Cornell Wrecking Co. v. United States

184 Ct. Cl. 289, 1968 U.S. Ct. Cl. LEXIS 118, 1968 WL 9150
CourtUnited States Court of Claims
DecidedMay 10, 1968
DocketNo. 227-65
StatusPublished
Cited by9 cases

This text of 184 Ct. Cl. 289 (Cornell Wrecking Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cornell Wrecking Co. v. United States, 184 Ct. Cl. 289, 1968 U.S. Ct. Cl. LEXIS 118, 1968 WL 9150 (cc 1968).

Opinion

Per Curiam :

This case was referred to Chief Trial Commissioner Marion T. Bennett, with directions to make findings of fact and recommendation for conclusions of law under the order of reference and Buie 57(a). The commissioner has done so in an opinion and report filed on February 29, 1968. On March 28, 1968, the parties filed a stipulation setting forth that neither party desires to take exception to the report of the Chief Commissioner and electing to submit the case on the report without exceptions. Since the court agrees with the commissioner’s opinion, findings and recommended conclusion of law, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case without oral argument. Therefore, plaintiff is entitled to recover and judgment is entered for plaintiff in the sum of $19,405.20.

[291]*291OPINION OP COMMISSIONER

Bennett, Chief Commissioner: Plaintiff’s petition asks damages of $43,650 for breach of contract on the basis that defendant released to plaintiff beyond the contract deadline certain buildings which plaintiff had contracted to demolish. Defendant clearly breached the contract since defendant alone caused the delay which hindered performance, the delay was unreasonable, and the contract did not contemplate nor excuse such delays. Commerce Int'l Co. v. United States, 167 Ct. Cl. 529, 338 F. 2d 81 (1964). There was no suspension-of-work clause in the contract which would permit an administrative adjustment of the contract price for these delays.

Plaintiff had no books or records to establish its actual costs.

Plaintiff attempted, but was unable, to prove that the equipment which was idled by defendant’s delay was rented, and that rental rates should be used to compute damages. Absent this showing, damages for this idle time are computed using Associated General Contractor (AGC) rates for contractor-owned equipment usage, minus one-half since there is no wear and tear during idle time. L. L. Hall Constr. Co. v. United States, 177 Ct. Cl. 870, 379 F. 2d 559 (1966). In L. L. Hall the equipment was contractor-owned. Here it is not absolutely clear that it was so owned, but there is total failure of proof it was rented, even assuming it was owned by another corporate entity well blended into plaintiff. Under the facts of the case it is found that application of AGC rates gives the most realistic approximation of plaintiff’s actual costs for idle equipment.

Plaintiff also sought damages for a brief period early in the demolition process when the defendant released a building for demolition and then rescinded the release and fixed a new release date. The building was finally released to plaintiff well before the contract deadline and the contract clearly contemplates some uncertainty in release dates within the limitations there provided. The defendant did not act unreasonably and no breach occurred here.

Plaintiff is entitled to damages for supervision during idle time. Plaintiff is also entitled to recover its actual cost of [292]*292renting equipment for another job when it could not use its idled equipment which otherwise would have been available.

The facts are more fully set forth in the findings which follow.

Findings of Fact

1. Plaintiff is a corporation organized and operating under the laws of the District of Columbia with its principal place of business in Washington, D.C., and is engaged in the business of demolition contracting, specializing in the razing of buildings.

2. Plaintiff was the successful bidder on contract No. GS-03B-14153 awarded June 2, 1964, by the United States, acting through the General Services Administration, for the demolition and removal of buildings designated Temporary Buildings T-30, T-31, T-32, Barton Hall and Curie Hall, located in West Potomac Park, Washington, D.C. The contract price was $64,500.

3. Section 2.06 of the Special Conditions of the contract contained the following provisions regarding a time for release of the buildings and for completion of the demolition:

SCHEDULE FOR DEMOLITION
a. Demolition and removal work for all of the building shall be based, so far as is practicable, on the vacancy of the premises by the occupying agency in accordance with the following anticipated Vacancy Schedule:
1. Vacancy Schedule
a. Tempo T-30 — vacated June, 1964.
b. Tempo T-32 — vacated June, 1964.
c. Barton Hall — vacated July, 1964.
d. Tempo T-31 — vacated August, 1964.
e. Curie Hall — vacated August, 1964.
b. Completion Times
1. Demolition and removal work for each building listed in the Vacancy Schedule shall be completed within sixty (60) calendar days from dates to be furnished in “Final Schedule of Work”.
2. All dates for the start of demolition and removal work by the Contractor as listed in the Vacancy Schedule above, are approximate only and are subject to adjustments that might be made necessary by the removal and relocation of existing services, equipment and [293]*293personnel, supply and shut-down and termination of existing services to buildings, etc.
3.Any adjustment by the Government in the dates for the start of demolition and removal work by the Contractor shall be made within and limited to a three (3) month period starting from the dates indicated in the Vacancy Schedule.
c. Approval
No demolition and removal work shall be performed for any building listed in the Vacancy Schedule or under this Contract without prior written approval by the Contracting Officer.
d. Final Schedules of Work
The Contracting Officer will furnish and issue to the Contractor “Final Schedules of Work” designating the dates that any building or group of buildings will be available for the start of demolition and removal work required under the Contract. The final schedules will be issued to the Contractor not less than two (2) weeks before the start of any scheduled demolition and removal work and within the limitation period of three (3) months hereinbefore specified.

4. Plaintiff was informed by defendant on June 26, 1964,. that T-30 would be vacated by July 1,1964, after which time it would be available for demolition under the contract. Defendant vacated this building by July 1 and plaintiff demolished it between July 13 and July 24.

5. Plaintiff was informed by defendant on July 9, 1964, that T-31 would be vacated by July 15, 1964, and available for demolition. On July 17 plaintiff was informed by letter that the July 15 release date was rescinded because of delay in relocating tenants of the building. Approximately 16 working days later, defendant released the building and plaintiff completed the demolition by August 31,1964.

6. Plaintiff was informed by letter on November 20,1964,. that Barton Hall was released as of November 11,1964, thus confirming prior oral notice.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hernandez, Kroone and Associates, Inc. v. United States
110 Fed. Cl. 496 (Federal Claims, 2013)
K-Con Building Systems, Inc. v. United States
107 Fed. Cl. 571 (Federal Claims, 2012)
White Oak Corp. v. Department of Transportation
585 A.2d 1199 (Supreme Court of Connecticut, 1991)
McCollum v. United States
32 Cont. Cas. Fed. 73,013 (Court of Claims, 1984)
Degenaars Co. v. United States
31 Cont. Cas. Fed. 71,186 (Court of Claims, 1983)
W. G. Cornell Co. v. Ceramic Coating Co.
626 F.2d 990 (D.C. Circuit, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
184 Ct. Cl. 289, 1968 U.S. Ct. Cl. LEXIS 118, 1968 WL 9150, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cornell-wrecking-co-v-united-states-cc-1968.