Colonial Metals Co. v. United States

495 F.2d 1355, 204 Ct. Cl. 320
CourtUnited States Court of Claims
DecidedApril 17, 1974
DocketNo. 387-72
StatusPublished
Cited by17 cases

This text of 495 F.2d 1355 (Colonial Metals Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Colonial Metals Co. v. United States, 495 F.2d 1355, 204 Ct. Cl. 320 (cc 1974).

Opinion

Per Curiam:

This case comes before the court on defendant’s motion, filed January 22, 1974, requesting that the court adopt the recommended decision of Trial Judge David Schwartz, filed November 23, 1973, pursuant to Buie 166(c), on plaintiff’s motion and defendant’s cross-motion for summary judgment, as the basis for its judgment in [324]*324i.bi.g case since plaintiff has failed to file a request for review by the court of the said decision in accordance with the Rules of the court. Upon consideration thereof, without oral argument, since the court agrees with the decision, as hereinafter set forth, it hereby affirms and adopts the same as the basis for its judgment in this case. Therefore, defendant’s motion of January 22, 1974, is granted, plaintiff’s motion for summary judgment is denied, defendant’s cross-motion for summary judgment is granted and plaintiff’s petition is dismissed.

OPINION OP TRIAL JUDGE

Schwartz, Trial Judge:

This is a suit to review a decision of the Armed Services Board of Contract Appeals awarding $250 on plaintiff’s claim for $123,059 as the allowable costs on the Government’s termination for convenience of a contract to sell copper ingot to the Navy. A second count raises the claim, dismissed by the Board as beyond its jurisdiction, that the termination-for-convenience clause was invoked for an improper purpose and therefore constituted a breach of contract.

The parties have made cross-motions for summary judgment on both counts, thereby presenting the entire case for final disposition. Both counts are to be disposed of on the record made in the administrative proceeding; United States v. Carlo Bianchi & Co., 373 U.S. 709, 714 (1963), so holds for the count to review the Board action and an agreement of the parties so provides for the count for breach of contract. The review of the Board’s decision takes place in accordance with the standards of the Wunderlich Act, 41 U.S.C. §§ 821-22, by which the Board’s findings of fact are final if supported by substantial evidence and its decisions of law are open to fresh consideration.

The Navy’s invitation to bid, issued in late 1969, asked for the supply of 479,607 lbs. of copper ingot in May 1970. Plaintiff, a secondary dealer in copper, was the only bidder, and on December 24,1969 was awarded the contract, at the bid price of $.7838 per lb.

The invitation had also sought bids on a further 440,000 lbs., set aside under Armed Services Procurement Regulation [325]*3251-804.2(b), 32 CFB § 1.804-2(b) (1970), for supply by concerns in labor surplus areas. Plaintiff was qualified as such a concern. Immediately following the award, a Navy procurement officer and an officer of the plaintiff had a telephone conversation in which the plaintiff claims the parties concluded an oral contract for the additional, set-aside quantity; the Board held to the contrary.

A week later, on December 31,1969, plaintiff ordered 960,-000 lbs. of May 1970 copper from Aaron Ferer & Sons Co. for $.7225 per lb., to fulfill the basic contract and the claimed contract for the additional, set-aside quantity.

On January 20,1970 the Government terminated the basic contract for its convenience, under the contract clause on that subject, and thereafter it denied the making of a contract for the set-aside quantity. Between January 27 and March 12 the Government bought the copper it needed from primary sources — leading copper mining companies — at between $.55 and $.56 per lb. The purpose of the termination was to obtain the prices, much lower than the contract price, at which copper is sold by the primary sources. Their prices are common knowledge, regularly published. The purpose and circumstances of the termination are the basis of plaintiff’s claim of breach of contract.

Immediately upon the termination, plaintiff cancelled its purchase order with the Ferer firm for purposes of the Government contract, simultaneously replaced the order for its own account, and thereafter, in April 1970, sold the copper for more than it had paid for it but less than the price in the contract with the Navy. In a termination costs proceeding, the Board allowed neither profit on the contract with the Government nor loss on the contract with Ferer.

