RAM Engineering & Construction, Inc. v. University of Louisville

127 S.W.3d 579, 2003 Ky. LEXIS 264, 2003 WL 22971158
CourtKentucky Supreme Court
DecidedDecember 18, 2003
Docket2001-SC-0264-DG
StatusPublished
Cited by20 cases

This text of 127 S.W.3d 579 (RAM Engineering & Construction, Inc. v. University of Louisville) is published on Counsel Stack Legal Research, covering Kentucky Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RAM Engineering & Construction, Inc. v. University of Louisville, 127 S.W.3d 579, 2003 Ky. LEXIS 264, 2003 WL 22971158 (Ky. 2003).

Opinions

GRAVES, Justice.

In August 1996, Appellee, the University of Louisville, began accepting bids for the construction of its new Papa John’s Cardinal stadium in accordance with the Kentucky Model Procurement Code, KRS Chapter 45A. The University’s construction plans involved seven different “packages,” including Bid Package No. 1 — Site Development, the subject of this case. After receiving all of the bids, the University determined that the low bids exceeded the construction budget. Pursuant to KRS 45A.090(2), the University negotiated with the three lowest bidders, which included Appellant, RAM Engineering and Construction, Inc. (RAM). On September 23, 1996, RAM was declared the lowest of the three bidders at $7,593,325.

MAC Construction and Excavating, Inc., the original low bidder, filed a protest with the University challenging the award of Bid Package No. 1 to RAM. The University denied the protest and, on September 26, 1996, issued a Notice to Proceed to RAM. MAC thereafter filed a declaratory judgment action against the University in the Franklin Circuit Court and sought to enjoin the University from commencing construction of the stadium. RAM neither received notice of nor was made a party to the action. That same day, the circuit court issued a Temporary Restraining Order preventing RAM from proceeding with construction. However, the TRO was never signed or entered into the record. MAC and the University subsequently entered into an agreed order, which was entered by the circuit court. The agreed order declared any prior award of Bid Package No. 1 null and void, and required the University to rebid the package once again.

On October 2, 1996, the University issued a third invitation to bid on the stadium project. RAM was once again the low bidder on Bid Package No. 1 at $6,993,900, which was $599,425 less than its previous bid. The University accepted RAM’s bid and issued another Notice to Proceed on October 4, 1996. However, RAM filed a protest with the University, objecting to the reduction in the bid contract. The University denied the protest on the grounds that no contract had existed between RAM and the University following the previous bid, or that if it had existed, the University had the power to terminate the contract at its convenience.

RAM then filed an action in the Franklin Circuit Court seeking money damages for breach of the original bid contract. The circuit court ruled that although the University and RAM had entered into a valid and binding contract, the contract was rendered void by entry of the agreed order from the MAC litigation. The circuit court reasoned that entry of the agreed order constituted a substantial change in circumstances allowing the Uni[582]*582versity to properly invoke the Termination for Convenience clause of the contract. Accordingly, summary judgment was entered in favor of the University.

The Court of Appeals upheld the summary judgment in favor of the University. Further, in rejecting RAM’s due process argument that the agreed order voiding RAM’s initial contract could have no effect because RAM had not been joined in the MAC litigation, the Court of Appeals held, “RAM had no right or ability to affect the outcome of the litigation” and thus, “was not denied due process, and was not an indispensable party to the MAC litigation.”

This Court thereafter granted RAM’s motion for discretionary review. RAM contends that it was an indispensable party to the MAC litigation and was entitled to participate and defend its contract with the University. RAM further argues that the lower courts erroneously found that the agreed order between the University and MAC constituted the substantial change in circumstances required for the University to terminate RAM’s contract for convenience.

I. INDISPENSABLE PARTIES

RAM argues that it should have been joined in the MAC litigation as a party needed for just adjudication pursuant to both CR 19.01 and the good faith obligations of the Kentucky Model Procurement Code. RAM posits that the Court of Appeals effectively rendered CR 19.01 and KRS 418.075 meaningless by refusing to require the presence of a successful bidder, in this case RAM, in an action challenging the public bidding process. See Veith v. City of Louisville, Ky., 355 S.W.2d 295 (1962).

