Drywall Systems, Inc. v. ZVI Construction Co.

747 N.E.2d 168, 51 Mass. App. Ct. 353, 2001 Mass. App. LEXIS 253
CourtMassachusetts Appeals Court
DecidedApril 17, 2001
DocketNo. 98-P-675
StatusPublished
Cited by6 cases

This text of 747 N.E.2d 168 (Drywall Systems, Inc. v. ZVI Construction Co.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Drywall Systems, Inc. v. ZVI Construction Co., 747 N.E.2d 168, 51 Mass. App. Ct. 353, 2001 Mass. App. LEXIS 253 (Mass. Ct. App. 2001).

Opinion

Jacobs, J.

An arbitration panel resolved a construction contract dispute in favor of the plaintiff (Drywall) with an award that included treble damages and attorney’s fees under G. L. c. 93A, § 11. In the course of addressing the parties’ claims under G. L. c. 251, a Superior Court judge allowed a motion for partial summary judgment filed by the defendant (ZVI), concluding that the arbitrators exceeded their authority by awarding multiple damages and attorney’s fees. A judgment was entered vacating the arbitration award to the extent that it allowed c. 93A dam[354]*354ages and fees, but otherwise confirming the award to Drywall in the amount of $447,365, plus interest, and arbitration costs. Both parties appeal. Drywall seeks to restore the award of multiple damages and attorney’s fees, and ZVI claims that the underlying award should not have been confirmed, citing evidentiary errors by the arbitrators.

1. Background. Pursuant to five contracts entered into by the parties, Drywall was to perform, as subcontractor, specified construction work at five retail store sites where ZVI was the general contractor. Two of the sites were in Ohio, two were in New York, and one was in Massachusetts. Each contract was governed by the following arbitration provision: “Any controversy or [c]laim arising out of or related to the [c]ontract, or the breach thereof, shall be settled by arbitration, in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association” (AAA).

In 1995, Drywall filed a demand for arbitration with the AAA seeking monies due under the contracts and “treble damages and legal fees for violation of c. 93A.” Drywall also sought “delay and business liquidation damages” and compensation for extra work. Approximately twenty days of hearings were held before a panel of three arbitrators in Boston during the period between June, 1995, and April, 1996. During the initial hearing, the parties stipulated that Massachusetts law would be applied to each of the contracts in issue. On January 15, 1996, after the completion of approximately fifteen days of hearings, ZVI filed a counterclaim with respect to Drywall’s Massachusetts contract alleging fraud, misrepresentation, breach of contract, and “violation of c. 93A” and seeking “$57,250 plus treble damages” and other fees and costs.

In 1996, the arbitrators awarded Drywall various amounts with respect to each of the five contracts at issue totaling $447,365, and found against ZVI with respect to its counterclaim. They also found, referencing c. 93A, §§ 21 and 11, that ZVI committed unfair and deceptive acts and practices “primarily and substantially” within Massachusetts and that [355]*355ZVI’s acts and omissions were “willful and knowing.” The panel further awarded to Drywall “treble damages” of $894,730 in addition to its contract damages of $447,365. They also awarded Drywall its “reasonable attorney’s fees” in the amount of $146,000.

2. Arbitrability of c. 93A, § 11, multiple damages claims. In ruling that the arbitrators exceeded their authority by awarding multiple damages, the judge relied on a 1989 amendment to c. 93A, § 11, and two cases interpreting that amendment: Bonofiglio v. Commercial Union Ins. Co., 411 Mass. 31 (1991), and Clegg v. Butler, 424 Mass. 413 (1997). We set out a portion of § 11 with the amendment italicized:

“If the court finds for the petitioner, recovery shall be in the amount of actual damages; or up to three, but not less than two, times such amount if the court finds that the use or employment of the method of competition or the act or practice was a willful or knowing violation of said section two. For the purposes of this chapter, the amount of actual damages to be multiplied by the court shall be the amount of the judgment on all claims arising out of the same and underlying transaction or occurrence regardless of the existence or nonexistence of insurance coverage available in payment of the claim.”2

