J. D. Hedin Construction Co. v. United States

456 F.2d 1315, 197 Ct. Cl. 782, 1972 U.S. Ct. Cl. LEXIS 34
CourtUnited States Court of Claims
DecidedMarch 17, 1972
DocketNo. 121-60
StatusPublished
Cited by40 cases

This text of 456 F.2d 1315 (J. D. Hedin Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. D. Hedin Construction Co. v. United States, 456 F.2d 1315, 197 Ct. Cl. 782, 1972 U.S. Ct. Cl. LEXIS 34 (cc 1972).

Opinion

Per Curiam:

This case was referred to Trial Commissioner Saul Richard Gamer with directions to make findings of fact and recommendation for conclusions of law. The commissioner has done so in an opinion and report filed on December 23, 1971, under the order of reference and Rule 134(h). By joint motion the parties requested an extension of time to January 31, 1972, to file a notice of intention to except. However, on January 25, 1972, defendant filed a notice that it did not intend to except to the report of the commissioner and on January 26, 1972, plaintiff filed a motion requesting that the court adopt the commissioner’s report as the basis for its decision. Since the court agrees with the commissioner’s opinion, findings of fact and recommended conclusion of law, as hereinafter set forth, it hereby grants plaintiff’s motion and adopts the report as the basis for its judgment in this case without oral argument. It is therefore concluded that plaintiff is entitled to recover and judgment is entered for plaintiff in the sum of $614,088.23.

OPINION OP COMMISSIONER

Gamer, Commissioner: Plaintiff’s right to proceed under a contract with the Veterans Administration for the performance of certain construction work at the Administration’s hospital in Marion, Indiana, was terminated hy the contracting officer in the midst of construction operations. Its appeal of such action under the pertinent contract clauses was heard by the agency’s Construction Contract Appeals Board. Upon the Board’s recommendation, the appeal was denied by the agency’s Assistant Administrator for Construction, the official designated to make such decisions.

Plaintiff also took four other appeals to the Board with respect to additional contract disputes, some aspects of which related to the termination action. These disputes were, for the most part, resolved against plaintiff by the Board and the Assistant Administrator.

Contending that the termination was wrongful and con-[787]*787sfcituted a breadla of its contract, plaintiff filed its petition herein contesting such action, as well as the agency’s disposition of the other four appeals.1

On the parties’ motions for summary judgment, grounded on an enormous administrative record,2 the court, on March 14, 1969, concluded that the termination was improper. 187 Ct. Cl. 45, 408 F. 2d 424. The court held that the termination could not validly be based upon a contract “Termination for Default” clause authorizing a termination for the contractor’s failure to prosecute the work with such diligence as would insure its completion within the time specified in the contract. This was so because, had plaintiff been granted an extension of time, to which the court held it was entitled (contrary to the agency determination), plaintiff would not, as of the termination date, have been behind time, or at least would not then have been behind to such a degree as would have warranted a default termination. This exfcension-of-time dispute involved a critical nationwide cement shortage which occurred shortly after construction operations commenced and which seriously affected plaintiff’s progress.

The court further held that the agency had also erred in relying upon the “Inspection” clause of the contract as an additional basis for the termination. This clause gave the contracting officer the right to reject, and to require the contractor to correct, defective material and workmanship, and, if the contractor failed to so correct “at once,” to terminate the eontractoi'’s right to proceed. The Board and the Assistant Administrator determined that, of the host of instances in controversy, each of 33 specified items of alleged 'defective workmanship or materials independently warranted the termination action, but the court concluded that the record [788]*788failed to support any of them as justifying termination under the clause in question.

After the termination, plaintiff’s surety agreed with the VA to complete the project and employed another contractor, the James Stewart Corporation, for this purpose. By the time such completion was effected, there was an overrun of 518 days from the original contract completion date as extended, and plaintiff, being held responsible for such late completion because of its alleged default, was consequently assessed with liquidated damages in the amount of $155,400 ($300 per day) for the entire overrun. Such amount was withheld from moneys otherwise due plaintiff under the contract. The court held, however, that such assessment was unwarranted since the termination itself was improper.

