MB Oil Ltd., Co. v. City of Albuquerque

2016 NMCA 090, 10 N.M. 542
CourtNew Mexico Court of Appeals
DecidedJuly 25, 2016
DocketS-1-SC-36053; Docket 34,493
StatusPublished

This text of 2016 NMCA 090 (MB Oil Ltd., Co. v. City of Albuquerque) is published on Counsel Stack Legal Research, covering New Mexico Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MB Oil Ltd., Co. v. City of Albuquerque, 2016 NMCA 090, 10 N.M. 542 (N.M. Ct. App. 2016).

Opinion

OPINION

VANZI, Judge.

{1} The City of Albuquerque (the City) appeals from a judgment awarding nearly four million dollars in anticipatory profits for the wrongful termination of a supply contract (Contract) that was expressly terminable for cause or convenience. Because we conclude as a matter of law that the contract was not wrongfully terminated, we reverse and remand for entry of judgment in favor of the City.

BACKGROUND

{2} The following factual background is derived from the district court’s findings of fact, to which we generally defer, see State v. Munoz, 1998-NMCA-140, ¶ 14, 125 N.M. 765, 965 P.2d 349, and from the terms of the Contract itself, which we can interpret as well as the district court. See Krieger v. Wilson Corp., 2006-NMCA-034, ¶ 12, 139 N.M. 274, 131 P.3d 661 (“In the absence of ambiguity, the interpretation of language in a contract is an issue of law which we review de novo.”).

{3} MB Oil Ltd., Co. (Plaintiff) is a wholesale fuel distributor that contracted with the City to be the primary supplier of certain fuels to the City’s Fleet Management Division. The Contract provided that the quantities of fuel to be delivered would vary depending on the City’s needs. During the contract period, Plaintiff would treat the City as a “preferred customer,” delivering requested fuel within twelve hours of any order and always assigning first priority to the City’s requirements. In exchange, the City would treat Plaintiff as its primary fuel supplier, ordering from Plaintiff first at prices agreed upon in the Contract before turning to secondary and tertiary suppliers in the event Plaintiff could not meet the City’s needs.

{4} Section 26 of the request for bids, which was later merged into the Contract, gave the City the right to terminate the agreement for default, after giving notice to cure, if Plaintiff failed to fulfill its delivery obligations “in a timely and proper manner[.]” Immediately following the termination for default clause, Section 27 then provided an alternative basis for termination, which is the subject of this Opinion:

Termination for the Convenience of the City:
The City may terminate [the Cjontract... at any time by giving at least thirty (30) days’ notice in writing of such termination to [Plaintiff], In such event, [Plaintiff] shall be paid under the terms of the [C]ontract for all goods/services provided to and accepted by the City, if ordered or accepted by the City prior to the effective date of termination.

A termination for convenience clause is generally understood to be a risk-allocating tool, intended to permit a government to “terminate a contract, even in the absence of fault or breach by the other party, without incurring the usual financial consequences of breach.” Mark Dunning Indus. v. Cheney, 934 F.2d 266, 267 n.1 (11th Cir. 1991) (per curiam) (internal quotation marks and citation omitted). It has become a standard term in federal procurement contracts. See Krygoski Constr. Co. v. United States, 94 F.3d 1537, 1541 (Fed. Cir. 1996); see also 48 C.F.R. § 49.502 (2007) (noting the types of contracts that utilize a termination for convenience by the government clause). Like other municipalities — and even some private parties' — the City has apparently taken the federal government’s lead and begun including the clause in its own contracts. See, e.g., Old Colony Constr., LLC v. Town of Southington, 113 A.3d 406, 408 n.1 (Conn. 2015); Vila & Son Landscaping Corp. v. Posen Constr., Inc., 99 So. 3d 563, 566-68 (Fla. Dist. Ct. App. 2012). It does so because, as the Director forFinance and Administration for the City of Albuquerque testified at trial, the City needs to be able to cancel its contracts if operational reasons require it to change course.

{5} Plaintiff submitted its bid in October 2009 — —its first time bidding on a city contract. An exhibit admitted at trial indicates that it offered to charge the City a paltry delivery price of $148,660.46 compared to the second lowest bidder, which proposed a price nearly six times higher. Not surprisingly, the City ultimately awarded the primary supply Contract to Plaintiff, and Plaintiff began performing in March 2010.

