George Hyman Construction Co. v. United States

564 F.2d 939, 24 Cont. Cas. Fed. 81,802, 215 Ct. Cl. 70, 1977 U.S. Ct. Cl. LEXIS 91
CourtUnited States Court of Claims
DecidedOctober 19, 1977
DocketNo. 61-76
StatusPublished
Cited by37 cases

This text of 564 F.2d 939 (George Hyman Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George Hyman Construction Co. v. United States, 564 F.2d 939, 24 Cont. Cas. Fed. 81,802, 215 Ct. Cl. 70, 1977 U.S. Ct. Cl. LEXIS 91 (cc 1977).

Opinions

Skelton, Senior Judge,

delivered the opinion of the

court:

The plaintiff, George Hyman Construction Company (contractor or plaintiff), entered into contract No. GS-00B-01214 on June 30, 1972, as contractor with the General Services Administration of the United States Government (the Government or defendant), for the construction of Phase I of the United States Tax Court Building in Washington, D.C., for the sum of $13,228,000. During construction a dispute arose between the contractor and the Government with reference to the construction of eight utility lines, namely the storm and sanitary sewer, water service, steam and condensate return lines, which are shown on drawing No. 9-0S-1, designated "Site Utility Plan.” These lines ran underground to existing lines of the same kind, two of which ran to the wall of the Labor Department Building, all of which are shown on the above drawing. The contractor took the position that it was only required to "stub-out” the utility lines a distance of five feet from the building as shown on drawing 9-P-l, designated "Basement Floor Plan-Plumbing,” and was not required to construct and install the utility lines to the existing lines of the same kind outside the building, two of which entered the nearby Labor Department Building. The Government contended that the contractor was required by the contract to construct the utility lines to the existing lines and to the Labor Department Building, as aforesaid. The contracting officer ordered the contractor to so construct the lines, which it did, but it claimed this was a constructive change order not covered by the contract and that it was entitled to an equitable adjustment. It filed a claim to that effect with the contracting officer, who denied the claim. The contractor appealed to the GSA Board of Contract Appeals (Board), which heard the appeal and [73]*73denied the contractor’s claim in GSBCA-3722 on January 23, 1974, 74-1 BCA ¶ 10,451, with one member of the Board dissenting. The contractor has appealed from the Board’s decision to this court under the Wunderlich Act, 41 U.S.C. §§ 321, 322, claiming that the decision of the Board is arbitrary, capricious, unsupported by substantial evidence, and is erroneous as a matter of law. The Government says that the decision of the Board is correct and should be affirmed. The case is before the court on cross-motions for summary judgment. We have concluded that the law and the facts do not support the contractor’s claim, and we hold for the Government.

The facts show that in the beginning the Government intended to construct the Tax Court Building under one contract, but before issuing the invitation for bids, the plan was changed so as to have the building constructed by two contracts designated "Phase I” and "Phase II.” When the plaintiff noticed these designations on the drawings, it made inquiry on June 9, 1972, of the GSA as to their meaning. The GSA responded by amending the special conditions of the contract on June 13, 1972, by adding to section 0110 a new paragraph 1.2 immediately after paragraph 1.1 as follows:

1.2 A separate contract designated as Phase II will be awarded to complete the United States Tax Court Building project. The Contractor for Phase I construction shall provide access to the site for the Phase II Contractor without additional cost to the Government or charge to the Phase II Contractor. He shall cooperate with the Phase II Contractor and with the contractor for subway construction to coordinate and execute the work properly.

On June 20, 1972, amendment No. 4 to the invitation for bids was added to new paragraph 1.2 as follows:

Any reference to Phase I means contract requirements of GS-00B-01214.

Being satisfied with the reply of the GSA, the contractor submitted its bid and was awarded the contract (No. GS-00B-01214) on June 30, 1972, after which it began construction.

