Glasgow Associates v. United States

495 F.2d 765, 203 Ct. Cl. 532, 1974 U.S. Ct. Cl. LEXIS 91
CourtUnited States Court of Claims
DecidedFebruary 20, 1974
DocketNo. 178-65
StatusPublished
Cited by6 cases

This text of 495 F.2d 765 (Glasgow Associates v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Glasgow Associates v. United States, 495 F.2d 765, 203 Ct. Cl. 532, 1974 U.S. Ct. Cl. LEXIS 91 (cc 1974).

Opinion

KuNzig, Judge,

delivered the opinion of the court:

At issue in this suit for recovery of $200,000 is whether the Government, through various uncontroverted 'actions, breached a Capehart Housing contract between the Air Force [535]*535and plaintiff. We hold for defendant, rejecting plaintiff’s assertion that the Government’s course of conduct constituted actionable breach.

The present action represents the sole surviving claim of a 14-count petition filed by plaintiff in this court for uncompensated costs arising under plaintiff’s Capehart Act contract for the construction of 460 housing units at Glasgow Air Force Base, Montana (Glasgow).1 By decision of June 13, 1967, the Armed Services Board of Contract Appeals declined consideration of this count on the ground that it lacked jurisdiction over it.2 To expedite the court’s de novo consideration of this final 'claim, the parties have stipulated “all the pertinent facts,”3 whieh are summarized as follows:

Plaintiff is a joint venture organized for the purpose of contracting with defendant for the construction of Capehart Housing under section 803 of the National Housing Act.4 On November 24,1958, the Department of the Air Force issued Invitation for Bid (IFB) No. 13-606-59-32 for the construction of the Glasgow housing project. At that time, the statutory maximum interest guaranty rate for Capehart Housing mortgages was 4y2 per cent while the maximum rate permitted by the Commissioner of the Federal Housing Administration (FHA) by administrative rule pursuant to the National Housing Act was 4% per cent. In accordance with this administrative rule, IFB 13-606-59-32 contemplated that the contractor would obtain financing at an interest rate not exceeding 4^4 per cent.

The availability of private construction mortgage funds, which are required for Capehart Housing, was dependent on the FHA guaranty. Since the maximum interest rate which FHA would guarantee was lower than the prevailing rate, Capehart borrowers were required (even with the FHA guaranty) to pay an additional fee by way of a discount or [536]*536“points” to obtain financing. The amount of these additional fees were fixed by lenders who received such “points” in addition to interest charged.

On January 24, 1959, plaintiff submitted its bid. Plaintiff computed the cost to it of obtaining financing as three “points,” or approximately $220,000, and included this sum in its bid. At this time, plaintiff had not yet actually secured private financing.

On February 17, 1959, Thomas Hefferan, the Director of Real Property Management, Office of the Assistant Secretary of Defense for Properties and Installations, advised the Under Secretary of the Air Force, Assistant Secretary of the Army, and Assistant Secretary of the Navy as follows:

After careful consideration of recent trends in the market for Capehart housing mortgages, this office has recommended to the Federal Housing Commissioner that the interest rate on Capehart mortgages be increased from 414 percent to 4y2 percent, the current statutory maximum rate.
In view of the fact that the announcement of the increased rate will doubtless have an adverse effect on the 41/4 percent mortgages, it appears that every possible step must be taken to reduce to a minimum the number of projects affected by the change.

Beginning in mid-February, rumors circulated throughout the financial community that a change in the maximum permissible interest rate was probable.

The Hefferan memorandum was received by the office of the Assistant Secretary of the Air Force for Installations on or shortly before February 25. On February 25, it was forwarded through a routine chain of operation to the Housing-Division of the Assistant Secretary’s office. One of the functions of this division was to review the three lowest bids for a construction contract and to recommend award to the lowest qualified bidder.

Under date of Friday, February 27, 1959, the Housing Division issued plaintiff a Letter of Acceptability advising that plaintiff’s bid was the lowest acceptable for IFB 13-606-59-32 and directing completion of various requirements in preparation for initial closing of the contract. On this date, the individuals involved on behalf of defendant in [537]*537the contracting process with, plaintiff did not have actual knowledge of when, if at all, the Commissioner of FHA would officially increase to 4y2 per cent the maximum permissible interest guaranty rate.

Announcement of such an increase was made by the Commissioner on the following Monday, March 2, effective following the close of business that day. The news release stated:

This action was taken as a result of a recommendation from the Department of Defense and of analysis of the current mortgage market by the Federal Housing Administration indicating the necessity for such an increase in order to improve the flow of funds to [the Capehart] program.

At no time prior to the FHA announcement did defendant advise plaintiff of the contemplated interest guaranty rate increase.

Plaintiff received the Letter of Acceptability on March 6. By memorandum dated that same day, the Assistant Secretary of Defense for Properties and Installations advised the Under Secretary of the Air Force, the Assistant Secretary of the Army, and the Assistant Secretary of the Navy as follows:

Effective March 3, 1959 the new interest rate will be applied to Capehart projects in accordance with the following criteria:
1. Projects which were advertised and bid at 4% percent will be closed at 4% percent, as follows:
a. Letter of Acceptability issued — no exception.
b. Letter of Acceptability not issued — if hardship is clearly demonstrated and is directly attributable to the lower interest rate, all bids should be rejected and the project re-advertised.
2. Projects currently under advertising (bids not opened) at 414 percent will be subject to the new rate and advertising will be amended accordingly.
3. Projects advertised subsequent to the effective date will be subject to the rate prescribed by the FHA rules and regulations at the time of advertising.

On April 30, 1959, the parties entered into a contract for the construction of the Glasgow Capehart project. Plaintiff [538]*538at that time also delivered to defendant various documents required under the Letter of Acceptability, including evidence of the fact that plaintiff had arranged financing the project with mortgages bearing a 4% per cent interest rate. The actual cost to plaintiff of obtaining a financing commitment, which was accomplished subsequent to the March 2 guaranty rate announcement, was 5% “points,” or $419,678, approximately $200,000 more than plaintiff originally estimated and included in its bid. It is this last amount of additional cost which plaintiff here seeks to recover.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Scott Timber Co. v. United States
692 F.3d 1365 (Federal Circuit, 2012)
Montego Bay Imports, Ltd. v. United States
25 Cl. Ct. 639 (Court of Claims, 1992)
Sun Oil Co. v. United States
572 F.2d 786 (Court of Claims, 1978)
Huerta v. United States
548 F.2d 343 (Court of Claims, 1977)
Tony Downs Foods Co. v. United States
530 F.2d 367 (Court of Claims, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
495 F.2d 765, 203 Ct. Cl. 532, 1974 U.S. Ct. Cl. LEXIS 91, Counsel Stack Legal Research, https://law.counselstack.com/opinion/glasgow-associates-v-united-states-cc-1974.