Simas v. House of Cabinets, Inc.

757 N.E.2d 277, 53 Mass. App. Ct. 131, 2001 Mass. App. LEXIS 1009
CourtMassachusetts Appeals Court
DecidedOctober 30, 2001
DocketNo. 99-P-1121
StatusPublished
Cited by21 cases

This text of 757 N.E.2d 277 (Simas v. House of Cabinets, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Simas v. House of Cabinets, Inc., 757 N.E.2d 277, 53 Mass. App. Ct. 131, 2001 Mass. App. LEXIS 1009 (Mass. Ct. App. 2001).

Opinion

Cohen, J.

These cross appeals arise from an eight year old dispute between Simas, a homeowner, and the House of Cabinets, Inc., a building contractor (contractor), over a home-improvement project gone awry. After nonbinding arbitration pursuant to G. L. c. 142A, the case was heard de nova in the Superior Court. A jury returned a verdict for the contractor on Simas’s claim for breach of contract; however, the trial judge reserved a related claim under G. L. c. 93A, § 9, and decided it in favor of Simas. For the reasons that follow, we conclude that neither party’s appeal has merit, and we affirm.

1. Background. In August, .1993, Simas purchased a single-family house in Burlington, Massachusetts, and before moving in, he hired the contractor to make renovations. The parties entered into three separate contracts, all dated August 3, 1993, for work to be done on various parts of the house. The total price of the three contracts was $36,311.93. Under each of the agreements, Simas was to pay the contractor an initial amount upon execution of the contract, additional amounts at various stages of each project, and the balance upon completion. In each contract, the contractor agreed to perform the specified [133]*133work, to obtain all necessary permits, and to “perform this contract in conformity with customary industry standards.” Each contract also contained a clause providing for nonbinding arbitration.

Suffice it to say that the job did not go smoothly, and the project was terminated before the work was completed. After an exchange of written demands and counter-demands, Simas filed a request for arbitration with the home improvement contractor arbitration program of the executive office of consumer affairs, pursuant to G. L. c. 142A, on a form provided by that office.

General Laws c. 142A, entitled “Regulation of Home Improvement Contractors,” was inserted by St. 1991, c. 453. Among other things, it enumerates prohibited acts which may subject a contractor or subcontractor to administrative sanctions, criminal prosecution, and civil remedies. G. L. c. 142A, § 17. It also sets out requirements for residential contracting agreements and authorizes the inclusion of arbitration clauses, so long as the provisions are clearly and conspicuously disclosed in language designated by the director of consumer affairs and business regulation, and each party assents by separately signing and dating the provision. G. L. c. 142A, § 2.1 The statute establishes a private arbitration services program, to be approved by the director, to consider disputes arising from contracts for residential contracting services. G. L. c. 142A, § 4. This program is made available not only in cases where the parties have contracted to use it, as was the case here, but also at the homeowner’s request, in cases where there is no arbitration agreement.2 G. L. c. 142A, § 3(b). The arbitrator’s decision is not final; it may be appealed by seeking a trial de nova in the Superior or District Court, within twenty-one days of the issuance of the arbitrator’s findings. G. L. c. 142A, § 4(e). In the trial de nova, “[a]ll findings of fact issuing from arbitra[134]*134tian shall be taken as prima facie evidence . . . .” G. L. c. 142A, § 4(d).

On February 25, 1994, the arbitration in this case was decided in favor of Simas. The arbitrator found, inter alla, that the contracted work was incomplete and performed poorly; that the contractor violated the payment schedule by invoicing and receiving payment for work that had not been done and materials that had not been delivered; that the contractor failed to procure all legally required permits; and that the contractor covered up work requiring rough inspection without first having had it examined by the appropriate town building officials. The arbitrator awarded Simas damages of $29,957.00, plus $800.00 in reimbursement of the arbitration fee.

On March 11, 1994, the contractor initiated an action in the Superior Court by filing a document entitled “Defendant’s Appeal of Arbitrator’s Decision Pursuant to Massachusetts General Laws Chapter 142A.” Although filed by the contractor, this document was styled as a pleading in which Simas was named as the plaintiff and the contractor was named as the defendant. It prayed for a trial de nova of the arbitrator’s decision and contained a jury demand on behalf of the defendant.3

The contractor’s filing was accepted as the equivalent of a complaint; the case was entered; and discovery ensued. However, because of the manner in which the initial pleading was styled, Simas did not respond with an answer or counterclaim. It was not until nearly a year later that Simas attempted a pleading of his own by filing a paper entitled “Motion to Amend Request for Relief.” In this document, Simas sought leave to amend his request for arbitration to include a demand for relief under G. L. c. 93A. Simas’s motion was allowed, over the contractor’s opposition, by a judge other than the one who later presided at thé trial. As a result, Simas’s c. 93A claim was included with Simas’s claim under G. L. c. 142A in the de nova proceedings.