[74]*74As stated above, during construction the contracting officer ordered the contractor to install the eight utility lines above-described and connect them with existing lines of the same kind which were located outside the foundation walls of the Tax Court Building. The contractor took the position that it was only required to "stub-out” the utility lines five feet from the building as shown by drawing No. 9-P-l. It contended further that architectural drawing 2-1 and other architectural drawings contained notations such as "Limit Phase I Construction @ Face of Building” and other notations of like import, and the contractor argued that these drawings indicated that it was only required to do the work of Phase I within the confines of the four walls of the building and any work outside of the building was to be performed by the contractor who was to work on Phase II of the building. Consequently, the contractor contended that it had no duty or obligation to construct and install the utility lines in question so that they would connect with existing lines outside of the building, and that such work was to be done by the Phase II contractor. The contracting officer disagreed and required the contractor to connect the utility lines with those existing outside the building. The contractor appealed from the decision of the contracting officer and exhausted its administrative remedy when it received an adverse decision from the Board, and the case is now before us for review under the provisions of the Wunderlich Act.

The contractor makes an ingenious argument, but the controlling facts do not support its position. The contract specifications and drawings make it abundantly clear that the contract required the contractor to install the utility lines so that they would connect with existing lines outside of the Tax Court Building.

Specifications section 0110, "Special Conditions,” clause 1, "General,” paragraph 1.1 provides in full:

1.1 Requirements of the contract include furnishing all labor and materials and performing all work for construction of United States Tax Court Building, Second Street Northwest between D & D Streets [sic], Washington, D. C., including all changes and repairs incident thereto, as specified and as shown on Drawings No. 0-1, [75]*751-1 through 1-4, 2-1, 2-2, 3-1 through 3-7, 4-1 through 4-5, 5-1 through 5-25, 7-1 through 7-15, 9-0S-1, 9-ME-1, 9-ACH-l through 9-ACH-15, 9-P-l through 9-P-10, 9-E-l through 9-E-22 (all numbers inclusive) and the listed Standard Details and noted modification thereto.

This section of the specifications is crucial to a decision of this case. It will be noted that the contractor is required to furnish all labor and materials and to perform all work as specified and shown on drawings "9-0S-1” and "9-P-l” and the other enumerated drawings. The contractor relies on drawing 9-P-l, which is the basement floor plan that shows the utility lines extending five feet from the sides of the building. The Government relies mainly on drawing 9-0S 1, which is the site utility plan that shows in great detail the required construction of the utility lines so that they connect with existing utility lines of the same kind, two of which enter the nearby Labor Department Building. A reduced copy of the relevant and pertinent parts of drawing 9-0S-1 is attached to the end of this opinion as an appendix.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SUFI Network Services, Inc. v. United States
108 Fed. Cl. 287 (Federal Claims, 2012)
Centex Construction Co. v. United States
49 Fed. Cl. 790 (Federal Claims, 2001)
PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
United Computer Supplies, Inc. v. United States
43 Fed. Cl. 351 (Federal Claims, 1999)
Mass Transit Administration v. CSX Transportation, Inc.
708 A.2d 298 (Court of Appeals of Maryland, 1998)
Town Center Management Corp. v. United States
39 Cont. Cas. Fed. 76,691 (Federal Claims, 1994)
Weston Services, Inc. v. Halliburton Nus Environmental Corp.
839 F. Supp. 1144 (E.D. Pennsylvania, 1993)
Western States Construction Co. v. United States
38 Cont. Cas. Fed. 76,376 (Court of Claims, 1992)
Halifax Engineering, Inc. v. The United States
949 F.2d 403 (Federal Circuit, 1991)
C. Sanchez & Son, Inc. v. United States
37 Cont. Cas. Fed. 76,152 (Court of Claims, 1991)
Clay Bernard Systems International, Ltd. v. United States
37 Cont. Cas. Fed. 76,067 (Court of Claims, 1991)
McDevitt Mechanical Contractors, Inc. v. United States
36 Cont. Cas. Fed. 75,954 (Court of Claims, 1990)
Titan Pacific Construction Corp. v. United States
35 Cont. Cas. Fed. 75,693 (Court of Claims, 1989)
North Santiam Sand & Gravel, Inc. v. The United States
868 F.2d 1277 (Federal Circuit, 1989)
Avedon Corp. v. United States
35 Cont. Cas. Fed. 75,592 (Court of Claims, 1988)
George Hyman Construction Company v. The United States
832 F.2d 574 (Federal Circuit, 1987)
United States v. Turner Construction Co.
819 F.2d 283 (Federal Circuit, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
564 F.2d 939, 24 Cont. Cas. Fed. 81,802, 215 Ct. Cl. 70, 1977 U.S. Ct. Cl. LEXIS 91, Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-hyman-construction-co-v-united-states-cc-1977.