Winston Bros. Company v. United States

371 F. Supp. 130, 1973 U.S. Dist. LEXIS 12128
CourtDistrict Court, D. Minnesota
DecidedAugust 28, 1973
Docket4-73-Civil 30
StatusPublished
Cited by7 cases

This text of 371 F. Supp. 130 (Winston Bros. Company v. United States) is published on Counsel Stack Legal Research, covering District Court, D. Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Winston Bros. Company v. United States, 371 F. Supp. 130, 1973 U.S. Dist. LEXIS 12128 (mnd 1973).

Opinion

MEMORANDUM

LARSON, District Judge.

This is an action under the Federal Tort Claims. Act, 28 U.S.C. § 1346(b), *132 seeking $81,238.39 reimbursement for damages to two drill jumbos. The pieces of heavy construction equipment were buried and subsequently demolished in a cave-in of a portion of a tunnel being excavated in connection with the DeGray Dam and Reservoir Project in Clark County, Arkansas. The case comes here after adjudications by the Contracting Officer, Board of Contract Appeals for the Army Corps of Engineers, and the Court of Claims, all of which have denied the claim.

Plaintiffs Winston Brothers Company and Green Construction Company, d/b/a Winston-Green, are engaged in the heavy construction industry. They assert breach of contract, breach of warranty, and negligence on the part of the Government in preparing and issuing allegedly deficient plans and specifications in connection with the project, resulting in the cave-in and attendant damages incurred by Winston-Green. Additionally, a subrogation claim is asserted by Connecticut Fire Insurance Company (Connecticut Fire), Winston-Green’s insurer.

The Government advances two dispositive arguments in its motion for summary judgment: the Court lacks jurisdiction over contract claims being asserted here, and the other claims are barred by the statute of limitations. Because the pleadings and other matters before this Court establish as a matter of law that the claims cannot be heard by this Court, the Government’s motion will be granted.

Winston-Green and the Department of Army, Corps of Engineers, made a $4,687,947.35 contract (later modified to $5,145,789.05) on January 10, 1964, under which Winston-Green was to construct a 1,684 foot tunnel and appurtenances in connection with the DeGray Project. Plans and specifications were to be furnished by the Corps.

Work on the upstream portal of the tunnel began August 11, 1964, with excavation to be done mainly by blasting. On August 20, 1964, about three hours and forty-five minutes after a misfired dynamite blast, a large cave-in occurred in which the two drill jumbos and other equipment were ruined. Connecticut Fire paid Winston-Green the full amount of the claimed loss in a November 20, 1964, transaction cast in the form of a “loan” agreement, repayment contingent on Winston-Green’s recovery from the Government.

Since then Winston-Green has thrice attempted to secure reimbursement from the Government. First, a claim was filed with the Contracting Officer on May 19, 1965, pursuant to the contractually specified procedures for handling disputes under the contract. On July 1, 1965, the Officer ruled that there was no provision in the contract for reimbursement for losses of this kind.

Winston-Green then appealed to the Board of Contract Appeals on July 13, 1965. After hearing extensive evidence, the Board on September 6, 1968, ruled that the collapse resulted from the Corps’ deficient design of rock bolts shoring up the walls of the tunnel. Lacking authority to hear tort allegations, both the Contracting Officer and Board ruled only on the contractual aspect of the claim. Accordingly, the Board’s finding that the Government was “responsible” for the cave-in was not necessarily indicative of fault cognizable under tort law.

Although granting time extension and price adjustments, the Board affirmed the denial of reimbursement for the damaged equipment. Its decision was grounded on relevant provisions of the contract and the Armed Services Procurement Regulations incorporated therein leaving the risk of this kind of loss on the contractor. Eng. BCA Nos. 2732 and 2768, 68-2 BCA Par. 7240.

Winston-Green next instituted suit in the Court of Claims on June 20, 1969, seeking review under the Wunderlich Act, 41 U.S.C. § 322 (1970), and, in the alternative, claiming breach of warranty. In an opinion rendered April 14,1972, the *133 Court agreed with the reasoning of the Board. It found relevant contractual provisions precluding the contractor’s claims and also rejected the contention of a Government “warranty” to pay for damages to equipment due to defective specifications. Winston Brothers Co. v. United States, 458 F.2d 49, 198 Ct.Cl. 37 (1972). The instant action was commenced January 15,1973.

Winston-Green’s breach of contract claim must be dismissed because this Court lacks jurisdiction under the Tucker Act, 28 U.S.C. § 1346(a)(2), to hear contractual claims against the Government in excess of $10,000. Akin Mobile Homes, Inc. v. Secretary of Housing & Urban Development, 475 F.2d 1261, 1262 (5th Cir. 1973); Putnam Mills Corp. v. United States, 432 F.2d 553, 554 (2d Cir. 1970); Murray v. United States, 132 App.D.C. 91, 405 F.2d 1361, 1366 (1968).

The nature of the warranty claim is unclear from the pleadings. The Court of Claims did treat a warranty claim as being based on the contract, but this is understandable in view of that Court lacking jurisdiction over claims sounding in tort. 28 U.S.C. § 1491. If Winston-Green is likewise here presenting a claim under the contract, it would meet the same fate of dismissal under the Tucker Act as the breach of contract allegation.

It is possible, however, to construe the warranty allegation here as constituting a claim of strict liability in tort. See Annot., Products Liability-— Strict Liability, 13 A.L.R.3d 1057 (1967). Rather than being precluded by the Tucker Act, such a claim could be asserted under the Federal Torts Claims Act. 1 But it would be barred by the same statute of limitations defense that the Court finds fatal to the negligence and subrogation claims.

The applicable statute of limitations for tort claims against the Government provides as follows:

“A tort claim . . . shall be forever barred unless action is begun within two years after such claim accrues . . . . ” 28 U.S.C. § 2401(b) (1964 ed.), Act of April 25, 1949, ch. 92, § 1, 63 Stat. 62.

This provision governs all claims accruing prior to January 18, 1967, even if a civil action is brought subsequent to that date. Katzer v. United States, 342 F.Supp. 1088 (E.D.Wis.1972); Rygg v. United States, 334 F.Supp. 219 (D.N.D. 1971); Whealton v. United States, 271 F.Supp. 770 (E.D.Va.1967).

Claims arising after that date are governed by the amended statute of limitation. 28 U.S.C. § 2401(b), as amended, Act of July 18, 1966, Pub.L. 89-506, § 7, 80 Stat. 307. This version requires a claim to be filed with the pertinent administrative agency in all tort claims and then gives the claimant six months after denial of the claim to sue in District Court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. House
100 F. Supp. 2d 967 (D. Minnesota, 2000)
Group Health Inc. v. United States
662 F. Supp. 753 (S.D. New York, 1987)
Vega-Velez v. United States
627 F. Supp. 773 (D. Puerto Rico, 1986)
Norma Denton v. United States
638 F.2d 1218 (Ninth Circuit, 1981)
Albert Korgel and Margaret Korgel v. United States
619 F.2d 16 (Eighth Circuit, 1980)
In Re Bomb Disaster at Roseville, Cal., on April 28
438 F. Supp. 769 (E.D. California, 1977)
United Missouri Bank South v. United States
423 F. Supp. 571 (W.D. Missouri, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
371 F. Supp. 130, 1973 U.S. Dist. LEXIS 12128, Counsel Stack Legal Research, https://law.counselstack.com/opinion/winston-bros-company-v-united-states-mnd-1973.