McCollum v. United States

32 Cont. Cas. Fed. 73,013, 6 Cl. Ct. 373, 1984 U.S. Claims LEXIS 1291
CourtUnited States Court of Claims
DecidedOctober 4, 1984
DocketNo. 346-82C
StatusPublished
Cited by6 cases

This text of 32 Cont. Cas. Fed. 73,013 (McCollum v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McCollum v. United States, 32 Cont. Cas. Fed. 73,013, 6 Cl. Ct. 373, 1984 U.S. Claims LEXIS 1291 (cc 1984).

Opinion

OPINION

MAYER, Judge.

Plaintiff Paul E. McCollum, Sr., seeks review under the Wunderlich Act, 41 U.S.C. §§ 321-322 (1976), of a decision of the Armed Services Board of Contract Appeals (Board), ASBCA No. 23269, 81-2 BCA ¶ 15,311. The case is before the court on cross-motions for summary judgment. The stated facts are findings of the Board or otherwise properly derived from the administrative record. See Ordnance Research, Inc. v. United States, 609 F.2d 462, 465, 221 Ct.Cl. 641 (1975).

Background

The facts are fully presented in two Board decisions. Paul E. McCollum, Sr., ASBCA No. 23269, 81-2 BCA ¶ 15,311; Paul E. McCollum, Sr., ASBCA No. 20120, 77-1 BCA ¶ 12,271. Those essential to this decision are set out here.

Under a small business set aside, plaintiff was awarded a Department of Health and Human Services contract on October 23, 1974, for the construction of water distribution systems on two Indian reservations near San Diego, California. The contract was terminated for default on February 12, 1975. Plaintiff timely appealed the default termination on February 18, 1975. On November 29, 1976, the Board determined that the default termination was improper and converted it to one for the convenience of the government.

The Board directed the parties to negotiate a termination for convenience settlement. Plaintiff submitted his first settlement proposal on March 2, 1977, and on June 14, 1977, he increased it. Defendant [375]*375did not respond, and plaintiff filed an appeal (quantum appeal) with the Board on September 13, 1978, some 15 months after he had presented his amended settlement claim. Finally, on October 6, 1978, defendant responded with a counter offer, to which plaintiff replied by increasing his settlement proposal. The parties were unable to reach agreement and the Board intervened. On August 12,1981, the Board ordered an award to plaintiff with interest to be computed at a fixed rate, the rate in effect at the time plaintiff filed his quantum appeal on September 13, 1978. Interest also began to accrue on this date.

In calculating the award, the Board determined that plaintiff was performing at a 20.7% loss and was therefore entitled to only 79.3% of his incurred costs. It refused to increase equipment costs reimbursement and denied any recovery for interest on investment. The Board further determined plaintiff was entitled to no additional compensation for his personal services. And because it could not tell which attorneys and accountants fees were incurred solely in preparation of his settlement claim, it allowed no recovery for any of them.

Plaintiff challenges the Board’s decision with these arguments:

1. The Board improperly calculated the settlement award by using a fixed instead of a variable interest rate.
2. Interest on the settlement award should have accrued from the appeal of his default termination, not from the appeal of the termination for convenience settlement.
3. The Board wrongly determined that plaintiff was in a loss position.
4. Equipment costs reimbursement should have been calculated at a higher rate.
5. Plaintiff should have been allowed interest on his investment.
6. Plaintiff was not fully compensated for his personal work.
7. Compensation for attorneys and accountants fees should have been allowed.

Defendant urges affirmance of the decision in its entirety.

Discussion

“Under the Wunderlich Act, a board’s determinations on questions of law are not binding on the court, but will be credited if reasonable and based on a board’s expertise. See, Flexible Metal Hose Manufacturing Co. v. United States, 4 Cl.Ct. 522, 527 (1984) [appeal docketed, No. 84-1108 (Fed.Cir. April 13, 1984)]; Dale Ingram, Inc. v. United States, 475 F.2d 1177, 1185, 201 Ct.Cl. 56 (1973). A board’s findings of fact, however, are binding on the court unless shown to be arbitrary, capricious or not supported by substantial evidence. See Flexible Metal Hose Co. v. United States, 4 Cl.Ct. at 527; Koppers Co. v. United States, 405 F.2d 554, 557, 186 Ct.Cl. 142 (1968).” Peterson-Sharpe Engineering Corp. v. United States, 6 Cl.Ct. 288, at 293 (1984).

Fixed Rate of Interest

“An allowance of interest on a claim against the United States, absent constitutional requirements, requires an explicit waiver of sovereign immunity by Congress. Such express consent to the payment of interest must be found in either a specific statutory or an express contractual provision.” Fidelity Construction Co. v. United States, 700 F.2d 1379, 1383 (Fed.Cir.1983). See also Brookfield Construction Co. v. United States, 661 F.2d 159, 165, 228 Ct.Cl. 551 (1981). The contract here expressly permits the recovery of interest on a claim, but the parties disagree about whether it accrues at variable rates.

General Provision 25 (GP 25) of the contract says, “Such interest shall be at the rate determined by the Secretary of the Treasury pursuant to Public Law 92-41, 85 Stat. 97 ____” Under Public Law 92-41, the Renegotiation Act, the interest rate paid by the government is adjusted by the Secretary of the Treasury every six months so that the rates parallel private commercial rates. Because this statute was referred to in the contract, plaintiff believes [376]*376the interest on his award should vary in accordance with the periodic Treasury adjustments.

In support of this proposition, plaintiff cites Brookfield Construction Co. v. United States, 661 F.2d 159, in which the court interpreted section 12 of the Contracts Disputes Act of 1978, 41 U.S.C. § 611, a statutory payment of interest provision similar in language to GP 25. The court there held that interest on payments under government contracts should be paid at a variable rate, id. 661 F.2d at 170, and plaintiff argues that Brookfield’s construction should apply as well to his contract.

He also urges the court to follow the General Services Board of Contract Appeals decision in Joseph Penner, GSBCA No. 6820, 83-1 BCA ¶ 16,282, where the Board applied Brookfield to a contract clause identical to GP 25. It reasoned that because section 12 and the contract clause have essentially the same language, Brook-field requires that they both be interpreted the same. “The Act and the clause are in pari materia: they use the same language, serve substantially the same purpose, and ought to be similarly interpreted.” 83-1 BCA ¶ 16,282 at 80,894.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lion Raisins, Inc. v. United States
52 Fed. Cl. 629 (Federal Claims, 2002)
White Buffalo Construction, Inc. v. United States
52 Fed. Cl. 1 (Federal Claims, 2002)
North Slope Technical Ltd. v. United States
34 Cont. Cas. Fed. 75,430 (Court of Claims, 1988)
McCollum v. United States
32 Cont. Cas. Fed. 73,472 (Court of Claims, 1985)
J.F. Shea Company, Inc. v. The United States
754 F.2d 338 (Federal Circuit, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
32 Cont. Cas. Fed. 73,013, 6 Cl. Ct. 373, 1984 U.S. Claims LEXIS 1291, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mccollum-v-united-states-cc-1984.