Limbach Company v. Gevyn Construction Corporation

544 F.2d 1104, 1976 U.S. App. LEXIS 6588
CourtCourt of Appeals for the First Circuit
DecidedOctober 20, 1976
Docket76-1247
StatusPublished
Cited by8 cases

This text of 544 F.2d 1104 (Limbach Company v. Gevyn Construction Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Limbach Company v. Gevyn Construction Corporation, 544 F.2d 1104, 1976 U.S. App. LEXIS 6588 (1st Cir. 1976).

Opinion

McENTEE, Circuit Judge.

In 1970 Middlesex County terminated the Gevyn Construction Corporation’s contract to build a courthouse in Cambridge, Massachusetts. This case marks yet another step in the protracted litigation stemming from that event. 1

After the County’s action, Gevyn, the general contractor, successfully demanded arbitration of all claims flowing from the contract termination. 2 In addition to Gevyn, parties to the consolidated arbitration proceeding were the County, which Gevyn accused of wrongful breach, and Gevyn’s subcontractors, including appellee Limbach Company. Limbach sought damages for breach of its subcontract which was terminated as a result of the cancellation of the principal contract. Gevyn claimed damages from the County; alternatively, in the event Gevyn were held liable to the County, Gevyn sought indemnification from its subcontractors.

In 1971, after arbitration had begun, Limbach sued Gevyn in Superior Court in Massachusetts to preserve its claim under Mass.Gen.Laws c. 149, § 29. Limbach filed a “petition in equity” seeking to recover from Gevyn or its surety on the bond which that statute requires for the benefit of subcontractors. Gevyn removed the case to the district court on grounds of diversity of citizenship, and the proceeding was stayed pending the outcome of the consolidated arbitration.

By early 1976 the arbitration hearings had not been completed. 3 The district court summoned the attorneys for all parties to suits that had been stayed pending the outcome of the consolidated arbitration to explore ways of removing the eases from the *1106 court’s docket. The judge expressed concern that the cases had continued on the docket for so long, stating that they were “giving this Court a very black eye, in terms of its statistical median time for the pendency of civil cases . . . .” While other litigants were able to agree on some method for disposing of their cases, Limbach and Gevyn were not. After a fruitless exploration of possibilities such as a stipulated dismissal without prejudice or an agreed remand to state court, the'’ judge on April 2, 1976 ordered that an award be entered as to Limbach’s claim in the consolidated arbitration proceeding within 60 days. 4 This appeal followed.

Appellant Gevyn challenges the propriety of the judge’s order, on various grounds. At this time, however, we need not reach the merits, for we conclude that we are without jurisdiction to entertain this appeal.

The jurisdictional bases for this appeal are to be found, if at all, in 28 U.S.C. §§ 1291, 1292. Under § 1291, this court may review only “final decisions” of the district court. And, § 1292(a)(1) confers jurisdiction for appeals from “[interlocutory orders of the district courts granting, continuing, modifying, refusing or dissolving injunctions, or refusing to dissolve or modify injunctions. . .

In this case the order of the district court requiring the prompt conclusion of arbitration of the Gevyn-Limbach portion of the courthouse claims does not terminate the litigation and therefore is not a “final decision” within the traditional meaning of that term. E. g., Baetjer v. Garzot Fernandez, 329 F.2d 798 (1st Cir. 1964). The source of this litigation, Limbach’s action under Mass.Gen.Laws c. 149, § 29, which was stayed pending arbitration, will not be concluded until the accelerated arbitration has resolved Limbach’s claim against Gevyn and the court has disposed of the stayed judicial proceeding.

Having determined that the order in this case is interlocutory in nature, we must consider whether it disposes of an independent or collateral claim of right which will evade review if not immediately appealable. New England Power Co. v. Asiatic Petroleum Corp., 456 F.2d 183, 185 (1st Cir. 1972). See Cohen v. Beneficial Industrial Loan Corp., 337 U.S. 541, 546-47, 69 S.Ct. 1221, 93 L.Ed. 1528 (1949); 9 J. Moore, Federal Practice 1 110.10, at 133 (2d ed. 1975). Appellant Gevyn asserts that this case fits within the Cohen exception since the district court’s order exposes Gevyn to the “risk of inconsistent arbitration awards.” Gevyn evidently fears that the arbitrators, if they are required to rule at an early stage on Limbach’s claim for the balance due for its services, will fail to include this early ruling in their calculations when making an award on Gevyn’s counterclaim for indemnification. Gevyn’s fears in this regard are heightened by the allegedly common practice of arbitrators to enter lump-sum awards without written explanation.

Assuming that Gevyn’s fears are well-founded, we do not believe that the assertedly prejudicial impact of the district judge’s order of April 2 will escape our review if enforcement by the court of an unfavorable arbitral award is ultimately appealed. Rather, it seems clear to us that Gevyn’s ability to assert the alleged error of the April 2 order will not be vitiated at all by requiring appellant to await appeal of a final decision. It may well be that the error asserted by Gevyn will be insufficiently prejudicial to defeat enforcement of an arbitral award, an assumption on which we intimate no opinion. See generally, 5 Am. Jur.2d “Arbitration and Award,” §§ 163, 167 (1962). The insufficiency of the defense in such a case, however, would result, not from the timing of Gevyn’s appeal, but from the standard of review to be applied uniformly to arbitral awards.

As a result of our failure to entertain this appeal on the merits, Gevyn will be put to the added expense and inconvenience of seeing to its end an arbitral proceeding which Gevyn asserts was fatally infected by error at an early stage. This unfortunate *1107 consequence does not bring the case within the Cohen exception to § 1291, however. Rather, this is the price which litigants must pay if the federal judicial system is to be protected from piecemeal appeals from erroneous interlocutory orders, even those which ultimately result in reversible error. See New England Power Co. v. Asiatic Petroleum Corp., supra. The wisdom of the policy requiring litigants to defer appeals until the end of the case is particularly clear in this case where the ultimate effect of the trial judge’s unusual order is largely speculative, suggesting that hindsight is the better tool for examining its allegedly prejudicial impact. 5

Gevyn asserts in the alternative that the 1971 stay of judicial proceedings was an “injunction” within the meaning of § 1292(a)(1) and that the district judge’s order of April 2 was a “modification” of that injunction and therefore appealable under § 1292(a)(1).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
544 F.2d 1104, 1976 U.S. App. LEXIS 6588, Counsel Stack Legal Research, https://law.counselstack.com/opinion/limbach-company-v-gevyn-construction-corporation-ca1-1976.