T & M Distributors, Inc. v. United States

185 F.3d 1279, 1999 U.S. App. LEXIS 17030, 1999 WL 538206
CourtCourt of Appeals for the Federal Circuit
DecidedJuly 26, 1999
Docket98-5106
StatusPublished
Cited by64 cases

This text of 185 F.3d 1279 (T & M Distributors, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
T & M Distributors, Inc. v. United States, 185 F.3d 1279, 1999 U.S. App. LEXIS 17030, 1999 WL 538206 (Fed. Cir. 1999).

Opinion

SCHALL, Circuit Judge.

T & M Distributors, Inc. (T & M) appeals from the final judgment of the United States Court of Federal Claims dismiss *1280 ing its claim against the United States for breach of a requirements contract. T & M Distrib. v. United States, No. 97-148C, 1998 WL 118077 (Fed.Cl. Mar. 17, 1998).

Shortly after award, the Navy terminated its contract with T & M for the convenience of the government. In due course, T & M submitted a termination settlement proposal and a breach of contract claim alleging wrongful termination. The parties reached settlement on termination costs to which T & M was entitled, but the contracting officer denied the breach of contract claim. T & M appealed the denial to the Court of Federal Claims, which granted the government’s motion for summary judgment after concluding that the contracting officer had not acted improperly in invoking the contract’s termination for convenience clause. We affirm.

BACKGROUND

I

On October 19, 1995, the Navy awarded Contract No. N00406-96-D-4026 to T & M. Under the contract, T & M was to provide the Navy with automotive and related vehicle parts and accessories to support the United States Public Works Center on the island of Guam. The contract was awarded pursuant to a competitive procurement bid solicitation. The solicitation sought bids for the operation and maintenance of a Contractor Operated Parts Store (“COPARS”) on Guam for one base year and four one-year option periods. The Navy’s annual requirements were estimated in a list of anticipated expenditures that was appended to the solicitation. An amendment to the solicitation included a list of questions and answers, among which was the following:

Q10. What amount, if any, of government owned parts are currently on hand? Is there a listing available? What category are those parts under?
Answer: The amount of government owned parts on hand changes rapidly from day to day. The contractor shall assume that the Government does not have a supply of parts on hand to supplement contractor inventory.

T & M was awarded the contract, with performance to begin on December 1, 1995. The value of the contract for all five years was estimated at $1,130,000. The contract contained the standard clause found at 48 C.F.R. § 52.249-2, allowing for termination of the contract for the convenience of the government.

After experiencing difficulties in compiling a comprehensive parts inventory list, T & M’s president, Thomas W. Daly, visited Guam in early November 1995. Upon his return from Guam, Mr. Daly wrote the contracting officer that he had discovered circumstances that suggested a diminished value of the contract and possible obstacles to contract performance:

[I]t was revealed to us that the Public Works Facility at Guam had an existing “base store” which provided them with replacement parts for their vehicles. This was troubling for two reasons; the contract clearly calls for the establishment of a COPARS to supply the [Department of Public Works (DPW) ] with repair parts and this also affects our ability to put together a workable inventory if the DPW “base store” already stocks some parts.
* * * * * *
I discovered the following: the base store maintains an inventory of approximately $700,000.00 with a total number of 4000 line items. This is a long way from no inventory as had been stated. I was also informed that the DPW was required to go to the base store as their first source of supply, to [Fleet and Industrial Supply Center] next and then to the contractor. I also learned unofficially that the DPW also had [Basie Purchase Agreements] with local parts distributors. As you can imagine this all plays a part in how we structure our inventory and our ability to do business with DPW.

*1281 Although Mr. Daly assured the contracting officer that T & M was ready, willing, and able to be operational by December 1, 1995, he requested that the date for the commencement of contract performance be postponed to January 2,1996.

On November 28, 1995, the contracting officer instructed T & M to suspend preparations. The next day, Mr. Daly sent a letter to the contracting officer in which he proposed contract modifications to “resolve the problems [in] making the COPARS store operational.” In December, a government attorney visited Guam to investigate Mr. Daly’s concerns and to obtain relevant information. The contracting officer later recounted what the investigation revealed:

a. The government did have an existing inventory in the approximate amount of $700,000 and had Basic Purchase Agreement’s (BPA’s) with local firms. This information had not been disclosed to the Contracting Officer and this office during the solicitation process.
b. The estimated amount in the contract was grossly understated. A review of the historical usage indicated the estimated amount for the base period and option periods should have been $4,455,911 rather than the [$]595,250 as awarded by the contract.
c. There were conflicting opinions among Navy managers at the [Public Works Center], Guam as to the type of contract desired. Ultimately, however, the decision was made to utilize an indefinite requirements type of contract with performance to begin April 1, 1996. In a letter dated December 21, 1995, the

contracting officer terminated the contract for the convenience of the government. On January 17, 1996, the Navy issued a second solicitation, which took into account the existence of a temporary base store and the increased estimated value of the contract. The solicitation estimated the contract value at $5,048,590, a 450 percent increase over the estimate in the first solicitation. T & M and one other contractor submitted bids. The contract was awarded to the other contractor, who had not bid on the first solicitation.

II

On September 3, 1996, T & M submitted to the contracting officer a certified claim for breach of contract, seeking damages in the form of anticipated profits in the amount of $1,325,00o. 1 In a decision dated January 3, 1997, the contracting officer denied the claim, based on his determination that the termination of the contract was neither arbitrary nor capricious, and that T & M would be reimbursed for its costs through a termination settlement.

The contracting officer stated that mission needs could not have been met under the original contract because the Navy’s estimated usage and the scope of the work had been substantially underestimated, and he pointed out differences in the requirements set forth in the original contract and the second contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

27-35 Jackson Ave LLC v. United States
127 F.4th 1314 (Federal Circuit, 2025)
Nexagen Networks, Inc.
Armed Services Board of Contract Appeals, 2019
Securiforce International America, LLC v. United States
879 F.3d 1354 (Federal Circuit, 2018)
Securiforce International America, LLC v. United States
125 Fed. Cl. 749 (Federal Claims, 2016)
Che Consulting, Inc. v. United States
125 Fed. Cl. 234 (Federal Claims, 2016)
E & E Enterprises Global, Inc. v. United States
120 Fed. Cl. 165 (Federal Claims, 2015)
Two Shields v. United States
119 Fed. Cl. 762 (Federal Claims, 2015)
Tigerswan, Inc. v. United States
118 Fed. Cl. 447 (Federal Claims, 2014)
Handi-Van, Inc. v. Broward County
116 So. 3d 530 (District Court of Appeal of Florida, 2013)
McTech Corporation v. United States
109 Fed. Cl. 28 (Federal Claims, 2013)
Road & Highway Builders, LLC v. United States
702 F.3d 1365 (Federal Circuit, 2012)
Sierra Nevada Corp. v. United States
107 Fed. Cl. 735 (Federal Claims, 2012)
McTech Corp. v. United States
105 Fed. Cl. 726 (Federal Claims, 2012)
Latham v. Board of Education Albuquerque
489 F. App'x 239 (Tenth Circuit, 2012)
Terry v. United States
103 Fed. Cl. 645 (Federal Claims, 2012)
Road & Highway Builders, LLC v. United States
102 Fed. Cl. 88 (Federal Claims, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
185 F.3d 1279, 1999 U.S. App. LEXIS 17030, 1999 WL 538206, Counsel Stack Legal Research, https://law.counselstack.com/opinion/t-m-distributors-inc-v-united-states-cafc-1999.