McTech Corporation v. United States

109 Fed. Cl. 28, 2013 U.S. Claims LEXIS 92, 2013 WL 600360
CourtUnited States Court of Federal Claims
DecidedFebruary 19, 2013
Docket12-222C
StatusPublished

This text of 109 Fed. Cl. 28 (McTech Corporation v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McTech Corporation v. United States, 109 Fed. Cl. 28, 2013 U.S. Claims LEXIS 92, 2013 WL 600360 (uscfc 2013).

Opinion

Pre-award bid protest; series of incremental corrective actions; cumulative effect of actions; mootness

OPINION AND ORDER

LETTOW, Judge.

In this pre-award bid protest, the government has taken a series of incremental steps over a period of months to address the grounds of the protest by plaintiff, MeTech Corporation. The question presented is whether those steps, considered cumulatively, have the effect of redressing McTech’s claims such that McTeeh’s action is moot.

MeTech filed its protest after it had been eliminated from competition for a contract to construct a conference center and dormito *30 ries for the Customs and Border Protection’s Advanced Training Center in Harpers Ferry, West Virginia. MeTech had been an incumbent contractor for other work at the Training Center, but it had not been involved with the design of the new buildings. After having submitted a bid on the new work, McTeeh was disqualified by the contracting officer on the ground that it had a relationship with an entity involved in the design of the project. MeTech challenged its elimination in a protest to the Government Accountability Office (“GAO”) but did not prevail, and subsequently filed suit in this court.

During the course of this litigation, the government slowly, on a step-by-step basis, reversed its elimination of McTeeh from the procurement process and took actions to reconfigure that process. At an earlier midpoint in this litigation, the government had taken a measure of corrective action by eliding MeTeeh’s disqualification, and it then moved to dismiss the action on the mootness grounds. The court denied the government’s motion on the ground that the corrective action taken at that point had not eliminated the possibility of meaningful relief. McTech Corp. v. United States, 105 Fed.Cl. 726 (2012). A “whistleblower” letter then triggered additional review and further actions by the government. Subsequently, after a hearing, the court provided MeTech with a measure of injunctive relief by granting a temporary restraining order that prevented the government from cancelling the original solicitation and resolieiting the procurement until the government explained why transferring decisionmaking to a different office of the United States Army Corps of Engineers (“the Corps”), which oversaw the procurement, would not be sufficient. See Order of November 8, 2012, ECF No. 89. The explanation was submitted and the further corrective action was described in some detail. See Def.’s Notice of Filing Affs. (“Def.’s Notice”) (Nov. 19, 2012), ECF No. 94. Although the government’s actions have been both tortuous and torpid, and occurred on an incremental basis only when driven by necessity or the threat of an adverse result, the sum of the actions has provided MeTech with the relief it sought and removed any prejudice MeTech may have suffered. Consequently, dismissal on grounds of mootness is appropriate.

BACKGROUND

MeTech is a construction company incorporated in Ohio, maintaining its primary place of business in Cleveland, Ohio. Am. Compl. ¶¶ 1-2. The solicitation at issue was being conducted by the Corps through its Fort Worth District Office on behalf of the Department of Homeland Security, Customs and Border Protection. See Am. Compl. ¶¶ 3-4. Request for Proposal No. W9126G-11-0128 (“the Solicitation”) was issued on August 29, 2011. Id. It solicited offers for the construction of a conference center and dormitory at Customs and Border Protection’s Advanced Training Center in Harpers Ferry, West Virginia. McTech, 105 Fed.Cl. at 727-28. MeTech timely submitted an offer in response to the Solicitation. Am. Compl. ¶ 6.

Prior to any award, MeTech was notified that the Corps had become concerned about a potential conflict of interest regarding McTech’s relationship with another entity, BrooAlexa Design Joint Venture, LLC, which was involved in the design of the Har-pers Ferry project. Am. Compl. ¶¶ 7, 31-40. This concern was reportedly prompted by an anonymous phone call to the contract specialist assigned to the solicitation. See McTech, 105 Fed.Cl. at 728. McTech responded to the notice by denying the existence of any conflict and providing the Corps with additional documentation as requested. Id. Nonetheless, the Corps’ contracting officer concluded that either an actual or potential conflict existed and disqualified McTech from the competition for the award. Id.

After McTeeh failed to obtain relief in a pre-award bid protest to GAO, 1 it filed the present action in this court. MeTech sought relief in the form of a permanent injunction against the Corps, prohibiting any award un *31 der the Solicitation until McTeeh had been reinstated and the Corps had conducted a proper conflict analysis of all offerors participating in the acquisition. Am. Compl. ¶ 123.

The Corps’ incremental steps to provide elements of corrective relief have occurred over a seven-month period. On April 24, 2012, the government filed a notice of corrective action, stating that it intended to withdraw its letters disqualifying McTeeh from the competition for an award and to reinstate McTeeh to the pool of eligible bidders. Def.’s Notice of Corrective Action, ECF No. 31. On May 4, 2012, the Corps wrote to all offerors, inquiring about their relationships with BrooAlexa LLC, BrooAlexa Design Joint Venture LLC and Perspeetus Architecture, but it failed to ask about relationships with any of the other six entities that were also identified as working on the design or providing cost estimates for the construction project. See Am. Compl, Attach. 9. On May 31, 2012, the Corps amended the Solicitation and reassigned administrative and contract duties to officials in the Fort Worth District Office other than those who had originally disqualified McTeeh. See Am. Compl., Attach. 10. On June 1, 2012, McTeeh amended its complaint in light of these measures. In the amended complaint, McTeeh requested equitable relief in the form of a new “source selection authority,” direction for the Corps to perform a proper conflict analysis of the offerors, a determination that McTeeh had and has no conflict related to BrooAlexa Design Joint Venture LLC, reinstatement of McTeeh in the competition, and a permanent injunction prohibiting the Corps from using the Fort Worth District Office on this procurement. Am. Compl. ¶ 123.

In August 2012, the court received an ex parte “whistleblower” letter. This letter was disclosed to the parties at a hearing held on August 22, 2012. The letter contained detailed allegations that particular members of the Fori Worth District Office had taken improper actions in managing the Solicitation. Hr’g Tr. (sealed) (Aug. 22, 2012). The letter raised the specter of bias against McTeeh on the pari of certain (if not all) members of the Corps’ procurement officials in the Fort Worth Distinct Office. Id. In September, partially responding to these allegations, the Corps replaced all key procurement personnel associated with the Solicitation, concluded its investigation of McTeeh, and declared McTeeh eligible to compete for the award. See Def.’s Resp. in Opp’n to Pl.’s Mot. to Compel Produe. of the Admin. Record (Sept.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. W. T. Grant Co.
345 U.S. 629 (Supreme Court, 1953)
Powell v. McCormack
395 U.S. 486 (Supreme Court, 1969)
Hall v. Beals
396 U.S. 45 (Supreme Court, 1969)
County of Los Angeles v. Davis
440 U.S. 625 (Supreme Court, 1979)
Princeton University v. Schmid
455 U.S. 100 (Supreme Court, 1982)
T & M Distributors, Inc. v. United States
185 F.3d 1279 (Federal Circuit, 1999)
McTech Corp. v. United States
105 Fed. Cl. 726 (Federal Claims, 2012)
Kalvar Corp. v. United States
543 F.2d 1298 (Court of Claims, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
109 Fed. Cl. 28, 2013 U.S. Claims LEXIS 92, 2013 WL 600360, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mctech-corporation-v-united-states-uscfc-2013.