Contrary to the judge’s decision, the 1989 amendment to c. 93A, § 11, does not operate to prohibit an arbitral award of multiple damages in the circumstances of this case. In explaining the purpose of the same language, simultaneously inserted in G. L. c. 93A, § 9(3) (see note 2, supra), the Supreme Judicial Court stated the objective was to “penalize insurers who unreasonably and unfairly force claimants into litigation by wrongfully withholding insurance proceeds.” Clegg v. Butler, supra at 425. As pointed out by Justice Kaplan in Yeagle v. Aetna Cas. & Sur. Co., 42 Mass. App. Ct. 650, 654-655 (1997), the amendment reflected dissatisfaction with a line of cases brought against insurers limiting damages under c. 93A to double or triple those directly caused by the unfair practice and [356]*356was directed at cases in which the “insurer had acted in bad faith in declining reasonable settlement,” thereby obliging a claimant to file suit and obtain a judgment on the underlying claim.3 The perceived inequity was that a plaintiff who brought a c. 93A action after obtaining a judgment on the underlying claim could recover only what amounted to loss of use damages for the period of the wrongful withholding. Id. at 654. The response of the amendment was to permit recovery of a multiple of the underlying judgment itself, generally a far greater penalty to the defendant. See Greelish v. Drew, 35 Mass. App. Ct. 541, 544 (1993).

That statutory response has been circumscribed by Bonofiglio and Clegg. Bonofiglio held that an arbitrator’s award on an underlying claim is not a “judgment” within the meaning of the amendment and, therefore, cannot serve as a basis for multiple damages. In Clegg, the court took a similar approach, not permitting a settlement of the underlying claims to be a multiplicand for multiple damages purposes. These cases, however, do not have the broad effect accorded them by the judge. Both cases involved combined G. L. c. 176D and c. 93A claims of unfair settlement practices brought against insurers and out-of-court resolutions of underlying personal injury claims by way of arbitration or settlement. Each rejected an attempt under c. 93A to multiply the amount paid on the underlying claim on the ground that the amendment permitted only the multiplication of a “judgment” based on that underlying claim. Given the purpose of the 1989 amendment, these cases may be seen as applying only to actions against insurers for unfair settlement practices. See Clegg v. Butler, supra at 425, describing the amendment “[a]s part of a statutory scheme meant to encourage out-of-court resolutions.” So narrowly confined, neither Bonofiglio nor Clegg applies to the circumstances of the case before us. Viewed more broadly, the rule that emerges from Bonofiglio and Clegg is that, in order for a party to be awarded § 11 multiple damages on its underlying claim, as [357]*357distinguished from loss of use damages, the underlying claim must have been reduced to a judgment, see Metropolitan Prop. & Cas. Ins. Co. v. Choukas, 47 Mass. App. Ct. 196 (1999), or must have been resolved in the same proceeding, see Linkage Corp. v. Trustees of Boston Univ., 425 Mass. 1, 27-29, cert. denied, 522 U.S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maverick Construction Management Services, Inc. v. Hodgson
26 Mass. L. Rptr. 369 (Massachusetts Superior Court, 2009)
Janney Montgomery Scott LLC v. Tobin
571 F.3d 162 (First Circuit, 2009)
Kady v. Arbella Mutual Insurance
25 Mass. L. Rptr. 577 (Massachusetts Superior Court, 2009)
Jonas v. Deutsche Bank Securities
24 Mass. L. Rptr. 475 (Massachusetts Superior Court, 2008)
Drywall Systems, Inc. v. ZVI Construction Co.
761 N.E.2d 482 (Massachusetts Supreme Judicial Court, 2002)
Aguilera v. Palm Harbor Homes, Inc.
2001 NMCA 091 (New Mexico Court of Appeals, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
747 N.E.2d 168, 51 Mass. App. Ct. 353, 2001 Mass. App. LEXIS 253, Counsel Stack Legal Research, https://law.counselstack.com/opinion/drywall-systems-inc-v-zvi-construction-co-massappct-2001.