Centex Construction Co. v. United States

49 Fed. Cl. 790, 2001 U.S. Claims LEXIS 128, 2001 WL 793061
CourtUnited States Court of Federal Claims
DecidedJuly 13, 2001
DocketNo. 99-159C
StatusPublished

This text of 49 Fed. Cl. 790 (Centex Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Centex Construction Co. v. United States, 49 Fed. Cl. 790, 2001 U.S. Claims LEXIS 128, 2001 WL 793061 (uscfc 2001).

Opinion

OPINION

ALLEGRA, Judge.

The basic issue in this case is whether the contract in question, to construct an addition to a Veteran’s Administration medical facility, required the installation of channel bracing in stud walls with door openings. If it did not, then plaintiff is entitled to additional compensation for ultimately having to install those braces; if the contract did so provide, [791]*791then plaintiff is entitled to no compensation. After careful consideration of the briefs filed and the oral argument, and for the reasons discussed below, the court concludes that the contract required the channel bracing and, therefore, GRANTS defendant’s motion for summary judgment.

I. Statement of Facts

On or about September 30, 1993, the Department of Veterans Affairs (“VA”) entered into Contract No. V101DC0086 with Centex Construction Company, Inc. (“Centex” or “plaintiff’) to construct a clinical addition and Spinal Chord Injury Center (“SCI Center”) at the VA Medical Center in Dallas, Texas. Section 1.45 of this contract, entitled “SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FAR 52.236-21) (APR 1984),” contained a standard Federal Acquisition Regulation (FAR) clause, which provided, in pertinent part:

(a) The Contractor shall keep on the work site a copy of the drawings and specifications and shall at all times give the Contracting Officer access thereto. Anything mentioned in the specifications and not shown on the drawings, or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned in both.

The VA contract contained two sets of drawings — one set pertaining to the SCI Center and the other to the clinical addition. Architectural Drawing No. 74-71R, pertaining to the SCI Center, and Architectural Drawing No. 2-240R, pertaining to the Clinical Addition, both were entitled “Door Schedules and Details.” Architectural Drawing No. 74-71R includes detail 74-71/04 entitled “Elevation of Framing at Door Opening,” which applies to metal door frames and requires the installation of % inch channel bracing. Architectural Drawing No. 2-240R identifies this same detail as 2-240/04 and also requires the installation of % inch channel bracing.

Centex subsequently subcontracted various work to Cleveland Construction, Inc. (“Cleveland”), including the installation of interior door frame systems in the SCI Center. The subcontract required, in pertinent part: 34. STATEMENT OF WORK AND SUBCONTRACT PRICE

B. INCLUSIONS. In addition to the foregoing, it is further understood and agreed that this Subcontract also includes the furnishing and installation of the below listed items regardless of whether or not they are in the above specification sections), or any other specification section, or shown on the plans:

4. The receiving, unloading, and storing of all hollow metal frames as directed by the Contractor’s project office. Subcontractor will distribute, install and grout (if required) all frames, including elevator frames, and provide all wall framing and bracing as required to keep the frames plumb and square.

On November 14, 1995, Centex and Cleveland employees met with the VA’s senior resident engineer, Paul Newman, to discuss several outstanding issues regarding the VA contract. At this meeting, Cleveland asserted that, because detail 74-71/04 was not described as a “typical” detail on the contract drawing, it was therefore not part of the VA contract. In his response dated December 14, 1995, Mr. Newman stated “[t]he 3/4” channel as wall bracing shown by 74-71/04 is in the drawings. Because the detail 74-71R/04 is in the contract you are required to install the wall bracing.

On December 21, 1995, Centex again disputed, in writing, Mr. Newman’s assertion that the VA contract required the installation of the door support material at the hollow metal door frames. On January 22, 1996, Mr. Newman responded to Centex’s letter, writing “[olur position is that details is on the drawings, so it is part of the contract and therefore must be incorporated into construction.” On February 7, 1996, Centex and Cleveland employees again met with Mr. Newman to discuss detail 2-240/04.1 At that [792]*792time, the VA directed Cleveland to install the door opening bracing in the clinical addition in accordance with the contract detail. On February 21, 1996, Cleveland informed Cen-tex that it would install channel bracing at all door openings at the clinical addition pursuant to detail 2/240-04, but added that it would submit a proposal for the added cost associated with the installation.

On December 10,1997, Centex submitted a claim to the VA’s contracting officer in the amount of $82,777, asserting that it was entitled to this amount as a result of the “extra contractual requirements” imposed by the VA in connection with the installation of channel supports at hollow metal door frames. On March 24, 1998, the contracting officer denied Centex’s claim. On March 23, 1999, Centex filed suit in this court. On October 25, 2000, defendant filed its Motion for Summary Judgment. Subsequently, this case was reassigned to the undersigned judge. On May 15, 2001, this court heard oral argument in this case.

II. Discussion

“Summary judgment is ... an integral part of the Federal Rules,” the Supreme Court has stated, and is “designed ‘to secure the just, speedy and inexpensive determination of every action.’ ” Celotex Corp. v. Ca-trett, 477 U.S. 317, 327, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986) (quoting Fed.R.Civ.P. 1). Summary judgment is appropriate when there is no genuine dispute as to any material fact and the moving party is entitled to judgment as a matter of law. RCFC 56; Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). Such is the case here.

Contract interpretation is a matter of law and, as such, is amenable to disposition on summary judgment. See Textron Defense Sys. v. Widnall, 143 F.3d 1465, 1468 (Fed. Cir.1998); Dalton v. Cessna Aircraft Co., 98 F.3d 1298, 1305 (Fed.Cir.1996); ECC Intern. Corp. v. United States, 43 Fed. Cl. 359, 365 (1999). In interpreting a contract, the court’s examination begins — and in this particular case, ends — with the plain language used in the contract. Textron Defense Sys., 143 F.3d at 1469; Gould, Inc. v. United States, 935 F.2d 1271, 1274 (Fed.Cir.1991); Craft Mach. Works Inc. v. United States, 926 F.2d 1110, 1113 (Fed.Cir.1991). The court must interpret the contract as a whole to give reasonable meaning to all its parts and to avoid “conflict or surplusage of its provisions.” Granite Const. Co. v. United States,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Unicon Management Corporation v. The United States
375 F.2d 804 (Court of Claims, 1967)
Craft MacHine Works, Inc. v. The United States
926 F.2d 1110 (Federal Circuit, 1991)
Gould, Inc. v. The United States
935 F.2d 1271 (Federal Circuit, 1991)
Granite Construction Company v. The United States
962 F.2d 998 (Federal Circuit, 1992)
Foley Company v. United States
11 F.3d 1032 (Federal Circuit, 1993)
Blinderman Construction Co. v. United States
42 Cont. Cas. Fed. 77,210 (Federal Claims, 1997)
ECC International Corp. v. United States
43 Cont. Cas. Fed. 77,452 (Federal Claims, 1999)
Input/Output Technology, Inc. v. United States
44 Fed. Cl. 65 (Federal Claims, 1999)
Carothers Construction Co. v. United States
36 Cont. Cas. Fed. 75,873 (Court of Claims, 1990)
Foley Co. v. United States
26 Cl. Ct. 936 (Court of Claims, 1992)
George Hyman Construction Co. v. United States
564 F.2d 939 (Court of Claims, 1977)
B. D. Click Co. v. United States
614 F.2d 748 (Court of Claims, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
49 Fed. Cl. 790, 2001 U.S. Claims LEXIS 128, 2001 WL 793061, Counsel Stack Legal Research, https://law.counselstack.com/opinion/centex-construction-co-v-united-states-uscfc-2001.