Pioneer Industries, a Division of Sos Consolidated, Inc. v. Gevyn Construction Corporation

458 F.2d 582, 1972 U.S. App. LEXIS 10147
CourtCourt of Appeals for the First Circuit
DecidedApril 11, 1972
Docket71-1401
StatusPublished
Cited by3 cases

This text of 458 F.2d 582 (Pioneer Industries, a Division of Sos Consolidated, Inc. v. Gevyn Construction Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pioneer Industries, a Division of Sos Consolidated, Inc. v. Gevyn Construction Corporation, 458 F.2d 582, 1972 U.S. App. LEXIS 10147 (1st Cir. 1972).

Opinion

McENTEE, Circuit Judge.

This appeal involves the arbitrability of a claim for materials on a subcontract between a supplier and the principal contractor and its surety on a Massachusetts public construction project. On October 27, 1967, the defendant, Gevyn Construction Corporation, entered into a written contract with the County of Middlesex for the construction of a new County Superior Court House in the City of Cambridge. Pursuant to the contract and as required by state law, a bond was executed by Gevyn as principal and the codefendant, Travelers Indemnity Company, as surety to secure payment for all labor and materials furnished in the construction. On January 12, 1968, Gevyn entered into a subcontract with Pioneer Industries under which the latter agreed for a subcontract price of $98,300 to furnish certain materials required on the project. Pioneer alleges that it has completed its subcontract with Gevyn, has furnished certain extras and that after deducting all payments and credits there remains due from Gevyn a balance of $59,787.36, plus interest for which Pioneer demanded payment but which Gevyn has refused to pay.

During the course of construction a dispute arose between the County and Gevyn concerning the performance of the principal contract, and as a result, the County terminated the contract on May 29, 1970. About the same time Gevyn instituted an arbitration proceeding against the County to resolve certain controversies relating to so-called “foundation remedial work.” Pioneer, along with a number of other subcontractors, is a party to this arbitration and asserted a claim for $10,341. This claim is not related, however, to the instant case. Subsequently, Gevyn commenced a second arbitration proceeding against the County asserting a claim for wrongful termination of the principal contract. The record indicates that included in this second arbitration proceeding is a claim for all work performed and/or damages incurred by Gevyn, including claims by Pioneer and other affected subcontractors and suppliers. Gevyn contends that the termination arbitration will be determinative of Pioneer’s claim against it as well as those of the other subcontractors and suppliers. 1 Pioneer, however, is not a party to the second arbitration proceeding and has not asserted any claim therein. On the contrary, it filed a timely sworn statement of its claim with the Middlesex County Treasurer and brought this suit to enforce a statutory right of payment against Gevyn and its surety, Travelers, under Mass.Gen.Laws ch. 149, § 29 (1971). After removing the case to the district court on diversity grounds Gevyn and Travelers filed motions under the Federal Arbitration Act for an order staying the suit and directing Pioneer to *584 proceed with arbitration. The district court denied both motions and this appeal followed. 2

As indicated above, the principal issue on appeal is whether Pioneer is contractually required to arbitrate its claim against Gevyn or whether it is entitled to proceed with the instant suit and reduce its claim to judgment. Since it is well settled that arbitration is a matter of agreement between the parties, the question here is whether Pioneer agreed, under any reasonable construction of its subcontract with Gevyn to arbitrate the instant dispute. See United Steelworkers of America v. American Mfg. Co,, 363 U.S. 564, 80 S.Ct. 1343, 4 L.Ed.2d 1403 (1960); United Steelworkers of America v. Warrior & Gulf Navigation Co., 363 U.S. 574, 80 S.Ct. 1347, 4 L.Ed.2d 1409 (1960); United Steelworkers of America v. Enterprise Wheel & Car Corp., 363 U.S. 593, 80 S.Ct. 1358, 4 L.Ed.2d 1424 (1960).

Initially we assume, as defendants vigorously argue, that the broad arbitration provision of the principal contract is incorporated by reference into the subcontract. However, Section 1 of the subcontract states, “In the event of any conflict between the provisions of this contract and of the Principal Contract the provisions of this contract shall control.” Therefore the question here is whether any provision of the subcontract is applicable to arbitrability of this dispute. Section 18 of the subcontract provides as follows:

“Any dispute or claim between the parties arising out of this Contract or any termination thereof by the Contractor shall be submitted to a Court of Competent Jurisdiction by either party if $3500.00 or more is involved. Should such dispute or claim be in an amount under $3500.00, then the parties hereto agree to arbitrate such dispute in accordance with the rules of the American Arbitration Association then obtaining.”

Since Pioneer’s claim exceeds $3500, this section is squarely applicable and arbitration is not required. Defendants contend that § 18 does not cover Pioneer’s claim because it arises out of the termination of the principal contract by the owner and thus is not a claim arising out of the subcontract or its termination by the contractor within the meaning of § 18. The defendants read this section too narrowly. The phraseology “any dispute or claim . . . arising out of this contract” includes the instant dispute, and we cannot see that the phrase “or any termination thereof by the Contractor” in any way limits the generality of the “any dispute” language.

Nor do we think that § 19 in any way alters the situation. 3 Arguably § 19 *585 limits the defendants’ liability to Pioneer to the amount paid by the Owner. It does not, however, expressly or impliedly require that such amount be determined in an arbitration proceeding. In the absence of an agreement to the contrary, a claim to which § 19 may apply and which involves interpretation of that section falls within the ambit of § 18 because it is, ipso facto, a dispute arising out of the subcontract.

The defendants further argue that since § 19 limits the extent of Pioneer’s recovery to the amount received by Gevyn from the County, a stay is appropriate to avoid inconsistent results between this ease and the termination arbitration proceeding. 4 If they are correct, Pioneer’s success in this action would rise or fall with Gevyn’s success in the termination arbitration, and should Gevyn recover nothing in the arbitration, it would be exonerated here. Such a result directly contravenes the legislative objective underlying ch. 149, § 29, a statute which the parties concede is applicable here. In American Air Filter Co., Inc. v. Innamorati Bros., Inc., Mass., 260 N.E.2d 718 (1970), the Supreme Judicial Court found that a contractor’s surety was liable to one who supplied heating equipment to a heating subcontractor despite the intervening bankruptcy of the subcontractor and his nonperformance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barboza v. Aetna Casualty & Surety Co.
465 N.E.2d 290 (Massachusetts Appeals Court, 1984)
Limbach Company v. Gevyn Construction Corporation
544 F.2d 1104 (First Circuit, 1976)
Bel Pre Medical Center, Inc. v. Frederick Contractors, Inc.
320 A.2d 558 (Court of Special Appeals of Maryland, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
458 F.2d 582, 1972 U.S. App. LEXIS 10147, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pioneer-industries-a-division-of-sos-consolidated-inc-v-gevyn-ca1-1972.