MAC challenged the procedures used by the University for rebidding Bid Package No. 1. After the circuit court issued the Temporary Restraining Order, the University entered into an Agreed Order with MAC, rendering the bid contract with RAM null and void. The Court of Appeals found that RAM “was not a necessary party to [the] action, as RAM had no involvement in the actions complained of as being improper or unlawful.” However, in West v. Goldstein, Ky., 830 S.W.2d 379 (1992), this Court held, “The true meaning of ‘all necessary parties,’ as stated in Security Trust Co. v. Swope, 274 Ky. 99, 118 S.W.2d 200 (1938), is that the term refers to those persons whose interest would be divested by an adverse judgment.”

RAM’s interest in the validity of the disputed bidding procedures was as great as any other possible party because the bidding resulted in the University’s awarding the contract to RAM. RAM’s interest in defending its contract fits squarely within the qualifications of a necessary party under CR 19.01(b), because its interest related to the validity of the bidding process through the awarded contract, and its absence from the action impaired RAM’s ability to protect the contract. Even though RAM may have intervened after entry of the agreed order, Rosenbalm v. Commercial Bank of Middlesboro, Ky. App., 838 S.W.2d 423 (1992), it chose instead to enter into an agreement with the University whereby RAM would participate in the rebidding while retaining any rights from the first contract in order to expedite the commencement of construction in good faith. As we held in City of Louisville v. Louisville Auto. Club, 290 Ky. 241, 250, 160 S.W.2d 663, 668 (1942), wherein the city entered into a purchase contract for parking meters and citizens challenged the validity of the ordinance requiring meters, “The contract here involves a bit of money; it is but fit and proper that the interested contractor have his day in court.” Accordingly, we con-[583]*583dude that RAM was, in fact, an indispensable party to the MAC litigation.

II. FEDERAL PROCUREMENT LAW

The concept of termination for the government’s convenience developed as a method to avoid procurement contracts after the close of the Civil War. The government, under certain circumstances, would terminate contracts and settle with the contractor for partial performance. See generally Tomcello v. United States, 231 Ct.Cl. 20, 681 F.2d 756, 764-766 (1982), explaining United States v. Corliss Steamr-Engine Co.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Douglas T. Jones v. University Medical Center, Inc.
Court of Appeals of Kentucky, 2025
James Ridenour v. Commonwealth of Kentucky
Court of Appeals of Kentucky, 2021
A.L. Prime Energy Consultant, Inc. v. Mass. Bay Transportation Authority
95 N.E.3d 547 (Massachusetts Supreme Judicial Court, 2018)
MB Oil Ltd., Co. v. City of Albuquerque
2016 NMCA 090 (New Mexico Court of Appeals, 2016)
Jansing v. State of Calif. CA4/1
California Court of Appeal, 2016
Ford Contracting, Inc. v. Kentucky Transportation Cabinet
429 S.W.3d 397 (Court of Appeals of Kentucky, 2014)
Louisville Arena Authority, Inc. v. RAM Engineering & Construction, Inc.
415 S.W.3d 671 (Court of Appeals of Kentucky, 2013)
Commonwealth v. Morseman
379 S.W.3d 144 (Kentucky Supreme Court, 2012)
Vila & Son Landscaping Corp. v. Posen Construction, Inc.
99 So. 3d 563 (District Court of Appeal of Florida, 2012)
McMullin v. McMullin
338 S.W.3d 315 (Court of Appeals of Kentucky, 2011)
Questar Builders, Inc. v. CB Flooring, LLC
978 A.2d 651 (Court of Appeals of Maryland, 2009)
RAM Engineering & Construction, Inc. v. University of Louisville
127 S.W.3d 579 (Kentucky Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
127 S.W.3d 579, 2003 Ky. LEXIS 264, 2003 WL 22971158, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ram-engineering-construction-inc-v-university-of-louisville-ky-2003.