massachusetts Superior Court, 1995)
Canal Electric Co. v. Westinghouse Electric Corp.
548 N.E.2d 182 (Massachusetts Supreme Judicial Court, 1990)
North American Consolidated, Inc. v. Kopka
644 F. Supp. 191 (D. Massachusetts, 1986)
Rodgers Builders, Inc. v. McQueen
331 S.E.2d 726 (Court of Appeals of North Carolina, 1985)
Old Rochester Regional Teacher's Club v. Old Rochester Regional School District
18 Mass. App. Ct. 117 (Massachusetts Appeals Court, 1984)
Sabates v. International Med. Centers, Inc.
450 So. 2d 514 (District Court of Appeal of Florida, 1984)
J&K Cement Construction, Inc. v. Montalbano Builders, Inc.
456 N.E.2d 889 (Appellate Court of Illinois, 1983)
Computer Corp. of America v. Zarecor
452 N.E.2d 267 (Massachusetts Appeals Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
447 N.E.2d 9, 15 Mass. App. Ct. 571, 1983 Mass. App. LEXIS 1277, Counsel Stack Legal Research, https://law.counselstack.com/opinion/greenleaf-engineering-construction-co-v-teradyne-inc-massappct-1983.