Winston Bros. & Green Construction Co. v. United States

458 F.2d 49, 198 Ct. Cl. 37, 1972 U.S. Ct. Cl. LEXIS 57
CourtUnited States Court of Claims
DecidedApril 14, 1972
DocketNo. 288-69
StatusPublished
Cited by16 cases

This text of 458 F.2d 49 (Winston Bros. & Green Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Winston Bros. & Green Construction Co. v. United States, 458 F.2d 49, 198 Ct. Cl. 37, 1972 U.S. Ct. Cl. LEXIS 57 (cc 1972).

Opinion

Nichols, Judge,

delivered the opinion of the court:

This case is before us on cross-motions for summary judgment. The plaintiff was engaged in constructing a tunnel in Arkansas for the Army Corps of Engineers. On August 20, 1964, the tunnel caved in, causing substantial delay and extra cost in the project, and destroying some of plaintiff’s equipment. Following the disputes procedure of the contract, plaintiff sought a time extension and an equitable adjustment for equipment lost, and certain other expenses. The Corps of Engineers Board of Contract Appeals, (Eng. BCA Nos. 2732 and 2768,68-2 BCA ¶ 7240) found the cave-in to be the result of the Govermnent’s non-negligent but deficient design of rock bolts intended to shore up the walls of the tunnel. The Board determined that plaintiff should have an extension of time and an equitable adjustment for a constructive change. [41]*41It denied, in BOA No. 2732, plaintiff’s claim for reimbursement for loss of its equipment, two drill jumbos, on the ground that the loss was covered by insurance, the cost of which was presumably covered in the bid. Plaintiff seeks review under the Wunderlich Act, 41 U.S.C. §322 (1970), saying that, as a matter of law, such a loss of equipment is compensable under the Changes clause. In the alternative, plaintiff says that the equipment loss was a result of a breach of the Government’s warranty of its specifications and thus is compensable as a breach claim brought in this court.

Defenses raised by defendant include among others the admitted fact that the loss was insured and thus that plaintiff has been fully paid for the loss. Our ruling on the so-called insurance issue makes it unnecessary to address the others. Whether the claim is based on breach of warranty or on a theory of constructive change the result is still governed by the disposition of the threshhold issue of the effect of insurance coverage carried on the lost equipment. As we read the contract, plaintiff cannot recover by either route.

The policy of granting equitable adjustments under contract clauses is limited by the sense of what is or may be equitable. Thus, within the contract the parties have provided for compensation to contractors for some work not previously contemplated in the contract, made necessary by Government action or, as in this case, error. But the duty of the Government to the contractor does not extend beyond the contract and the general procurement process, for plaintiff of course does not prosecute a tort claim in this court, nor did it before the Board. In the primary portion of its claim before the Board, Eng. BOA No. 2768, plaintiff recovered for all the extra work made necessary by the cave-in. The Government’s duty has been performed through the administrative relief provided. The contractor is whole, in no worse position than if the contract had been performed without a hitch. In Bruce Constr. Corp. v. United States, 163 Ct. Cl. 97, 101, 324 F. 2d 516, 518-19 (1963) this court said:

But the standard of reasonable cost ‘must be viewed in the light of a particular contractor’s cost * * *’ (footnote omitted), and not the universal, objective deter-[42]*42initiation of wbat the cost would have been to other contractors at large. (Emphasis in original.)

While that case was concerned with quantum of the adjustment, the language can be applied equally as a test as to who is entitled to recover. If the contractor has incurred no cost, there is neither necessity nor rationale for an adjustment. In Bruce, supra, at 100, 324 F. 2d 518, we said:

Equitable adjustments in this context are simply corrective measures utilized to keep a contractor whole when the 'Government modifies a contract. Since the purpose underlying such adjustments is to safeguard the contractor against increased costs engendered by the modification, it appears patent that the measure of damages cannot be the value received by the Government, but must be more closely related to and contingent upon the altered position m which the contractor finds himself by reason of the modification. * * * (Emphasis supplied.)