[135]*135The claim under G. L. c. 142A was submitted to the jury as a simple claim for breach of contract.4 5The jury answered “No” to a special question asking, “Did the House of Cabinets, Inc. breach the contract with Julius J. Simas, Jr.?” Thereafter the judge, in considering the c. 93A claim, found that the contractor had committed a number of violations of G. L. c. 142A that entitled Simas to relief under G. L' c. 93A.5 The judge found further that Simas had suffered damages on account of some, but not all, of these violations and assessed total damages of $19,198.00. Because the judge also found that the contractor had not made a written tender of settlement under G. L. c. 93A, § 9(3), he ruled that Simas was entitled to recover costs of $4,474.30, and attorney’s fees in the amount of $9,800. Judgment therefore entered on the c. 93A claim in the amount of $33,472.30, plus prejudgment interest from October 14, 1993, the date of Simas’s initial written demand to the contractor.

2. Simas’s appeal. Simas raises but one point in his appeal from the judgment against him on the jury’s verdict on the breach of contract claim: that the trial judge erroneously excluded testimony about a telephone conversation on September 28, 1993, between Simas and the contractor’s attorney, and a related letter from the contractor’s attorney to Simas dated October 1, 1993. Simas contends that the excluded evidence was essential to rebut the contractor’s defense to the breach of contract claim, which was that it remained willing to work on the project and to correct any deficiencies, but was prevented from doing so because Simas went to the premises on September 28, 1993, and removed the key that the contractor had been using to enter. According to Simas, the excluded testimony and [136]*136letter would have established that, by September 28, the contractor had refused to perform any further work unless Simas made an additional, unjustified payment.

The fatal flaw in Simas’s argument is that the trial judge did, in fact, permit him to testify that he removed the key only after he learned that the contractor was refusing to do any more work unless it received more money. Since the substance of the excluded conversation ultimately came in evidence, Simas suffered no prejudice from the trial judge’s ruling.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DAMIAN ANKETELL & another v. OFFICE OF CONSUMER AFFAIRS AND BUSINESS REGULATION.
101 Mass. App. Ct. 628 (Massachusetts Appeals Court, 2022)
Great Day Improvements, LLC v. Spinale-Rea
122 N.E.3d 1102 (Massachusetts Appeals Court, 2019)
Downey v. Chutehall Construction Co., Ltd.
42 N.E.3d 1194 (Massachusetts Appeals Court, 2016)
Forbes v. D&D Mulch & Landscape, Inc.
2015 Mass. App. Div. 11 (Mass. Dist. Ct., App. Div., 2015)
Groleau v. Russo-Gabriele
32 Mass. L. Rptr. 513 (Massachusetts Superior Court, 2014)
Klairmont v. Gainsboro Restaurant, Inc.
465 Mass. 165 (Massachusetts Supreme Judicial Court, 2013)
Williams v. Perrault
2011 Mass. App. Div. 180 (Mass. Dist. Ct., App. Div., 2011)
Driscoll v. Toll MA Ltd. Partnership
26 Mass. L. Rptr. 345 (Massachusetts Superior Court, 2009)
McCarthy v. Quirk Nissan, Inc.
2009 Mass. App. Div. 159 (Mass. Dist. Ct., App. Div., 2009)
Booth v. Augis
889 N.E.2d 59 (Massachusetts Appeals Court, 2008)
Harrison Construction, LLC v. Cirurgiao
23 Mass. L. Rptr. 272 (Massachusetts Superior Court, 2007)
Yetman v. Cavanagh
2007 Mass. App. Div. 162 (Mass. Dist. Ct., App. Div., 2007)
Richards v. Arteva Specialties S.A.R.L.
850 N.E.2d 1068 (Massachusetts Appeals Court, 2006)
Reddish v. Bowen
849 N.E.2d 901 (Massachusetts Appeals Court, 2006)
West Waters v. Earthlink, Inc.
21 Mass. L. Rptr. 219 (Massachusetts Superior Court, 2006)
Anderson v. Brake King Automotive, Inc.
2006 Mass. App. Div. 15 (Mass. Dist. Ct., App. Div., 2006)
Evangelista v. Hingham Mutual Fire Insurance
19 Mass. L. Rptr. 105 (Massachusetts Superior Court, 2005)
Massachusetts Port Authority v. Employers Insurance of Wausau
19 Mass. L. Rptr. 32 (Massachusetts Superior Court, 2004)
Beals v. Commercial Union Insurance
808 N.E.2d 824 (Massachusetts Appeals Court, 2004)
Commonwealth v. Lepper
798 N.E.2d 1030 (Massachusetts Appeals Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
757 N.E.2d 277, 53 Mass. App. Ct. 131, 2001 Mass. App. LEXIS 1009, Counsel Stack Legal Research, https://law.counselstack.com/opinion/simas-v-house-of-cabinets-inc-massappct-2001.