Furthermore, after the termination the agency spent $8,769.33 to protect the work in its partially completed state, and considering this expense too as attributable to plaintiff’s alleged default, the agency reimbursed itself therefor by similarly deducting such amount from the sums otherwise due plaintiff under the contract. The court again held, however, that its conclusion that the termination was improper necessitated invalidating this charge against plaintiff.3

Accordingly, the court held that (a) plaintiff was entitled to recover the two withholdings, totaling $164,169.33; and (b) the improper default-termination constituted a breach of contract for which plaintiff was entitled to recover such common law damages, including anticipated profits, as it would be able to prove in further proceedings before this court. In connection with such proof, the court stated that plaintiff would have to show the amount of excusable delay resulting from the cement shortage, whether plaintiff would have timely completed the project even with the additional time extension to which it was entitled, and the monetary damage, if any, which it suffered by reason of the termination, i.e., whether it was deprived of any profit it would have [789]*789made had there been no termination, or, even if there would have been no such profit, whether its loss would have been less than it actually suffered by reason of the wrongful termination.

The issues relating to the damages led to further heated controversy. Extensive pretrial proceedings, a trial of over three weeks, and voluminous requested findings and briefs (totaling almost 400 pages) resulted. During the course of the proceedings, however, the parties were able to arrive at certain agreements. They stipulated that the cement shortage terminated oh November 1, 1955; that the shortage delayed plaintiff’s construction operations six months, or 180 days; and that, had plaintiff received the extension of time therefor to which it was entitled, such extension, together with those totaling 74 days which the agency had granted plaintiff for other reasons, would have extended the project completion date to March 8,1957.

Plaintiff’s petition alleges damages of $2,793,534.89, including the withheld liquidated damages and protection costs. As a result of the elimination of certain items which it has now abandoned,4 and adjustments in other items, plaintiff’s total claim (including the two withholdings which the court has already held plaintiff is entitled to recover) is now in the amount of $1,121,549.01.

There will be discussed herein only the remaining substantive differences between the parties. The details of the computations of the various damage items flowing from the resolution of these differences are set forth in the findings of fact.

[790]*790

Free access — add to your briefcase to read the full text and ask questions with AI

Related

System Fuels, Inc. v. United States
666 F.3d 1306 (Federal Circuit, 2012)
Energy Northwest v. United States
641 F.3d 1300 (Federal Circuit, 2011)
Boston Edison Co. v. United States
93 Fed. Cl. 105 (Federal Claims, 2010)
IMS Engineers-Architects, P.C. v. United States
92 Fed. Cl. 52 (Federal Claims, 2010)
System Fuels, Inc. v. United States
92 Fed. Cl. 101 (Federal Claims, 2010)
Energy Northwest v. United States
91 Fed. Cl. 531 (Federal Claims, 2010)
Wisconsin Electric Power Co. v. United States
90 Fed. Cl. 714 (Federal Claims, 2009)
Southern Nuclear Operating Co. v. United States
77 Fed. Cl. 396 (Federal Claims, 2007)
Die Casters International, Inc. v. United States
73 Fed. Cl. 174 (Federal Claims, 2006)
Westfed Holdings, Inc. v. United States
407 F.3d 1352 (Federal Circuit, 2005)
Home Savings of America, F.S.B. v. United States
57 Fed. Cl. 694 (Federal Claims, 2003)
Centex Corp. v. United States
55 Fed. Cl. 381 (Federal Claims, 2003)
General Services Commission v. Little-Tex Insulation Co.
39 S.W.3d 591 (Texas Supreme Court, 2001)
General Services v. Little-Tex Insulation
39 S.W.3d 591 (Texas Supreme Court, 2001)
Bluebonnet Sayings Bank v. United States
47 Fed. Cl. 156 (Federal Claims, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
456 F.2d 1315, 197 Ct. Cl. 782, 1972 U.S. Ct. Cl. LEXIS 34, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-d-hedin-construction-co-v-united-states-cc-1972.