The questions presented are whether the parties made a contract for the additional set-aside quantity; whether the termination for convenience was a breach of contract; and whether the Board wrongly failed to award, in the termination settlement proceeding, profit on the Government contract and losses on the Ferer contract. All these questions are herein answered in the negative, against the plaintiff.

[326]*326 The Alleged Contract for the Set-Aside Quantity

The threshold issue is the scope of the contract to be considered — whether it included the additional 440,000 lbs. of ingot set aside for specially qualified bidders, of whom plaintiff was one.

When the notice of award for the basic non-set-aside quantity had been mailed to plaintiff, a Mr. Hoover, a Navy procurement officer, called Mr. Mann, plaintiff’s executive vice president, told him of the award, and inquired whether plaintiff would be interested in an award of the set-aside quantity. On the basis of what then was said over the telephone, plaintiff maintains that an oral contract was concluded or “implied in fact.” Alternatively, it is contended that the Government is equitably estopped to deny the existence of a contract, because in reliance on the representations made by Mr. Hoover, an agent clothed with apparent authority, plaintiff on December 31, 1969 bought 960,000 lbs. of copper ingot, to make delivery of both the basic and the set-aside quantities.

The Board accepted none of these arguments. Mr. Hoover did not, the Board found, purport to make an award of contract for the set-aside quantity; at most he assured Mr. Mann that plaintiff would receive an award subject to prior approval at a higher level. The Board further found that Mr. Hoover did not have and did not expressly or by implication represent that he had authority to award a contract.

Depositions by both participants to the telephone conversation were made a part of the record. Mr. Hoover testified that he called Mr. Mann, asked whether plaintiff would be interested in the set-aside quantity; that Mr. Mann said plaintiff would be interested; that they then had a little bit of discussion as to “whether a new contract would be issued, or whether the existing contract would be modified. And I indicated to him that it would be handled by a modification, but it would take several days to get it out because of necessary internal approvals.” Mr. Hoover added that “We had every intention at that time to award the set-aside portion to plaintiff.”

Mr. Mann’s version was that when he told Mr. Hoover that plaintiff was interested, “He said, okay, that we have [327]*327the contract and the set-aside, but it would take a couple of days to get the papers out.”

Mr. Hoover was not a contracting officer with authority to contract but a lesser officer called a procurement officer, subordinate to the contracting officer. In talking to Mr. Mann he did not identify himself other than, Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Handi-Van, Inc. v. Broward County
116 So. 3d 530 (District Court of Appeal of Florida, 2013)
Questar Builders, Inc. v. CB Flooring, LLC
978 A.2d 651 (Court of Appeals of Maryland, 2009)
RAM Engineering & Construction, Inc. v. University of Louisville
127 S.W.3d 579 (Kentucky Supreme Court, 2003)
Cray Research, Inc. v. United States
42 Cont. Cas. Fed. 77,349 (Federal Claims, 1998)
Krygoski Construction Company, Inc. v. United States
94 F.3d 1537 (Federal Circuit, 1996)
Advanced Materials, Inc. v. United States
40 Cont. Cas. Fed. 76,868 (Federal Claims, 1995)
City of Klawock v. United States
31 Cont. Cas. Fed. 71,244 (Court of Claims, 1983)
Airborne Data, Inc. v. The United States
702 F.2d 1350 (Federal Circuit, 1983)
Torncello v. United States
681 F.2d 756 (Court of Claims, 1982)
American General Leasing, Inc. v. United States
587 F.2d 54 (Court of Claims, 1978)
Allied Materials & Equipment Co.
24 Cont. Cas. Fed. 81,810 (Court of Claims, 1977)
James E. McFadden, Inc.
24 Cont. Cas. Fed. 81,819 (Court of Claims, 1977)
Kalvar Corp. v. United States
543 F.2d 1298 (Court of Claims, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
495 F.2d 1355, 204 Ct. Cl. 320, Counsel Stack Legal Research, https://law.counselstack.com/opinion/colonial-metals-co-v-united-states-cc-1974.