'Plaintiff takes the position that it has not been paid by the insurance company for its loss, but merely loaned an amount equal to its loss “repayable only in the event and to the extent of any net recovery” in any legal action brought in furtherance of claims for liability for the damage covered by the loan agreement. The courts have generally found this type of insurance loan arrangement to be an acceptable business practice and have given them effect as intended. See, e.g., Luckenbach v. W. J. McCahan Sugar Refining Co., 248 U.S. 139 (1918); Dixey v. Federal Compress & Warehouse Co., 132 F. 2d 275 (8th Cir., 1942).

Accepting that the proceeds accompanying this agreement were a loan and not insurance proceeds of the underlying insurance contract, plaintiff is the only party entitled to press this action in this court, but it is still an insured contractor and had a valid claim against its insurer when the disaster happened. Therefore, we must necessarily focus on the costs suffered by plaintiff, and only its necessary costs, with regard to the claim it is now pressing. Under the circumstances presented in this case, plaintiff is now financially whole and suffers no loss regardless of this court’s decision. The insurance loan agreement clearly provides that plaintiff will be [43]*43required to repay to its insurer only tbe amounts, if any, recovered in this action. If plaintiff does not recover, it need not repay tbe loan. Thus plaintiff is not in the position of most plaintiffs in this court who have suffered an actual loss and are seeking to be made whole.

The construction contract included a clause entitled General Condition 8 which states:

GC-8. Protection of Material and, 'Work. The contractor shall at all times protect and preserve all materials, supplies and equipment of every description * * *

Defendant argues that the word “protect” places the risk of loss or damage upon plaintiff. Plaintiff suggests that this is a strained reading of the clause and beyond the “usual and ordinary meaning” admonition of Hotpoint Co. v. United States, 127 Ct. Cl. 402, 117 F. Supp 572, cert. denied, 348 U.S. 820 (1954). We agree with plaintiff that this clause, in and of itself, does not place the risk of loss caused by defective Government specifications on the contractor. The clause goes on to recite that if the contractor failed to protect equipment, the Government would do so and transfer the cost of protection to the contractor. Plaintiff suggests that the loss anticipated by the clause was damage by the elements. While plaintiff’s contract of insurance covering the drill jumbos is not in evidence, it is fair to assume a fairly broad coverage, including damage due to weather. Therefore, plaintiff at least partially would have been motivated to insure its equipment in part because General Condition 8 wherever encountered in Government contracts made clear that the Government did not intend to act as caretaker of the equipment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

North Slope Technical, Ltd. v. United States
38 Cont. Cas. Fed. 76,458 (Federal Claims, 1992)
D.H. Blattner & Sons, Inc. v. The United States
909 F.2d 1495 (Federal Circuit, 1990)
Amoco Oil Co. v. United States
3 Cl. Ct. 785 (Court of Claims, 1983)
Raytheon Co. v. United States
31 Cont. Cas. Fed. 71,309 (Court of Claims, 1983)
Oman Construction Co. v. Tennessee Valley Authority
486 F. Supp. 375 (M.D. Tennessee, 1979)
General Dynamics Corp. v. United States
585 F.2d 457 (Court of Claims, 1978)
George Hyman Construction Co. v. United States
564 F.2d 939 (Court of Claims, 1977)
S.W. Aircraft Inc. v. United States
551 F.2d 1208 (Court of Claims, 1977)
Marinette Marine Corp. v. United States
546 F.2d 365 (Court of Claims, 1976)
Atlantic Gulf & Pacific Co. of Manila
21 Cont. Cas. Fed. 84,079 (Court of Claims, 1975)
Victory Construction Co. v. United States
510 F.2d 1379 (Court of Claims, 1975)
AMCO Electric v. United States
493 F.2d 647 (Court of Claims, 1974)
Hills Transportation Co. v. United States
492 F.2d 1394 (Court of Claims, 1974)
Winston Bros. Company v. United States
371 F. Supp. 130 (D. Minnesota, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
458 F.2d 49, 198 Ct. Cl. 37, 1972 U.S. Ct. Cl. LEXIS 57, Counsel Stack Legal Research, https://law.counselstack.com/opinion/winston-bros-green-construction-co-v-united-states-cc-1972.