{6} There were then various occasions throughout the summer of 2010 where Plaintiff was unable to timely deliver fuel or unable to deliver fuel at all due to what the district court later concluded was a lack of availability of fuel to deliver. The district court also concluded that in each of the instances when fuel was unavailable to Plaintiff, the City was forced to turn to its backup vendors to provide the fuel. It is thus apparent that the fuel that was unavailable to Plaintiff was in fact available to other suppliers, including the City’s backup vendors.

{7} On multiple occasions, beginning in July 2010, the City notified Plaintiff in writing that fuel requirements were not being met. Specifically, a letter dated July 12, 2010, informed Plaintiff that it was in default. That letter also stated that Plaintiff had been unable to provide unleaded fuel to the City for a month. And a second letter, dated August 31, 2010, explained that Plaintiffs failure to provide fuel when ordered “creates problems for the City and is in violation of the [C]ontract requirements.” The City finally terminated the contract for default and/or convenience on September 9, 2010, citing Plaintiffs failure to “provid[e] fuel within the delivery time requirements of the [C]ontract, i.e., within [twelve] hours of order placementf.]” The cancellation letter also noted that Plaintiff made partial deliveries, and “on several occasions,” actually refused to provide fuel.

{8} Plaintiff filed suit alleging various tort claims that have since been dismissed and leaving two contract claims that went to trial. Count I’s breach of contract claim essentially alleged a bait-and-switch scheme: that the City’s request for bids misrepresented the amounts and types of fuel the City would order to the detriment of vendors who relied on those estimates in formulating their bids. Of particular importance was the City’s failure to accurately estimate requirements of E85 (85% ethanol-blended fuel), which was the basis for Plaintiffs profit margin in the Contract. To Plaintiffs detriment, the City “cancell[ed]” all orders of that fuel type early in the Contract term.

{9} Count IV similarly alleged only that the City “breached the covenant of good faith and fair dealing by knowingly and intentionally breaching the contractual agreements with [Plaintiff].” All told, the Complaint was directed at the City’s alleged conduct in soliciting bids and making untimely payments and such — behavior that Plaintiff alleged caused it various damages.

{10} Following a bench trial, the district court entered its findings and conclusions ruling in favor of Plaintiff and awarded substantial damages. Liability was not premised on the complaint’s bait-and-switch allegations, its late payments theory, or on the alleged cancellation of E85.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harris Corporation v. Giesting & Associates
297 F.3d 1270 (Eleventh Circuit, 2002)
Charles R. Nesbitt v. The United States
345 F.2d 583 (Court of Claims, 1965)
Maxima Corporation v. The United States
847 F.2d 1549 (Federal Circuit, 1988)
Krygoski Construction Company, Inc. v. United States
94 F.3d 1537 (Federal Circuit, 1996)
State v. Munoz
1998 NMCA 140 (New Mexico Court of Appeals, 1998)
Melnick v. State Farm Mutual Automobile Insurance
749 P.2d 1105 (New Mexico Supreme Court, 1988)
Smith v. PRICE'S CREAMERIES, DIV., ETC.
650 P.2d 825 (New Mexico Supreme Court, 1982)
Lopez v. Kline
1998 NMCA 016 (New Mexico Court of Appeals, 1997)
Knotts v. United States
121 F. Supp. 630 (Court of Claims, 1954)
RAM Engineering & Construction, Inc. v. University of Louisville
127 S.W.3d 579 (Kentucky Supreme Court, 2003)
Gadsden v. United States
78 F. Supp. 126 (Court of Claims, 1948)
Santa Fe Custom Shutters & Doors, Inc. v. Home Depot U.S.A., Inc.
2005 NMCA 051 (New Mexico Court of Appeals, 2005)
Ry-Tan Construction, Inc. v. Washington Elementary School District No. 6
93 P.3d 1095 (Court of Appeals of Arizona, 2004)
Planning & Design Solutions v. City of Santa Fe
885 P.2d 628 (New Mexico Supreme Court, 1994)
Vila & Son Landscaping Corp. v. Posen Construction, Inc.
99 So. 3d 563 (District Court of Appeal of Florida, 2012)
Krieger v. Wilson Corp.
2006 NMCA 034 (New Mexico Court of Appeals, 2005)
Kalvar Corp. v. United States
543 F.2d 1298 (Court of Claims, 1976)
Torncello v. United States
681 F.2d 756 (Court of Claims, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
2016 NMCA 090, 10 N.M. 542, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mb-oil-ltd-co-v-city-of-albuquerque-nmctapp-2016.